ITC505 Project Management Assignment: RALS Ticketing System Analysis
VerifiedAdded on 2020/04/07
|17
|3270
|40
Project
AI Summary
This assignment details the project management of a RALS Ticketing System. It begins with an analysis of Measurable Organizational Value (MOV), ranking strategic, customer, financial, operational, and social impacts, and defining metrics. The assignment then defines the project scope, outlining in-scope and out-of-scope items, deliverables, and acceptance criteria. A detailed resource list, including roles, activities, and costs, is provided. Part three includes a comprehensive project schedule with WBS, task durations, start and finish dates, predecessors, resources, and costs, supported by a Gantt chart and WBS diagram. Finally, the assignment concludes with a risk analysis, identifying potential risks like system failure, over budgeting, and design flaws, along with their descriptions, categories, triggers, potential responses, risk owners, probabilities, impacts, and statuses.

Running head: PROJECT MANAGEMENT
ITC505 Assignment 3 template
Name of the Student:
Student ID:
Name of the University:
Author’s note:
ITC505 Assignment 3 template
Name of the Student:
Student ID:
Name of the University:
Author’s note:
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Part One: MOV - Measurable Organisational Value
• Identify the desired area of impact - Rank the following areas in terms of
importance: Strategy / Customer / Financial / Operational / Social
The desired are of impact are strategy, customer, financial, operational, and social and
they are explained below,
Customer the customer can be understood as the system area of raising various
types of queries raised by the people in relation to the system and project developed
for RALS
Strategy the strategy can be defined for impacting the operations of the project of
RALS by developing some effective and improved operations
Financial the financial system can be explained as the operations of the processes
for the development of the operations for integrating the development of the
operations and implying the completion of the project
Operational the operational processes would be implied for forming the safety of
the operations and its integration of the process for the modification of the processes
of the organization
Social the operational processes would be implied for developing the safety of the
operations and its integration of the processes
1st Financial
2nd Customer
3rd Operational
4th Strategy
5th Social
• With reference to your project, identify one or two of the following types of value:
o Better – The RALS project had seen the development of a new system for
increasing the efficiency of work by information management
o Faster – The RALS project would help in integrating the operations of the
project and development of the increased speed of operations
o Cheaper – The RALS project would help in managing the information on a
single database and hence it would decrease the overall cost of the information
system management
o Do more – The system implementation at RALS would integrate the
information of the RALS and it would help in developing the smarter
processes of the organization.
• Identify the desired area of impact - Rank the following areas in terms of
importance: Strategy / Customer / Financial / Operational / Social
The desired are of impact are strategy, customer, financial, operational, and social and
they are explained below,
Customer the customer can be understood as the system area of raising various
types of queries raised by the people in relation to the system and project developed
for RALS
Strategy the strategy can be defined for impacting the operations of the project of
RALS by developing some effective and improved operations
Financial the financial system can be explained as the operations of the processes
for the development of the operations for integrating the development of the
operations and implying the completion of the project
Operational the operational processes would be implied for forming the safety of
the operations and its integration of the process for the modification of the processes
of the organization
Social the operational processes would be implied for developing the safety of the
operations and its integration of the processes
1st Financial
2nd Customer
3rd Operational
4th Strategy
5th Social
• With reference to your project, identify one or two of the following types of value:
o Better – The RALS project had seen the development of a new system for
increasing the efficiency of work by information management
o Faster – The RALS project would help in integrating the operations of the
project and development of the increased speed of operations
o Cheaper – The RALS project would help in managing the information on a
single database and hence it would decrease the overall cost of the information
system management
o Do more – The system implementation at RALS would integrate the
information of the RALS and it would help in developing the smarter
processes of the organization.

• Develop an appropriate metric - this sets the target and expectation of all the
stakeholders. It is important to determine a quantitative target that needs to be
expressed as a metric in terms of an increase or decrease of money. (4 Bullet Points)
Rank Impact Metrics
1 Financial Cash Profit and Revenue generation
2 Customer Number of customers coming back to the organization for their services
3 Operational Less Consumption of time for the completion of the organizational
operations
4 Strategy The volunteers would get tracked due to the use of the system developed in
RALS
5 Social Volunteers would be able to get socialized with the customers
• Determine the timeframe for achieving the MOV - ask yourselves, when do we want
to achieve this target metric?
• SUMMARISE THE MOV IN A CLEAR CONCISE STATEMENT OR TABLE
Rank Impact Timeframe
1 Financial 6 months
2 Customer 2 months
3 Operational 2 months
4 Strategy 1 month
5 Social 3 months
Part Two:
Define Scope and produce a Scope Management Plan
stakeholders. It is important to determine a quantitative target that needs to be
expressed as a metric in terms of an increase or decrease of money. (4 Bullet Points)
Rank Impact Metrics
1 Financial Cash Profit and Revenue generation
2 Customer Number of customers coming back to the organization for their services
3 Operational Less Consumption of time for the completion of the organizational
operations
4 Strategy The volunteers would get tracked due to the use of the system developed in
RALS
5 Social Volunteers would be able to get socialized with the customers
• Determine the timeframe for achieving the MOV - ask yourselves, when do we want
to achieve this target metric?
• SUMMARISE THE MOV IN A CLEAR CONCISE STATEMENT OR TABLE
Rank Impact Timeframe
1 Financial 6 months
2 Customer 2 months
3 Operational 2 months
4 Strategy 1 month
5 Social 3 months
Part Two:
Define Scope and produce a Scope Management Plan
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Define the scope: The project of RALS Ticketing System development would help in
developing the improvement of the operations of the Globex for tracking customer’s
and volunteer’s information by the help of system developed.
Requirements: The project of RALS would require the following human and
material resources,
S. No. Resource Resource Type
1 Project Manager Human
2 Planner Human
3 Documenter Human
4 Budgeter Human
5 System Analyst Human
6 IT Engineer Human
7 Tester Human
8 Computer Devices Materials
9 Network Components Materials
10 Storage Materials
11 Wireless routers Materials
In scope-out scope items: The in-scope items of the RALS project are plan for the
operations of the project, development of the RALS Ticketing System, increase of
efficiency of the management of the information about volunteers, and assisting for
operational as well as strategic development. The out of scope items of the RALS
project include maintenance activities, delivery of the materials, and training of the
workers in Globex
Deliverables: The deliverables for the RALS project are,
Project Plan and Resource Allocation Plan
Project Documents including Initiation and Charter Documentation
Scope Verification Plan
System Design and Implementation Plan
Testing Results
Acceptance Criteria: The acceptance criteria for the project would comprise of the
following checklist,
Checklist Item Checked
Development of the Project Plan
Optimized Resource Allocation Plan
Signing off the Project Documents including Initiation and Charter Documentation
Effective System Design
Step by step implementation plan
Expected Test results
developing the improvement of the operations of the Globex for tracking customer’s
and volunteer’s information by the help of system developed.
Requirements: The project of RALS would require the following human and
material resources,
S. No. Resource Resource Type
1 Project Manager Human
2 Planner Human
3 Documenter Human
4 Budgeter Human
5 System Analyst Human
6 IT Engineer Human
7 Tester Human
8 Computer Devices Materials
9 Network Components Materials
10 Storage Materials
11 Wireless routers Materials
In scope-out scope items: The in-scope items of the RALS project are plan for the
operations of the project, development of the RALS Ticketing System, increase of
efficiency of the management of the information about volunteers, and assisting for
operational as well as strategic development. The out of scope items of the RALS
project include maintenance activities, delivery of the materials, and training of the
workers in Globex
Deliverables: The deliverables for the RALS project are,
Project Plan and Resource Allocation Plan
Project Documents including Initiation and Charter Documentation
Scope Verification Plan
System Design and Implementation Plan
Testing Results
Acceptance Criteria: The acceptance criteria for the project would comprise of the
following checklist,
Checklist Item Checked
Development of the Project Plan
Optimized Resource Allocation Plan
Signing off the Project Documents including Initiation and Charter Documentation
Effective System Design
Step by step implementation plan
Expected Test results
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Provide a list of Resources
Resource Name Activities
Project Manager Project Meetings
Documents are Signed off
Recruiting Project team
Reviewing the plan
Documents are reviewed
Documents are Signed off
Planner Feasibility Analysis
Identification of the Requirements
Selecting Project Plan methodology
Developing Plan outline
Completing the project plan
Budgeter Developing Project Budget
Material Resources are Ordered
Ordered Materials are Received
System Analyst Analysis of the vendor requirements
Selecting design platform
Developing Design outline
Prototyping the design
Simulation is run on the design
IT Engineer Integrated Storage is developed
Data are transferred to the new storage
Design is used for integrated ticketing system
User Interface is developed
Necessary Functions are coded and programmed
Ticketing system is integrated with the storage
Hardware components are installed
Tester User Interface is tested
Functions are tested
Black box testing
White Box testing
Computer Devices Hardware components are installed
Network Components Ticketing system is integrated with the storage
Storage Integrated Storage is developed
Wireless Routers Hardware components are installed
Resource Name Std. Rate
Project Manager $80.00/hr
Planner $90.00/hr
Resource Name Activities
Project Manager Project Meetings
Documents are Signed off
Recruiting Project team
Reviewing the plan
Documents are reviewed
Documents are Signed off
Planner Feasibility Analysis
Identification of the Requirements
Selecting Project Plan methodology
Developing Plan outline
Completing the project plan
Budgeter Developing Project Budget
Material Resources are Ordered
Ordered Materials are Received
System Analyst Analysis of the vendor requirements
Selecting design platform
Developing Design outline
Prototyping the design
Simulation is run on the design
IT Engineer Integrated Storage is developed
Data are transferred to the new storage
Design is used for integrated ticketing system
User Interface is developed
Necessary Functions are coded and programmed
Ticketing system is integrated with the storage
Hardware components are installed
Tester User Interface is tested
Functions are tested
Black box testing
White Box testing
Computer Devices Hardware components are installed
Network Components Ticketing system is integrated with the storage
Storage Integrated Storage is developed
Wireless Routers Hardware components are installed
Resource Name Std. Rate
Project Manager $80.00/hr
Planner $90.00/hr

Documenter $85.00/hr
Budgeter $90.00/hr
System Analyst $70.00/hr
IT Engineer $75.00/hr
Tester $65.00/hr
Computer Devices $1200.00
Network Components $560.00
Storage $1500.00
Wireless routers $780.00
Part Three:
The table for the project schedule is given below,
WBS Task Name Duration Start Finish Predecessors Resource Names Cost
0 RALS Ticketing
System
138
days
Mon
10/2/17
Wed
4/11/18 $90,000.00
1 Project
Initialization 22 days Mon
10/2/17
Tue
10/31/17 $15,360.00
1.1 Feasibility
Analysis 6 days Mon
10/2/17
Mon
10/9/17 Planner $4,320.00
1.2 Identification of
the Requirements 6 days Tue
10/10/17
Tue
10/17/17 2 Planner $4,320.00
1.3 Project Initiation
Documents 4 days Wed
10/18/17
Mon
10/23/17 3 Documenter $2,720.00
1.4 Charter
Development 4 days Tue
10/24/17
Fri
10/27/17 4 Documenter $2,720.00
1.5 Project Meetings 1 day Mon
10/30/17
Mon
10/30/17 5 Project Manager $640.00
1.6 Documents are
Signed off 1 day Tue
10/31/17
Tue
10/31/17 6 Project Manager $640.00
M1 Project is Initiated 0 days Tue
10/31/17
Tue
10/31/17 7 $0.00
2 Project Resource
Accumulation 24 days Wed
11/1/17
Mon
12/4/17 $15,360.00
2.1 Analysis of the
vendor requirements 7 days Wed
11/1/17
Thu
11/9/17 8 System Analyst $3,920.00
2.2 Recruiting Project
team 10 days Fri
11/10/17
Thu
11/23/17 10 Project Manager $6,400.00
2.3 Developing
Project Budget 3 days Fri
11/24/17
Tue
11/28/17 11 Budgeter $2,160.00
2.4
Material
Resources are
Ordered
1 day Wed
11/29/17
Wed
11/29/17 12 Budgeter $720.00
2.5 Ordered Materials
are Received 3 days Thu
11/30/17
Mon
12/4/17 13 Budgeter $2,160.00
M2 Resources are
Accumulated 0 days Mon
12/4/17
Mon
12/4/17 14 $0.00
3 Project Planning
and Scheduling 12 days Tue
12/5/17
Wed
12/20/17 $8,480.00
3.1 Selecting Project
Plan methodology 1 day Tue
12/5/17
Tue
12/5/17 15 Planner $720.00
3.2 Developing Plan 3 days Wed Fri 17 Planner $2,160.00
Budgeter $90.00/hr
System Analyst $70.00/hr
IT Engineer $75.00/hr
Tester $65.00/hr
Computer Devices $1200.00
Network Components $560.00
Storage $1500.00
Wireless routers $780.00
Part Three:
The table for the project schedule is given below,
WBS Task Name Duration Start Finish Predecessors Resource Names Cost
0 RALS Ticketing
System
138
days
Mon
10/2/17
Wed
4/11/18 $90,000.00
1 Project
Initialization 22 days Mon
10/2/17
Tue
10/31/17 $15,360.00
1.1 Feasibility
Analysis 6 days Mon
10/2/17
Mon
10/9/17 Planner $4,320.00
1.2 Identification of
the Requirements 6 days Tue
10/10/17
Tue
10/17/17 2 Planner $4,320.00
1.3 Project Initiation
Documents 4 days Wed
10/18/17
Mon
10/23/17 3 Documenter $2,720.00
1.4 Charter
Development 4 days Tue
10/24/17
Fri
10/27/17 4 Documenter $2,720.00
1.5 Project Meetings 1 day Mon
10/30/17
Mon
10/30/17 5 Project Manager $640.00
1.6 Documents are
Signed off 1 day Tue
10/31/17
Tue
10/31/17 6 Project Manager $640.00
M1 Project is Initiated 0 days Tue
10/31/17
Tue
10/31/17 7 $0.00
2 Project Resource
Accumulation 24 days Wed
11/1/17
Mon
12/4/17 $15,360.00
2.1 Analysis of the
vendor requirements 7 days Wed
11/1/17
Thu
11/9/17 8 System Analyst $3,920.00
2.2 Recruiting Project
team 10 days Fri
11/10/17
Thu
11/23/17 10 Project Manager $6,400.00
2.3 Developing
Project Budget 3 days Fri
11/24/17
Tue
11/28/17 11 Budgeter $2,160.00
2.4
Material
Resources are
Ordered
1 day Wed
11/29/17
Wed
11/29/17 12 Budgeter $720.00
2.5 Ordered Materials
are Received 3 days Thu
11/30/17
Mon
12/4/17 13 Budgeter $2,160.00
M2 Resources are
Accumulated 0 days Mon
12/4/17
Mon
12/4/17 14 $0.00
3 Project Planning
and Scheduling 12 days Tue
12/5/17
Wed
12/20/17 $8,480.00
3.1 Selecting Project
Plan methodology 1 day Tue
12/5/17
Tue
12/5/17 15 Planner $720.00
3.2 Developing Plan 3 days Wed Fri 17 Planner $2,160.00
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

outline 12/6/17 12/8/17
3.3 Reviewing the
plan 2 days Mon
12/11/17
Tue
12/12/17 18 Project Manager $1,280.00
3.4 Completing the
project plan 6 days Wed
12/13/17
Wed
12/20/17 19 Planner $4,320.00
M3 Project Plan is
approved 0 days Wed
12/20/17
Wed
12/20/17 20 $0.00
4 System Designing 12 days Thu
12/21/17
Fri
1/5/18 $6,720.00
4.1 Selecting design
platform 2 days Thu
12/21/17
Fri
12/22/17 21 System Analyst $1,120.00
4.2 Developing
Design outline 4 days Mon
12/25/17
Thu
12/28/17 23 System Analyst $2,240.00
4.3 Prototyping the
design 4 days Fri
12/29/17
Wed
1/3/18 24 System Analyst $2,240.00
4.4 Simulation is run
on the design 2 days Thu
1/4/18
Fri
1/5/18 25 System Analyst $1,120.00
M4 Complete Design
is developed 0 days Fri
1/5/18
Fri
1/5/18 26 $0.00
5 System
Implementation 44 days Mon
1/8/18
Thu
3/8/18 $30,440.00
5.1 Integrated
Storage is developed 10 days Mon
1/8/18
Fri
1/19/18 27 IT Engineer, Storage
[1] $7,500.00
5.2
Data are
transferred to the new
storage
4 days Mon
1/22/18
Thu
1/25/18 29 IT Engineer $2,400.00
5.3
Design is used for
integrated ticketing
system
3 days Fri
1/26/18
Tue
1/30/18 30 IT Engineer $1,800.00
5.4 User Interface is
developed 5 days Wed
1/31/18
Tue
2/6/18 31 IT Engineer $3,000.00
5.5
Necessary
Functions are coded
and programmed
12 days Wed
2/7/18
Thu
2/22/18 32 IT Engineer $7,200.00
5.6
Ticketing system
is integrated with the
storage
4 days Fri
2/23/18
Wed
2/28/18 33
IT Engineer,
Network
Components[1]
$2,960.00
5.7
Hardware
components are
installed
6 days Thu
3/1/18
Thu
3/8/18 34
IT Engineer,
Computer
Devices[1], Wireless
routers[1]
$5,580.00
M5
System is
implemented ate
Globex
0 days Thu
3/8/18
Thu
3/8/18 35 $0.00
6 Testing Phase 16 days Fri
3/9/18
Fri
3/30/18 $8,320.00
6.1 User Interface is
tested 4 days Fri
3/9/18
Wed
3/14/18 36 Tester $2,080.00
6.2 Functions are
tested 4 days Thu
3/15/18
Tue
3/20/18 38 Tester $2,080.00
6.3 Black box testing 4 days Wed
3/21/18
Mon
3/26/18 39 Tester $2,080.00
6.4 White Box testing 4 days Tue
3/27/18
Fri
3/30/18 40 Tester $2,080.00
M6 Testing Results
are developed 0 days Fri
3/30/18
Fri
3/30/18 41 $0.00
3.3 Reviewing the
plan 2 days Mon
12/11/17
Tue
12/12/17 18 Project Manager $1,280.00
3.4 Completing the
project plan 6 days Wed
12/13/17
Wed
12/20/17 19 Planner $4,320.00
M3 Project Plan is
approved 0 days Wed
12/20/17
Wed
12/20/17 20 $0.00
4 System Designing 12 days Thu
12/21/17
Fri
1/5/18 $6,720.00
4.1 Selecting design
platform 2 days Thu
12/21/17
Fri
12/22/17 21 System Analyst $1,120.00
4.2 Developing
Design outline 4 days Mon
12/25/17
Thu
12/28/17 23 System Analyst $2,240.00
4.3 Prototyping the
design 4 days Fri
12/29/17
Wed
1/3/18 24 System Analyst $2,240.00
4.4 Simulation is run
on the design 2 days Thu
1/4/18
Fri
1/5/18 25 System Analyst $1,120.00
M4 Complete Design
is developed 0 days Fri
1/5/18
Fri
1/5/18 26 $0.00
5 System
Implementation 44 days Mon
1/8/18
Thu
3/8/18 $30,440.00
5.1 Integrated
Storage is developed 10 days Mon
1/8/18
Fri
1/19/18 27 IT Engineer, Storage
[1] $7,500.00
5.2
Data are
transferred to the new
storage
4 days Mon
1/22/18
Thu
1/25/18 29 IT Engineer $2,400.00
5.3
Design is used for
integrated ticketing
system
3 days Fri
1/26/18
Tue
1/30/18 30 IT Engineer $1,800.00
5.4 User Interface is
developed 5 days Wed
1/31/18
Tue
2/6/18 31 IT Engineer $3,000.00
5.5
Necessary
Functions are coded
and programmed
12 days Wed
2/7/18
Thu
2/22/18 32 IT Engineer $7,200.00
5.6
Ticketing system
is integrated with the
storage
4 days Fri
2/23/18
Wed
2/28/18 33
IT Engineer,
Network
Components[1]
$2,960.00
5.7
Hardware
components are
installed
6 days Thu
3/1/18
Thu
3/8/18 34
IT Engineer,
Computer
Devices[1], Wireless
routers[1]
$5,580.00
M5
System is
implemented ate
Globex
0 days Thu
3/8/18
Thu
3/8/18 35 $0.00
6 Testing Phase 16 days Fri
3/9/18
Fri
3/30/18 $8,320.00
6.1 User Interface is
tested 4 days Fri
3/9/18
Wed
3/14/18 36 Tester $2,080.00
6.2 Functions are
tested 4 days Thu
3/15/18
Tue
3/20/18 38 Tester $2,080.00
6.3 Black box testing 4 days Wed
3/21/18
Mon
3/26/18 39 Tester $2,080.00
6.4 White Box testing 4 days Tue
3/27/18
Fri
3/30/18 40 Tester $2,080.00
M6 Testing Results
are developed 0 days Fri
3/30/18
Fri
3/30/18 41 $0.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7 Final Documents 8 days Mon
4/2/18
Wed
4/11/18 $5,320.00
7.1 Final Documents
are made 5 days Mon
4/2/18
Fri
4/6/18 42 Documenter $3,400.00
7.2 Documents are
reviewed 2 days Mon
4/9/18
Tue
4/10/18 44 Project Manager $1,280.00
7.3 Documents are
Signed off 1 day Wed
4/11/18
Wed
4/11/18 45 Project Manager $640.00
M7 Project is Closed 0 days Wed
4/11/18
Wed
4/11/18 46 $0.00
The Gantt chart image for the project is also given below,
4/2/18
Wed
4/11/18 $5,320.00
7.1 Final Documents
are made 5 days Mon
4/2/18
Fri
4/6/18 42 Documenter $3,400.00
7.2 Documents are
reviewed 2 days Mon
4/9/18
Tue
4/10/18 44 Project Manager $1,280.00
7.3 Documents are
Signed off 1 day Wed
4/11/18
Wed
4/11/18 45 Project Manager $640.00
M7 Project is Closed 0 days Wed
4/11/18
Wed
4/11/18 46 $0.00
The Gantt chart image for the project is also given below,

ID Task
Mode
WBS Task Name Duration Start Finish Predecessors Resource Names Cost
0 0 RALS Ticketing System 138 days Mon 10/2/17 Wed 4/11/18 $90,000.00
1 1 Project Intialization 22 days Mon 10/2/17 Tue 10/31/17 $15,360.00
2 1.1 Feasibility Analysis 6 days Mon 10/2/17 Mon 10/9/17 Planner $4,320.00
3 1.2 Identification of the Requirements 6 days Tue 10/10/17 Tue 10/17/17 2 Planner $4,320.00
4 1.3 Project Initiation Documents 4 days Wed 10/18/17 Mon 10/23/17 3 Documenter $2,720.00
5 1.4 Charter Development 4 days Tue 10/24/17 Fri 10/27/17 4 Documenter $2,720.00
6 1.5 Project Meetings 1 day Mon 10/30/17 Mon 10/30/17 5 Project Manager $640.00
7 1.6 Documents are Signed off 1 day Tue 10/31/17 Tue 10/31/17 6 Project Manager $640.00
8 M1 Project is Initiated 0 days Tue 10/31/17 Tue 10/31/17 7 $0.00
9 2 Project Resource Accumulation 24 days Wed 11/1/17 Mon 12/4/17 $15,360.00
10 2.1 Analysis of the vendor requirements 7 days Wed 11/1/17 Thu 11/9/17 8 System Analyst $3,920.00
11 2.2 Recruiting Project team 10 days Fri 11/10/17 Thu 11/23/17 10 Project Manager $6,400.00
12 2.3 Developing Project Budget 3 days Fri 11/24/17 Tue 11/28/17 11 Budgeter $2,160.00
13 2.4 Material Resources are Ordered 1 day Wed 11/29/17 Wed 11/29/17 12 Budgeter $720.00
14 2.5 Ordered Materials are Received 3 days Thu 11/30/17 Mon 12/4/17 13 Budgeter $2,160.00
15 M2 Resources are Accumulated 0 days Mon 12/4/17 Mon 12/4/17 14 $0.00
16 3 Project Planning and Scheduling 12 days Tue 12/5/17 Wed 12/20/17 $8,480.00
17 3.1 Selecting Project Plan methodology 1 day Tue 12/5/17 Tue 12/5/17 15 Planner $720.00
18 3.2 Developing Plan outline 3 days Wed 12/6/17 Fri 12/8/17 17 Planner $2,160.00
19 3.3 Reviewing the plan 2 days Mon 12/11/17 Tue 12/12/17 18 Project Manager $1,280.00
20 3.4 Completing the project plan 6 days Wed 12/13/17 Wed 12/20/17 19 Planner $4,320.00
21 M3 Project Plan is approved 0 days Wed 12/20/17 Wed 12/20/17 20 $0.00
22 4 System Designing 12 days Thu 12/21/17 Fri 1/5/18 $6,720.00
23 4.1 Selecting design platform 2 days Thu 12/21/17 Fri 12/22/17 21 System Analyst $1,120.00
24 4.2 Developing Design outline 4 days Mon 12/25/17 Thu 12/28/17 23 System Analyst $2,240.00
25 4.3 Prototyping the design 4 days Fri 12/29/17 Wed 1/3/18 24 System Analyst $2,240.00
26 4.4 Simulation is run on the design 2 days Thu 1/4/18 Fri 1/5/18 25 System Analyst $1,120.00
27 M4 Complete Design is developed 0 days Fri 1/5/18 Fri 1/5/18 26 $0.00
28 5 System Implementation 44 days Mon 1/8/18 Thu 3/8/18 $30,440.00
29 5.1 Integrated Storage is developed 10 days Mon 1/8/18 Fri 1/19/18 27 IT Engineer,Storage [1] $7,500.00
30 5.2 Data are transferred to the new
storage
4 days Mon 1/22/18 Thu 1/25/18 29 IT Engineer $2,400.00
31 5.3 Design is used for integrated
ticketing system
3 days Fri 1/26/18 Tue 1/30/18 30 IT Engineer $1,800.00
32 5.4 User Interface is developed 5 days Wed 1/31/18 Tue 2/6/18 31 IT Engineer $3,000.00
33 5.5 Necessary Functions are coded and
programmed
12 days Wed 2/7/18 Thu 2/22/18 32 IT Engineer $7,200.00
34 5.6 Ticketing system is integrated with
the storage
4 days Fri 2/23/18 Wed 2/28/18 33 IT
Engineer,Network
Components[1]
$2,960.00
35 5.7 Hardware components are installed 6 days Thu 3/1/18 Thu 3/8/18 34 IT Engineer,Computer Devices[1],Wireless routers[1]$5,580.00
36 M5 System is implemented ate Globex 0 days Thu 3/8/18 Thu 3/8/18 35 $0.00
37 6 Testing Phase 16 days Fri 3/9/18 Fri 3/30/18 $8,320.00
38 6.1 User Interface is tested 4 days Fri 3/9/18 Wed 3/14/18 36 Tester $2,080.00
39 6.2 Functions are tested 4 days Thu 3/15/18 Tue 3/20/18 38 Tester $2,080.00
40 6.3 Black box testing 4 days Wed 3/21/18 Mon 3/26/18 39 Tester $2,080.00
41 6.4 White Box testing 4 days Tue 3/27/18 Fri 3/30/18 40 Tester $2,080.00
42 M6 Testing Results are developed 0 days Fri 3/30/18 Fri 3/30/18 41 $0.00
43 7 Final Documents 8 days Mon 4/2/18 Wed 4/11/18 $5,320.00
44 7.1 Final Documents are made 5 days Mon 4/2/18 Fri 4/6/18 42 Documenter $3,400.00
45 7.2 Documents are reviewed 2 days Mon 4/9/18 Tue 4/10/18 44 Project Manager $1,280.00
46 7.3 Documents are Signed off 1 day Wed 4/11/18 Wed 4/11/18 45 Project Manager $640.00
47 M7 Project is Closed 0 days Wed 4/11/18 Wed 4/11/18 46 $0.00
Planner
Planner
Documenter
Documenter
Project Manager
Project Manager
10/31
System Analyst
Project Manager
Budgeter
Budgeter
Budgeter
12/4
Planner
Planner
Project Manager
Planner
12/20
System Analyst
System Analyst
System Analyst
System Analyst
1/5
IT Engineer,Storage [1]
IT Engineer
IT Engineer
IT Engineer
IT Engineer
IT Engineer,Network Components[1]
IT Engineer,Computer Devices[1],Wireless router
3/8
Tester
Tester
Tester
Tester
3/30
Documenter
Project Manager
Project Manager
4/11
M W F S T T S M W F
Aug 20, '17 Oct 22, '17 Dec 24, '17 Feb 25, '18 Apr 29, '18
Mode
WBS Task Name Duration Start Finish Predecessors Resource Names Cost
0 0 RALS Ticketing System 138 days Mon 10/2/17 Wed 4/11/18 $90,000.00
1 1 Project Intialization 22 days Mon 10/2/17 Tue 10/31/17 $15,360.00
2 1.1 Feasibility Analysis 6 days Mon 10/2/17 Mon 10/9/17 Planner $4,320.00
3 1.2 Identification of the Requirements 6 days Tue 10/10/17 Tue 10/17/17 2 Planner $4,320.00
4 1.3 Project Initiation Documents 4 days Wed 10/18/17 Mon 10/23/17 3 Documenter $2,720.00
5 1.4 Charter Development 4 days Tue 10/24/17 Fri 10/27/17 4 Documenter $2,720.00
6 1.5 Project Meetings 1 day Mon 10/30/17 Mon 10/30/17 5 Project Manager $640.00
7 1.6 Documents are Signed off 1 day Tue 10/31/17 Tue 10/31/17 6 Project Manager $640.00
8 M1 Project is Initiated 0 days Tue 10/31/17 Tue 10/31/17 7 $0.00
9 2 Project Resource Accumulation 24 days Wed 11/1/17 Mon 12/4/17 $15,360.00
10 2.1 Analysis of the vendor requirements 7 days Wed 11/1/17 Thu 11/9/17 8 System Analyst $3,920.00
11 2.2 Recruiting Project team 10 days Fri 11/10/17 Thu 11/23/17 10 Project Manager $6,400.00
12 2.3 Developing Project Budget 3 days Fri 11/24/17 Tue 11/28/17 11 Budgeter $2,160.00
13 2.4 Material Resources are Ordered 1 day Wed 11/29/17 Wed 11/29/17 12 Budgeter $720.00
14 2.5 Ordered Materials are Received 3 days Thu 11/30/17 Mon 12/4/17 13 Budgeter $2,160.00
15 M2 Resources are Accumulated 0 days Mon 12/4/17 Mon 12/4/17 14 $0.00
16 3 Project Planning and Scheduling 12 days Tue 12/5/17 Wed 12/20/17 $8,480.00
17 3.1 Selecting Project Plan methodology 1 day Tue 12/5/17 Tue 12/5/17 15 Planner $720.00
18 3.2 Developing Plan outline 3 days Wed 12/6/17 Fri 12/8/17 17 Planner $2,160.00
19 3.3 Reviewing the plan 2 days Mon 12/11/17 Tue 12/12/17 18 Project Manager $1,280.00
20 3.4 Completing the project plan 6 days Wed 12/13/17 Wed 12/20/17 19 Planner $4,320.00
21 M3 Project Plan is approved 0 days Wed 12/20/17 Wed 12/20/17 20 $0.00
22 4 System Designing 12 days Thu 12/21/17 Fri 1/5/18 $6,720.00
23 4.1 Selecting design platform 2 days Thu 12/21/17 Fri 12/22/17 21 System Analyst $1,120.00
24 4.2 Developing Design outline 4 days Mon 12/25/17 Thu 12/28/17 23 System Analyst $2,240.00
25 4.3 Prototyping the design 4 days Fri 12/29/17 Wed 1/3/18 24 System Analyst $2,240.00
26 4.4 Simulation is run on the design 2 days Thu 1/4/18 Fri 1/5/18 25 System Analyst $1,120.00
27 M4 Complete Design is developed 0 days Fri 1/5/18 Fri 1/5/18 26 $0.00
28 5 System Implementation 44 days Mon 1/8/18 Thu 3/8/18 $30,440.00
29 5.1 Integrated Storage is developed 10 days Mon 1/8/18 Fri 1/19/18 27 IT Engineer,Storage [1] $7,500.00
30 5.2 Data are transferred to the new
storage
4 days Mon 1/22/18 Thu 1/25/18 29 IT Engineer $2,400.00
31 5.3 Design is used for integrated
ticketing system
3 days Fri 1/26/18 Tue 1/30/18 30 IT Engineer $1,800.00
32 5.4 User Interface is developed 5 days Wed 1/31/18 Tue 2/6/18 31 IT Engineer $3,000.00
33 5.5 Necessary Functions are coded and
programmed
12 days Wed 2/7/18 Thu 2/22/18 32 IT Engineer $7,200.00
34 5.6 Ticketing system is integrated with
the storage
4 days Fri 2/23/18 Wed 2/28/18 33 IT
Engineer,Network
Components[1]
$2,960.00
35 5.7 Hardware components are installed 6 days Thu 3/1/18 Thu 3/8/18 34 IT Engineer,Computer Devices[1],Wireless routers[1]$5,580.00
36 M5 System is implemented ate Globex 0 days Thu 3/8/18 Thu 3/8/18 35 $0.00
37 6 Testing Phase 16 days Fri 3/9/18 Fri 3/30/18 $8,320.00
38 6.1 User Interface is tested 4 days Fri 3/9/18 Wed 3/14/18 36 Tester $2,080.00
39 6.2 Functions are tested 4 days Thu 3/15/18 Tue 3/20/18 38 Tester $2,080.00
40 6.3 Black box testing 4 days Wed 3/21/18 Mon 3/26/18 39 Tester $2,080.00
41 6.4 White Box testing 4 days Tue 3/27/18 Fri 3/30/18 40 Tester $2,080.00
42 M6 Testing Results are developed 0 days Fri 3/30/18 Fri 3/30/18 41 $0.00
43 7 Final Documents 8 days Mon 4/2/18 Wed 4/11/18 $5,320.00
44 7.1 Final Documents are made 5 days Mon 4/2/18 Fri 4/6/18 42 Documenter $3,400.00
45 7.2 Documents are reviewed 2 days Mon 4/9/18 Tue 4/10/18 44 Project Manager $1,280.00
46 7.3 Documents are Signed off 1 day Wed 4/11/18 Wed 4/11/18 45 Project Manager $640.00
47 M7 Project is Closed 0 days Wed 4/11/18 Wed 4/11/18 46 $0.00
Planner
Planner
Documenter
Documenter
Project Manager
Project Manager
10/31
System Analyst
Project Manager
Budgeter
Budgeter
Budgeter
12/4
Planner
Planner
Project Manager
Planner
12/20
System Analyst
System Analyst
System Analyst
System Analyst
1/5
IT Engineer,Storage [1]
IT Engineer
IT Engineer
IT Engineer
IT Engineer
IT Engineer,Network Components[1]
IT Engineer,Computer Devices[1],Wireless router
3/8
Tester
Tester
Tester
Tester
3/30
Documenter
Project Manager
Project Manager
4/11
M W F S T T S M W F
Aug 20, '17 Oct 22, '17 Dec 24, '17 Feb 25, '18 Apr 29, '18
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

The WBS for the project is given in the diagram below,
WBS Task Name
0 RALS Ticketing System
1 Project Initialization
1.1 Feasibility Analysis
1.2 Identification of the Requirements
1.3 Project Initiation Documents
1.4 Charter Development
1.5 Project Meetings
1.6 Documents are Signed off
M1 Project is Initiated
2 Project Resource Accumulation
2.1 Analysis of the vendor requirements
2.2 Recruiting Project team
2.3 Developing Project Budget
2.4 Material Resources are Ordered
2.5 Ordered Materials are Received
M2 Resources are Accumulated
3 Project Planning and Scheduling
3.1 Selecting Project Plan methodology
3.2 Developing Plan outline
3.3 Reviewing the plan
3.4 Completing the project plan
M3 Project Plan is approved
4 System Designing
4.1 Selecting design platform
4.2 Developing Design outline
4.3 Prototyping the design
4.4 Simulation is run on the design
M4 Complete Design is developed
5 System Implementation
5.1 Integrated Storage is developed
5.2 Data are transferred to the new storage
5.3 Design is used for integrated ticketing system
5.4 User Interface is developed
5.5 Necessary Functions are coded and programmed
5.6 Ticketing system is integrated with the storage
5.7 Hardware components are installed
M5 System is implemented ate Globex
6 Testing Phase
6.1 User Interface is tested
6.2 Functions are tested
6.3 Black box testing
WBS Task Name
0 RALS Ticketing System
1 Project Initialization
1.1 Feasibility Analysis
1.2 Identification of the Requirements
1.3 Project Initiation Documents
1.4 Charter Development
1.5 Project Meetings
1.6 Documents are Signed off
M1 Project is Initiated
2 Project Resource Accumulation
2.1 Analysis of the vendor requirements
2.2 Recruiting Project team
2.3 Developing Project Budget
2.4 Material Resources are Ordered
2.5 Ordered Materials are Received
M2 Resources are Accumulated
3 Project Planning and Scheduling
3.1 Selecting Project Plan methodology
3.2 Developing Plan outline
3.3 Reviewing the plan
3.4 Completing the project plan
M3 Project Plan is approved
4 System Designing
4.1 Selecting design platform
4.2 Developing Design outline
4.3 Prototyping the design
4.4 Simulation is run on the design
M4 Complete Design is developed
5 System Implementation
5.1 Integrated Storage is developed
5.2 Data are transferred to the new storage
5.3 Design is used for integrated ticketing system
5.4 User Interface is developed
5.5 Necessary Functions are coded and programmed
5.6 Ticketing system is integrated with the storage
5.7 Hardware components are installed
M5 System is implemented ate Globex
6 Testing Phase
6.1 User Interface is tested
6.2 Functions are tested
6.3 Black box testing
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

6.4 White Box testing
M6 Testing Results are developed
7 Final Documents
7.1 Final Documents are made
7.2 Documents are reviewed
7.3 Documents are Signed off
M7 Project is Closed
Part Four:
Project Risk Analysis and Plan
No.: RTR001
Rank: 1st
Risk: System Failure
Description: System failure might be resulted when the ticketing system of RALS would fail to develop
the effective processing of the information for developing the improvement factors
Category: Technical
Triggers: Flaws in system
Potential Responses: Prior testing of the system before implementation
Risk Owner: IT Engineer
Probability: Likely
Impact: Critical
Status: 1 week set up
No.: RTR002
Rank: 2nd
Risk: Over budgeting
Description: The activities of the project might end up in causing excess utilization of the project
resources which might lead to the over budgeting of the project
Category: Financial
Triggers: Lack of Adequate Resources
Potential Responses: Development of provisional budget for the project
Risk Owner: Budgeter
M6 Testing Results are developed
7 Final Documents
7.1 Final Documents are made
7.2 Documents are reviewed
7.3 Documents are Signed off
M7 Project is Closed
Part Four:
Project Risk Analysis and Plan
No.: RTR001
Rank: 1st
Risk: System Failure
Description: System failure might be resulted when the ticketing system of RALS would fail to develop
the effective processing of the information for developing the improvement factors
Category: Technical
Triggers: Flaws in system
Potential Responses: Prior testing of the system before implementation
Risk Owner: IT Engineer
Probability: Likely
Impact: Critical
Status: 1 week set up
No.: RTR002
Rank: 2nd
Risk: Over budgeting
Description: The activities of the project might end up in causing excess utilization of the project
resources which might lead to the over budgeting of the project
Category: Financial
Triggers: Lack of Adequate Resources
Potential Responses: Development of provisional budget for the project
Risk Owner: Budgeter

Probability: Possible
Impact: Medium-high
Status: 2 week set up
No.: RTR003
Rank: 3rd
Risk: Design flaws
Description: The issues of the design made for the ticketing system would be a major risk factor that
could result in forming the downfall of the project
Category: Technical
Triggers: Absence of Design Methodology
Potential Responses: Selecting an accurate design methodology for the project
Risk Owner: Designer
Probability: Likely
Impact: Medium
Status: 3 week set up
No.: RTR004
Rank: 4th
Risk: Management Issue
Description: The issues in management is a major factor for the development of the hindrances in the
completion of the project
Category: Operational
Triggers: Lack of Management Approach
Potential Responses: Use of project management principles and operations
Risk Owner: Project Manager
Probability: Possible
Impact: Medium
Status: 1 week set up
No.: RTR005
Rank: 5th
Impact: Medium-high
Status: 2 week set up
No.: RTR003
Rank: 3rd
Risk: Design flaws
Description: The issues of the design made for the ticketing system would be a major risk factor that
could result in forming the downfall of the project
Category: Technical
Triggers: Absence of Design Methodology
Potential Responses: Selecting an accurate design methodology for the project
Risk Owner: Designer
Probability: Likely
Impact: Medium
Status: 3 week set up
No.: RTR004
Rank: 4th
Risk: Management Issue
Description: The issues in management is a major factor for the development of the hindrances in the
completion of the project
Category: Operational
Triggers: Lack of Management Approach
Potential Responses: Use of project management principles and operations
Risk Owner: Project Manager
Probability: Possible
Impact: Medium
Status: 1 week set up
No.: RTR005
Rank: 5th
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 17
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.