This project management assignment presents a comprehensive case study on the development of a rostering system for the Riverina Agricultural and Lifestyle Show (RALS). The project addresses the need for a volunteer management system to replace manual techniques, detailing the Measurable Organizational Value (MOV) in terms of customer satisfaction, strategic alignment, financial benefits, social impact, and operational efficiency. The assignment includes a scope management plan, resource allocation, project schedule with a Gantt chart, and a Work Breakdown Structure (WBS). Furthermore, it details a risk analysis and mitigation plan, addressing potential challenges like budget constraints and time management. A quality management plan outlines strategies for delivering a high-quality system. The project also provides a detailed project schedule, WBS, and milestone completion dates for the RALS rostering system, along with risk assessment and mitigation strategies. The project also includes the project assumptions like budget, time, schedule and resources. Overall, the assignment provides a thorough exploration of project management principles and their application in a real-world scenario.
Document Page
Running head: PROJECT MANAGEMENT
Topic- Project Management
Case Study-RALS Fostering System
Name of the Student
Name of the University
Author’s Note
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
1
PROJECT MANAGEMENT
Table of Contents
1.0 Introduction................................................................................................................................3
2.0 Measurable Organizational Value (MOV)................................................................................3
2.1 Desired area of Impact...........................................................................................................3
2.2 Value of project plan.............................................................................................................4
2.3 Stakeholder involved in the project work..............................................................................4
2.4 Appropriate timeframe and metric.........................................................................................5
3. Scope management Plan..............................................................................................................6
3.1 Detailed scope of the project.................................................................................................6
3.2 List of resources.....................................................................................................................7
4.0 Project schedule and Work Breakdown structure......................................................................8
4.1 Project schedule for RALS Rostering system.......................................................................8
4.2 Work Breakdown Structure.................................................................................................15
4.3 Milestone of the Project plan...............................................................................................15
5. Project risk analysis and plan....................................................................................................16
5.1 Project assumptions.............................................................................................................16
5.2 Risk Assessment..................................................................................................................17
6. Quality Management Plan.........................................................................................................20
6.1 Philosophy for delivering a quality system to the client......................................................20
6.2 Quality issues.......................................................................................................................20
7. Conclusion.................................................................................................................................22
Bibliography..................................................................................................................................23
Document Page
2
PROJECT MANAGEMENT
1.0 Introduction
The project mainly focuses on “Riverina Agricultual and Lifestyle Show (RALS)
rostering system. It is identified that RALS was a three-day event that displays various types of
agricultural events, local business, farmers as well as lifestyle products. It is found that the show
of RALS is mainly dependent on the volunteers and thus with the expansion of the show in the
recent years the business wants some system for managing the volunteers instead of using
manual techniques. Therefore, in order to manage the volunteers efficiently the management of
the show wants to develop a rostering system.
The report mainly elaborates the measurable organizational value (MOV), scope
management plan, resources, milestones, Gantt chart as well as quality management plan. It is
identified that the show will face number of challenges while progressing with the development
of the rostering system. Thus in order to resolve the issues, the paper also illustrates proper risk
mitigation strategies as well as methods.
2.0 Measurable Organizational Value (MOV)
2.1 Desired area of Impact
The desired area of impact includes:
Customer: The development of RALS rostering system would be helpful for the clients
as the system will be helpful in resolving different types of queries of the client quite easily.
Document Page
3
PROJECT MANAGEMENT
Strategy: It is identified that the development of “RALS rostering System” would be
helpful in tracking various types of information as well as details about the volunteers who are
mainly engaged with the show.
Financial: The rostering system that the show wants to develop for managing the
volunteers would be helpful in providing proper amount of profit to Globex by giving effective
amount of return the investment that is done by the business.
Social: The system is quite helpful in improving the entire procedure of communication
with the clients.
Operational: It is identified that with the implementation of the rostering system all the
details of the volunteers can be found quite easily as the operation by the business becomes less
time consuming and in addition to this, the utilization of system reduces human error.
2.2 Value of project plan
The value of the project plan is elaborated below:
Better: It is found that the new system is helpful in providing better services to both the
volunteers as well as clients in comparison to manual system. In addition to this, it is found that
the system would be helpful in securing the system.
Cheaper: With the implementation of the rostering system by the show, the costs that are
associated with the resources as well as operation generally reduce.
Faster: The system is quite advantageous in improving response time of both the
volunteers as well as the clients.
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
4
PROJECT MANAGEMENT
2.3 Stakeholder involved in the project work
The table below reflects the stakeholders who are mainly involved with the entire project
plan:
Keep satisfied
Globex CEO
Manage closely
Project Team
Monitor
RALS Volunteers
Keep Informed
Staffs who are engaged with
volunteers detail
2.4 Appropriate timeframe and metric
Rank Impact Metrics Timeframe
1 Operational It assist in making the
business operation
3 months
Interest
Power
Document Page
5
PROJECT MANAGEMENT
very much less time
consuming
2 Strategy It helps in tracking
the various details of
the volunteers
1 month
3 Customer It helps in reducing
the response time.
2 months
4 Social It helps in improving
the interaction with
different volunteers
5who are mainly
engaged with RALS
3 months
5. Financial It assists in reducing
the operational cost
by 20%.
5 months
3. Scope management Plan
3.1 Detailed scope of the project
The detailed scope of the project is provided below:
Requirements: The main function of the system is to enter information about the
volunteers who are mainly engaged with the RAILS. The system that is proposed has the
capability of tracking the volunteers by utilizing their personal details.
Document Page
6
PROJECT MANAGEMENT
In scope as well as out scope items:
In scope: The system that was proposed is helpful in keeping the details of the volunteers
who are mainly engaged with RAILS including information about name, contact, details,
qualification, certificate and more on behalf of time, days, rotator, ICV and more It also assists in
documenting all the non-functional as well as functional requirements.
Out Scope: It assists in providing proper training to the different workers of Globex for
using the system. System maintenance is very much needed for including both data security as
well as quality of service.
Deliverables: The deliverables of the project plan are as follows:
1. Providing detailed report on the requirements of the system
2. Test plan report for testing the system
3. Proper documentation of both non-functional as well as functional of RALS
4. Documentation of development phase
5. Document for the budget plan
6. Providing training document
Procedure of scope verification: The acceptance criteria of the system are meeting the
different demands as well as needs of the client. It also assists in reducing the response time of
the clients for providing instant solution to different queries.
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7
PROJECT MANAGEMENT
3.2 List of resources
The person who are mainly engaged with the project “development of RALS rostering
system” include business analyst, system developer, investment manager, system tester, risk
analyzer as well as project manager.
Resource
Name
Type
Materia
l Label
Initial
s
Grou
p
Max.
Units
Std. Rate
Ovt.
Rate
Cost/
Use
Accrue
At
Base
Calendar
Project
Manager
Work P 100%
$200.00/
hr
$0.00/hr $0.00
Prorate
d
Standard
Investment
Manager
Work I 100%
$100.00/
hr
$0.00/hr $0.00
Prorate
d
Standard
Project
Sponsor
Work P 100%
$120.00/
hr
$0.00/hr $0.00
Prorate
d
Standard
System
Analyst
Work S 100%
$150.00/
hr
$0.00/hr $0.00
Prorate
d
Standard
System
Developer
Work S 100%
$100.00/
hr
$0.00/hr $0.00
Prorate
d
Standard
Risk
Analyzer
Work R 100% $90.00/hr $0.00/hr $0.00
Prorate
d
Standard
Business
Analyst
Work B 100%
$100.00/
hr
$0.00/hr $0.00
Prorate
d
Standard
System
Tester
Work S 100% $80.00/hr $0.00/hr $0.00
Prorate
d
Standard
Document Page
8
PROJECT MANAGEMENT
Technology: For installing the new RALS system in Globes, the business requires
hardware as well as software devices, which include CPU, operating system, secondary storage,
display adapter and many more.
4.0 Project schedule and Work Breakdown structure
4.1 Project schedule for RALS Rostering system
WBS Task Name Duration Start Finish Resources
0 RALS Rostering System 155 days Mon
9/25/17
Fri
4/27/18
1 Initialization as well as
conceptualization of project
28 days Mon
9/25/17
Wed
11/1/17
1.1 Development of project
plan and charter
10 days Mon
9/25/17
Fri
10/6/17
1.1.1 Business requirements
identification
2 days Mon
9/25/17
Tue
9/26/17
Project Manager
1.1.2 Project specification
utilization
3 days Wed
9/27/17
Fri 9/29/17 Business
Analyst, Project
Manager
1.1.3 Meeting with project
plan
5 days Mon
10/2/17
Fri 10/6/17 Business
Analyst, Project
Manager,
Project Sponsor
Document Page
9
PROJECT MANAGEMENT
1.2 Appointment of vendor 18 days Mon
10/9/17
Wed
11/1/17
1.2.1 Vendor identification 2 days Mon
10/9/17
Tue
10/10/17
Project
Manager,
System
Developer
1.2.2 Analyzing the capability
of vendor
4 days Wed
10/11/17
Mon
10/16/17
Business
Analyst, Project
Manager
1.2.3 Budget planning 5 days Tue
10/17/17
Mon
10/23/17
Investment
Manager,
Project
Manager,
Project Sponsor
1.2.4 Planning the entire time
for completing the project
7 days Tue
10/24/17
Wed
11/1/17
Business
Analyst, Project
Manager
1.2.5 Milestone: Initialization
as well as conceptualization
completion
0 days Wed
11/1/17
Wed
11/1/17
2 Rostering system design
phase
19 days Thu
11/2/17
Tue
11/28/17
2.1 Labour management
improvement
2 days Thu
11/2/17
Fri 11/3/17 Project Manager
2.2 Procedure installation 3 days Mon Wed Project
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
10
PROJECT MANAGEMENT
improvement 11/6/17 11/8/17 Manager,
System
Developer
2.3 Initiation of building the
system
6 days Thu
11/9/17
Thu
11/16/17
Project Sponsor,
System Analyst
2.4 System requirements
understanding
8 days Fri
11/17/17
Tue
11/28/17
Project
Manager,
System Analyst,
System
Developer
2.5 Milestone: Rostering
system design phase
completion
0 days Tue
11/28/17
Tue
11/28/17
3 Rostering system
implementation system
36 days Wed
11/29/17
Wed
1/17/18
3.1 Implementing the system
as per goals
9 days Wed
11/29/17
Mon
12/11/17
Project
Manager,
System Analyst
3.2 Modification within the
implementation phase
8 days Tue
12/12/17
Thu
12/21/17
System Analyst,
System
Developer
3.3 Resources as well as
equipments requirement
10 days Fri
12/22/17
Thu 1/4/18 Project Manager
3.4 Equipment verification 9 days Fri 1/5/18 Wed
1/17/18
System Analyst,
System
Document Page
11
PROJECT MANAGEMENT
Developer,
System Tester
3.5 Milestone: Rostering
system implementation
system completion
0 days Wed
1/17/18
Wed
1/17/18
4 Testing phase 34 days Thu
1/18/18
Tue 3/6/18
4.1 Initiation of testing phase 4 days Thu
1/18/18
Tue
1/23/18
System
Developer,
System Tester
4.2 Reporting the test plan 30 days Wed
1/24/18
Tue 3/6/18
4.2.1 Reviewing the test plan 6 days Wed
1/24/18
Wed
1/31/18
System Analyst,
System Tester
4.2.2 Carrying out the entire
test plan
8 days Thu 2/1/18 Mon
2/12/18
System Analyst,
System
Developer
4.2.3 Test result analyze 7 days Tue
2/13/18
Wed
2/21/18
System
Developer,
System Tester
4.2.4 Test result presentation
to the client
9 days Thu
2/22/18
Tue 3/6/18 System Analyst,
System
Developer,
System Tester
4.2.5 Milestone: Sign off the 0 days Tue 3/6/18 Tue 3/6/18