Project Report: Lounge Event at QA Higher Education, London

Verified

Added on  2023/01/18

|19
|3128
|37
Report
AI Summary
This report details the project management of a lounge event organized by QA Higher Education to attract students after refurbishing its classrooms and labs. It begins with a Project Initiation Document (PID) outlining the project's background, budget, timescale, objectives, and key staff. The report then presents a stakeholder analysis, identifying various stakeholders and their interests. A Work Breakdown Structure (WBS) is provided, breaking down the project into tasks, durations, and dependencies. The report also includes a risk management and analysis section, identifying potential technical, HR, financial, and other risks, along with mitigation strategies. The importance of leadership and various project management methodologies are discussed, concluding with a summary of the project's key elements and successful completion.
Document Page
Lounge event 1
1
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Table of Contents
INTRODUCTION...........................................................................................................................3
TASK 1............................................................................................................................................3
a) Project initiation document......................................................................................................3
TASK 2............................................................................................................................................6
Work break down structure.........................................................................................................6
TASK 3............................................................................................................................................8
Risk management and analysis....................................................................................................8
TASK 4..........................................................................................................................................13
a) Importance of leadership.......................................................................................................13
b) Methodologies.......................................................................................................................13
CONCLUSION..............................................................................................................................15
REFERENCES..............................................................................................................................16
2
Document Page
INTRODUCTION
Project management refers to planning, organising, completing, activities and task in order
to attain specific goals and objectives. It also includes many significant components like time
scale, budget, risk, etc. that are defined by project manager. The project manager is responsible
for overall undertaking and completion of project (Kermanshachi, and et.al., 2016). Here,
current project is based on QA higher education. They have furnished computer labs and other
rooms. Thus, a lounge event is organised in order to attract more students. In this assignment it
will describe about PID. Moreover, how stakeholder role is crucial in project. In addition, several
methodologies of project will be described in it. Furthermore, types of risks are identified that
can occur in event.
TASK 1
a) Project initiation document
For every project it is necessary to develop a PID. This is because it is crucial components
in project management. It gives insight about what activities are to be followed. Moreover, it
helps manager to develop strategies that how project has to be completed. Thus, in QA higher
education they are planning to organise a lounge event to attract students. Furthermore, main
purpose is to provide high quality teaching environment with advance facilities to students.
Therefore, the PID of event is as follows :-
Project title
Launching of lounge event in QA higher education to attract students in university and
celebrate success of project (Sperry, and Jetter, 2019).
Background
QA higher education is a university located in London and has completed refurbishment
of classrooms and labs. The purpose is to provide high quality learning environment to them.
Budgetary information –
In project it is necessary to estimate budget so that resources are allocated in proper way.
Also, it gives insight about costs and expenses that can incur in event. Alongside, manager is
able to identify sources of funds by determining actual requirement of project. In current project
the budget required is as follows :-
Requirement Cost
3
Document Page
Cost of venue €10000
Catering services €7500
Security €5000
Transport €12000
Marketing €5000
Other materials €8000
Total €47500
Timescale
It is also a crucial element in project for its completion. The manager develop schedule
on basis of task. Through it, starting and ending time of each activity is identified. Thus,
according task are allocated and monitoring is done. If any activity is not completed on time than
it results in delaying further task in project. For organising lounge event the time required will be
1 month.
Objectives
They are those aims and goals that is required to be attained in project. The manager has
to define specific objective so that they are attained and project is successful. Furthermore, on
basis of objective the outcomes depend. If they are not set or defined according to project then it
can result in failure (Sanchez, and Terlizzi, 2017). The objective of project is to organise lounge
event for refurbishment of QA higher education computer labs. Another goal is to launch event
to attract student.
Approach
It is important for manager to make sure that team members are engaged in project. In
addition, the tasks in project are proceeded in systematic way. It benefits in ensuring that all
activities goals are achieved. However, selection of approach depends on project manager and
type of project. Generally, there are different methodologies that are followed which is agile,
PRINCE, etc. It is useful in completion of project in deadline.
Key staff
4
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
A project required experienced and qualified staff to perform activities. Each of them is
assigned different role and contribute in project. So, in recent event there are number of staff
which is required like event manager, quality executive, etc.
Stakeholder analysis -
There are many stakeholders in project that support in decision making. Also, they
provide relevant data and info as well. The manager needs to identify interest of stakeholder so
that their needs are fulfilled. In organising lounge event there are many stakeholders that is as
follows :- (Lee and et.al., 2015)
Stakeholder Interest Impact Priority
Technical team They are responsible
for technical
installation and
making it more
advanced.
High 2
Financial team They are responsible
for allocating funds
and managing cash
flow smoothly.
Moderate 2
Event sponsor They are responsible
for providing funds to
organize event.
High 1
Students They need to get
advance technologies
so that they can get
good learning
environment.
Moderate 4
Event manager Individual has interest
to complete this event
within specified time
and cost.
High 1
5
Document Page
Media They are involved in
board casting and
marketing of event.
Moderate 2
Local council The government will
grant permission to
college for organizing
event
High 1
Volunteers They are those who
are responsible for
managing overall
event activities.
High 2
Public They need to watch
event activities
Low 3
TASK 2
Work break down structure
Task Name Duration
Planning 9 days
Forming objectives 2 days
Conducting meeting 3 days
Draft event program 2 days
6
Document Page
Report 2 days
Inviting students 10 days
Preparing guest list 5 days
Sending invitation 3 days
Taking feedback 2 days
Technical and research 4 days
Research and development 2 days
Implementing techniques 2 days
Program 14 days
Planning draft 3 days
Guest confirmation 2 days
Managing accommodation 7 days
Confirm program
2 days
Catering 4 days
Designing menu 2 days
7
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Selecting items 2 days
Communication 6 days
Invitation print 2 days
Promotion of event 4 days
closure 1 day
End of event 1 day
Task Name Duration Start Finish Predecessors
Planning 9 days Mon 12/2/19 Thu 12/12/19
Forming objectives 2 days Mon 12/2/19 Tue 12/3/19
Conducting meeting 3 days Wed 12/4/19 Fri 12/6/19 2
Fdraft even program 2 days Mon 12/9/19 Tue 12/10/19 3
Report 2 days Wed
12/11/19 Thu 12/12/19 4
Inviting students 10 days Wed
12/11/19 Tue 12/24/19
preparing guest list 5 days Wed
12/11/19 Tue 12/17/19 4,2
sending invitation 3 days Wed
12/18/19 Fri 12/20/19 7
taking feedback 2 days Mon
12/23/19 Tue 12/24/19 8,2,3
technical and research 4 days Wed
12/25/19
Mon
12/30/19
research and
development 2 days Wed
12/25/19 Thu 12/26/19 9
implementing
techniques 2 days Fri 12/27/19 Mon
12/30/19 11
8
Document Page
program 14 days Tue 12/31/19 Fri 1/17/20
planning draft 3 days Tue 12/31/19 Thu 1/2/20 12
guest confirmation 2 days Fri 1/3/20 Mon 1/6/20 14
managing
accomodation 7 days Tue 1/7/20 Wed 1/15/20 14,15
confirm progam 2 days Thu 1/16/20 Fri 1/17/20 16
catering 4 days Mon 1/20/20 Thu 1/23/20
design menu 2 days Mon 1/20/20 Tue 1/21/20 17
selecting items 2 days Wed 1/22/20 Thu 1/23/20 19
communication 6 days Fri 1/24/20 Fri 1/31/20
invitation print 2 days Fri 1/24/20 Mon 1/27/20 20
promotion of event 4 days Tue 1/28/20 Fri 1/31/20 22
closure 1 day? Mon 2/3/20 Mon 2/3/20 23
end of event 1 day Tue 2/4/20 Tue 2/4/20 24
9
Document Page
10
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
TASK 3
Risk management and analysis
In a project there are many risks that can occur. The impact of risk depends on its level and
type of risk. So, it is necessary for project manager to identify risk and mitigate its impact. This
is because it enables in completion of project in effective way. Beside this, risk register is
beneficial in finding out areas where risk can occur and what measures can be taken. Thus, in
QA higher education the risks are described below :-
Technical risk- it is major risk that can occur. Here, in evet technical issues may occur that can
lead to failure of compute systems. So, due to this time and cost can increase as well. It can
impact on project completion. (Daniel, and Daniel, 2018)
HR risk – This risk can also occur in event. It might be possible that the skilful and qualified
staff is not available for event. Due to it, tasks are not completed in specified time. Moreover,
staff can leave event in between and do not finish their work in time.
Financial risk – This is crucial risk that can occur in event. There are high chances that a project
may require more budget as estimated. So, it might become difficult for manager to allocate
resources and complete project in given time. In event its cost can rise due to lack funds or any
other problem. It can impact on project to a great extent.
Scope risk – It is risk that can occur as event might not be successful and is not able to attract
large number of students and people.
11
Document Page
Legal – It might be possible that the permission is to granted by government to organise event. in
this case the event will not happen.
Environmental - it is a risk that is most critical. During an event it might be possible that
environment may get worse. Furthermore, natural disaster can occur during event. This can lead
to critical consequences at site. (Willems, and Vanhoucke, 2015)
Transportation risk – This risk can occur if transportation services are not available. So, it will
restrict people to reach event on time.
No Risk Risk
owner
Or
respon
sible
person
Likelihoo
d
Impact Mit
igat
ing
Contingenc
y action
Pre-weighting
score
Post-
weightin
g score
Risk
scor
e
1 Tech
nical
risk
Projec
t
manag
er,
techni
cal
manag
er
Moderate High Technical
manager and
project
manager
should
monitor task
time to time
and have to
ensure correct
machines are
being
installed.
Testing
of each
machine
should be
on time.
5 3 15
2 Hum
an
reso
urce
Projec
t
manag
er
High High Project
manager
should give
training to
Close
monitori
ng and
controllin
5 4 20
12
chevron_up_icon
1 out of 19
circle_padding
hide_on_mobile
zoom_out_icon
[object Object]