Project Management for RALS: Online Ticket Booking System Development
VerifiedAdded on  2020/05/28
|25
|3978
|93
Project
AI Summary
This project report details the development of an online ticket booking system for the Riverina Agricultural Lifestyle Show (RALS). The report outlines the project's measurable organizational value (MOV), emphasizing its impact on business strategy, consumers, finance, operations, and social aspects. It includes a scope management plan, detailing project resources and their responsibilities. A comprehensive project schedule, work breakdown structure (WBS), and resource identification are provided, along with cost estimations and a Gantt chart illustrating the project timeline. The report further addresses project risk analysis, quality management, and a closure checklist, ensuring a structured approach to project completion. The project's goal is to transition from manual to an advanced online ticket booking system to improve efficiency and consumer satisfaction.

Running head: RIVERINA AGRICULTURAL LIFESTYLE SHOW (RALS)
Project management: Riverina Agricultural Lifestyle Show (RALS)
Name of the student:
Name of the university:
Project management: Riverina Agricultural Lifestyle Show (RALS)
Name of the student:
Name of the university:
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1RIVERINA AGRICULTURAL LIFESTYLE SHOW (RALS)
Table of Contents
Project overview..............................................................................................................................3
Part 1: Measurable organizational value..........................................................................................3
1.1 Desired area of impact...........................................................................................................3
1.2 Identification of project values..............................................................................................5
1.3 Appropriate project metrics development.............................................................................6
1.4 Timeframe for the RALS project...........................................................................................7
1.5 Summary of MOV project...................................................................................................13
Part 2: Development of scope management plan..........................................................................13
2.1 List of project scope.............................................................................................................13
2.2 List of project resources.......................................................................................................13
2.3 Project resource details........................................................................................................14
Part 3: Project schedule and Work Breakdown Structure.............................................................14
3.1 Work Breakdown Structure.................................................................................................14
3.2 Activities of RALS project..................................................................................................15
3.3 Project resource identification.............................................................................................17
3.4 Cost estimation for RALS project.......................................................................................19
3.5 Time allotted for RALS project...........................................................................................19
Part 4: Project risk analysis and planning......................................................................................22
4.1 Developing project risk management..................................................................................22
Part 5: Quality management plan..................................................................................................24
5.1 Team philosophy for the RALS project...............................................................................24
5.2 Quality assurance.................................................................................................................24
Part 6: Closure checklist development..........................................................................................25
6.2 Outlining the project closure plan........................................................................................25
Annotated Bibliography.................................................................................................................26
References......................................................................................................................................28
Table of Contents
Project overview..............................................................................................................................3
Part 1: Measurable organizational value..........................................................................................3
1.1 Desired area of impact...........................................................................................................3
1.2 Identification of project values..............................................................................................5
1.3 Appropriate project metrics development.............................................................................6
1.4 Timeframe for the RALS project...........................................................................................7
1.5 Summary of MOV project...................................................................................................13
Part 2: Development of scope management plan..........................................................................13
2.1 List of project scope.............................................................................................................13
2.2 List of project resources.......................................................................................................13
2.3 Project resource details........................................................................................................14
Part 3: Project schedule and Work Breakdown Structure.............................................................14
3.1 Work Breakdown Structure.................................................................................................14
3.2 Activities of RALS project..................................................................................................15
3.3 Project resource identification.............................................................................................17
3.4 Cost estimation for RALS project.......................................................................................19
3.5 Time allotted for RALS project...........................................................................................19
Part 4: Project risk analysis and planning......................................................................................22
4.1 Developing project risk management..................................................................................22
Part 5: Quality management plan..................................................................................................24
5.1 Team philosophy for the RALS project...............................................................................24
5.2 Quality assurance.................................................................................................................24
Part 6: Closure checklist development..........................................................................................25
6.2 Outlining the project closure plan........................................................................................25
Annotated Bibliography.................................................................................................................26
References......................................................................................................................................28

2RIVERINA AGRICULTURAL LIFESTYLE SHOW (RALS)
Project overview
This paper defines the importance of development of new online ticket booking system
for delivery as per the expectation of the owners and to meet the requirements of the consumers.
The online ticket booking system is arranged for Riverina agriculture lifetime Show (RALS)
organized by the local business named as Virtucon and Globex Company. A show for 3 days has
been arranged by Globex Company to make discussion about the agriculture equipments,
suppliers and about the other lifetime products. In order to make the show successful and
beneficial from the business and consumers perspectives it is necessary to deal accurately with
the liver program display, volunteers and catering services as well.
The concepts for this show was generated the year of 2000 and from that time onwards
the show us being carried out by the company. In order to reduce the work pressure from the
members associated to the project a Measurable Organizational Value (MOV), time schedule and
Work Breakdown Structure (WBS) is also developed which is elaborated in this report. Apart
from this, a scope management plan, project risk management and a professional quality
management plan is also illustrated in this report.
Part 1: Measurable organizational value
1.1 Desired area of impact
Desired area for
MOV
Ranking Frequency Impact
Strategies 1 Very high Business strategy is referred to as the most
important things to gain measurable
Project overview
This paper defines the importance of development of new online ticket booking system
for delivery as per the expectation of the owners and to meet the requirements of the consumers.
The online ticket booking system is arranged for Riverina agriculture lifetime Show (RALS)
organized by the local business named as Virtucon and Globex Company. A show for 3 days has
been arranged by Globex Company to make discussion about the agriculture equipments,
suppliers and about the other lifetime products. In order to make the show successful and
beneficial from the business and consumers perspectives it is necessary to deal accurately with
the liver program display, volunteers and catering services as well.
The concepts for this show was generated the year of 2000 and from that time onwards
the show us being carried out by the company. In order to reduce the work pressure from the
members associated to the project a Measurable Organizational Value (MOV), time schedule and
Work Breakdown Structure (WBS) is also developed which is elaborated in this report. Apart
from this, a scope management plan, project risk management and a professional quality
management plan is also illustrated in this report.
Part 1: Measurable organizational value
1.1 Desired area of impact
Desired area for
MOV
Ranking Frequency Impact
Strategies 1 Very high Business strategy is referred to as the most
important things to gain measurable
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3RIVERINA AGRICULTURAL LIFESTYLE SHOW (RALS)
success from any project. With the help of
project strategies the Globex Company
would be able to gain competitive
advantages and profit at the same time.
Consumers 2 High For any business organization, consumers
are very important asset. In order to satisfy
them the company is required to develop
the system focusing the requirements of the
consumers. Therefore during the
development of the online ticket booking
system the developer should reduce the
level of complexity and must make the
system user friendly.
Financial 3 High In order to meet the requirement of the
consumers, exact amount of capital
investment is necessary. Due to
inappropriate capital investment, the
company might fail to meet the aim and
goal of the project. Therefore, in the project
initiation phase the finance manager should
make a feasibility to make sure about the
total investment and expected outcome.
Operation 4 High In order to grab more number of consumers
success from any project. With the help of
project strategies the Globex Company
would be able to gain competitive
advantages and profit at the same time.
Consumers 2 High For any business organization, consumers
are very important asset. In order to satisfy
them the company is required to develop
the system focusing the requirements of the
consumers. Therefore during the
development of the online ticket booking
system the developer should reduce the
level of complexity and must make the
system user friendly.
Financial 3 High In order to meet the requirement of the
consumers, exact amount of capital
investment is necessary. Due to
inappropriate capital investment, the
company might fail to meet the aim and
goal of the project. Therefore, in the project
initiation phase the finance manager should
make a feasibility to make sure about the
total investment and expected outcome.
Operation 4 High In order to grab more number of consumers
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4RIVERINA AGRICULTURAL LIFESTYLE SHOW (RALS)
the project manager should initially make
sure that the system is operating as per the
expectation. If it is found that, after
implementation it fails to meet the
functional and operational need then, the
operational ability of the company will be
interrupted.
Social 5 Medium Social support is another important thing
which defines the project success and other
operational criteria collectively. Again
support from the social media is also
required to implement the programs
sequentially.
1.2 Identification of project values
The project values must consider the following elements to ensure that the project is
beneficial.
Better: It is expected that the online ticket booking system will reduce the queue size of
the consumers and also will deliver on time service to the consumers with security and user
friendly application.
Faster: Considering the functional and operational ability of the online ticket booking
system, it is found that, it is faster than the manual ticket booking system.
the project manager should initially make
sure that the system is operating as per the
expectation. If it is found that, after
implementation it fails to meet the
functional and operational need then, the
operational ability of the company will be
interrupted.
Social 5 Medium Social support is another important thing
which defines the project success and other
operational criteria collectively. Again
support from the social media is also
required to implement the programs
sequentially.
1.2 Identification of project values
The project values must consider the following elements to ensure that the project is
beneficial.
Better: It is expected that the online ticket booking system will reduce the queue size of
the consumers and also will deliver on time service to the consumers with security and user
friendly application.
Faster: Considering the functional and operational ability of the online ticket booking
system, it is found that, it is faster than the manual ticket booking system.

5RIVERINA AGRICULTURAL LIFESTYLE SHOW (RALS)
Cheaper: The online ticket booking system automatically reduces the cost because in
this approach the number of both the operators and the manpower get reduce.
1.3 Appropriate project metrics development
In order to meet the requirement of the project, proper metrics are needed to be developed
by the project head. Followings are the metrics for project development:
Stakeholder Stakeholder’s Expectation
Project manager The project manager is expecting the complete
the project within estimated time and budget.
Project sponsors The project sponsors are expected to invest as
per the project requirements.
HR manager The HR manager is needed to manage all
project team members.
Operational manger The expectation of the operation manager is to
develop the system in such a way so that it
could operate accurately.
Finance manager The finance manager expects to develop the
online ticket booking system within the
estimated cost or budget.
System developer The system developer expects to develop the
online ticket booking system considering the
leading system requirements.
Business analyst Expects to develop the system considering the
Cheaper: The online ticket booking system automatically reduces the cost because in
this approach the number of both the operators and the manpower get reduce.
1.3 Appropriate project metrics development
In order to meet the requirement of the project, proper metrics are needed to be developed
by the project head. Followings are the metrics for project development:
Stakeholder Stakeholder’s Expectation
Project manager The project manager is expecting the complete
the project within estimated time and budget.
Project sponsors The project sponsors are expected to invest as
per the project requirements.
HR manager The HR manager is needed to manage all
project team members.
Operational manger The expectation of the operation manager is to
develop the system in such a way so that it
could operate accurately.
Finance manager The finance manager expects to develop the
online ticket booking system within the
estimated cost or budget.
System developer The system developer expects to develop the
online ticket booking system considering the
leading system requirements.
Business analyst Expects to develop the system considering the
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6RIVERINA AGRICULTURAL LIFESTYLE SHOW (RALS)
basic business strategies.
1.4 Timeframe for the RALS project
WBS Task Name Duration Start Finish Predecessors
Resource
Names
Cost
Variance
0
RALS project
scheduling
125 days
Wed
1/17/18
Tue
7/10/18
$30,088.00
1
Project
initiation phase
43 days
Wed
1/17/18
Fri
3/16/18
$10,792.00
1.1
Conceptualizin
g the project
6 days
Wed
1/17/18
Wed
1/24/18
business
analysts ,P
roject
manager
$1,680.00
1.2
Developing
project charter
4 days
Thu
1/25/18
Tue
1/30/18
2
Operation
manager ,
Project
manager
$1,120.00
1.3
Appointing
vendors
8 days
Wed
1/31/18
Fri 2/9/18 3
Project
manager ,
project
sponsors
$2,432.00
basic business strategies.
1.4 Timeframe for the RALS project
WBS Task Name Duration Start Finish Predecessors
Resource
Names
Cost
Variance
0
RALS project
scheduling
125 days
Wed
1/17/18
Tue
7/10/18
$30,088.00
1
Project
initiation phase
43 days
Wed
1/17/18
Fri
3/16/18
$10,792.00
1.1
Conceptualizin
g the project
6 days
Wed
1/17/18
Wed
1/24/18
business
analysts ,P
roject
manager
$1,680.00
1.2
Developing
project charter
4 days
Thu
1/25/18
Tue
1/30/18
2
Operation
manager ,
Project
manager
$1,120.00
1.3
Appointing
vendors
8 days
Wed
1/31/18
Fri 2/9/18 3
Project
manager ,
project
sponsors
$2,432.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7RIVERINA AGRICULTURAL LIFESTYLE SHOW (RALS)
1.4
Hardware
requirements
collection
5 days
Mon
2/12/18
Fri
2/16/18
4
Operation
manager ,
Project
manager
$1,400.00
1.5
Software
requirements
gathering
6 days
Mon
2/19/18
Mon
2/26/18
5
Operation
manager ,
Project
manager
$1,680.00
1.6
Estimating
project budget
3 days
Tue
2/27/18
Thu
3/1/18
6
finance
manager
$360.00
1.7 Time allotment 5 days Fri 3/2/18
Thu
3/8/18
7
finance
manager,
Project
manager
$1,400.00
1.8
Consideration
of SLA guidelines
6 days Fri 3/9/18
Fri
3/16/18
4,8
Operation
manager
$720.00
2
Milestone 1:
completion of
project initiation
phase
0 days Fri 3/16/18
Fri
3/16/18
9
Project
manager
$0.00
1.4
Hardware
requirements
collection
5 days
Mon
2/12/18
Fri
2/16/18
4
Operation
manager ,
Project
manager
$1,400.00
1.5
Software
requirements
gathering
6 days
Mon
2/19/18
Mon
2/26/18
5
Operation
manager ,
Project
manager
$1,680.00
1.6
Estimating
project budget
3 days
Tue
2/27/18
Thu
3/1/18
6
finance
manager
$360.00
1.7 Time allotment 5 days Fri 3/2/18
Thu
3/8/18
7
finance
manager,
Project
manager
$1,400.00
1.8
Consideration
of SLA guidelines
6 days Fri 3/9/18
Fri
3/16/18
4,8
Operation
manager
$720.00
2
Milestone 1:
completion of
project initiation
phase
0 days Fri 3/16/18
Fri
3/16/18
9
Project
manager
$0.00

8RIVERINA AGRICULTURAL LIFESTYLE SHOW (RALS)
3
Project
planning phase
31 days
Mon
3/19/18
Mon
4/30/18
$5,400.00
3.1
Outlining the
design of the
online ticket
booking system
5 days
Mon
3/19/18
Fri
3/23/18
10
Operation
manager ,s
ystem
developer
$1,200.00
3.2
Collection the
development
elements
6 days
Mon
3/26/18
Mon
4/2/18
12
Operation
manager ,s
ystem
developer
$1,440.00
3.3
Prototype
designing
8 days Tue 4/3/18
Thu
4/12/18
13
system
developer
$960.00
3.4
Prototype
building
3 days Fri 4/13/18
Tue
4/17/18
14
system
developer
$360.00
3.5
Prototype
implementation
12 days Fri 4/13/18
Mon
4/30/18
13,14
system
developer
$1,440.00
4
Milestone 2:
complete project
planning phase
0 days
Mon
4/30/18
Mon
4/30/18
16
Project
manager
$0.00
3
Project
planning phase
31 days
Mon
3/19/18
Mon
4/30/18
$5,400.00
3.1
Outlining the
design of the
online ticket
booking system
5 days
Mon
3/19/18
Fri
3/23/18
10
Operation
manager ,s
ystem
developer
$1,200.00
3.2
Collection the
development
elements
6 days
Mon
3/26/18
Mon
4/2/18
12
Operation
manager ,s
ystem
developer
$1,440.00
3.3
Prototype
designing
8 days Tue 4/3/18
Thu
4/12/18
13
system
developer
$960.00
3.4
Prototype
building
3 days Fri 4/13/18
Tue
4/17/18
14
system
developer
$360.00
3.5
Prototype
implementation
12 days Fri 4/13/18
Mon
4/30/18
13,14
system
developer
$1,440.00
4
Milestone 2:
complete project
planning phase
0 days
Mon
4/30/18
Mon
4/30/18
16
Project
manager
$0.00
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

9RIVERINA AGRICULTURAL LIFESTYLE SHOW (RALS)
5
Online ticket
booking system
testing
39 days Tue 5/1/18
Fri
6/22/18
17 $10,880.00
5.1
System unit
testing
6 days Tue 5/1/18
Tue
5/8/18
Operation
manager
$720.00
5.2
Integration
testing
9 days
Wed
5/9/18
Mon
5/21/18
19
Operation
manager ,
Project
manager ,s
ystem
developer
$3,600.00
5.3
Review the
testing phase
8 days
Tue
5/22/18
Thu
5/31/18
20
Operation
manager ,
Project
manager ,s
ystem
developer
$3,200.00
5.4
Field testing of
the designed
prototype
7 days Fri 6/1/18
Mon
6/11/18
14,21
Operation
manager
$840.00
5.5 Testing result 9 days Tue Fri 22 business $2,520.00
5
Online ticket
booking system
testing
39 days Tue 5/1/18
Fri
6/22/18
17 $10,880.00
5.1
System unit
testing
6 days Tue 5/1/18
Tue
5/8/18
Operation
manager
$720.00
5.2
Integration
testing
9 days
Wed
5/9/18
Mon
5/21/18
19
Operation
manager ,
Project
manager ,s
ystem
developer
$3,600.00
5.3
Review the
testing phase
8 days
Tue
5/22/18
Thu
5/31/18
20
Operation
manager ,
Project
manager ,s
ystem
developer
$3,200.00
5.4
Field testing of
the designed
prototype
7 days Fri 6/1/18
Mon
6/11/18
14,21
Operation
manager
$840.00
5.5 Testing result 9 days Tue Fri 22 business $2,520.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

10RIVERINA AGRICULTURAL LIFESTYLE SHOW (RALS)
analysis 6/12/18 6/22/18
analysts ,P
roject
manager
6
Milestone 3:
complete testing
phase
0 days Fri 6/22/18
Fri
6/22/18
23
Project
manager
$0.00
7 Project closure 12 days
Mon
6/25/18
Tue
7/10/18
$3,016.00
7.1
Stakeholders
signoff
5 days
Mon
6/25/18
Fri
6/29/18
24
HR
manager
$600.00
7.2
Final project
documentation
4 days
Mon
7/2/18
Thu
7/5/18
26
Project
manager ,
project
sponsors
$1,216.00
7.3
Post system
maintenance plan
3 days Fri 7/6/18
Tue
7/10/18
27
business
analysts ,
Operation
manager ,
Project
manager
$1,200.00
8 Milestone 4: 0 days Tue Tue 28 Project $0.00
analysis 6/12/18 6/22/18
analysts ,P
roject
manager
6
Milestone 3:
complete testing
phase
0 days Fri 6/22/18
Fri
6/22/18
23
Project
manager
$0.00
7 Project closure 12 days
Mon
6/25/18
Tue
7/10/18
$3,016.00
7.1
Stakeholders
signoff
5 days
Mon
6/25/18
Fri
6/29/18
24
HR
manager
$600.00
7.2
Final project
documentation
4 days
Mon
7/2/18
Thu
7/5/18
26
Project
manager ,
project
sponsors
$1,216.00
7.3
Post system
maintenance plan
3 days Fri 7/6/18
Tue
7/10/18
27
business
analysts ,
Operation
manager ,
Project
manager
$1,200.00
8 Milestone 4: 0 days Tue Tue 28 Project $0.00

11RIVERINA AGRICULTURAL LIFESTYLE SHOW (RALS)
Completion of
project closure
phase
7/10/18 7/10/18 manager
Figure 1: Gantt chart for RALS
(Source: created by Author)
Completion of
project closure
phase
7/10/18 7/10/18 manager
Figure 1: Gantt chart for RALS
(Source: created by Author)
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 25
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
 +13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024  |  Zucol Services PVT LTD  |  All rights reserved.