ICT 505: Rapid Bill Payment System Project Management Plan

Verified

Added on  2025/04/09

|28
|5411
|161
AI Summary
Desklib provides past papers and solved assignments. This document details the Rapid Bill software project management plan.
Document Page
ICT Project Management
ITC 505
1
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Table of Contents
Introduction......................................................................................................................................3
Project Description..........................................................................................................................4
Part One: MOV (Measurable Organisational Value)......................................................................5
Identification of desired influential area......................................................................................5
Value............................................................................................................................................5
Metric...........................................................................................................................................6
Expectations of the Stakeholder..................................................................................................6
Quantitative target.......................................................................................................................7
Timeframe for MOV....................................................................................................................7
Summary of MOV.......................................................................................................................8
Part Two: Scope...............................................................................................................................9
Scope............................................................................................................................................9
In scope and out range.................................................................................................................9
Acceptance criterion..................................................................................................................10
List of resources.........................................................................................................................10
Component Three: Work Breakdown Structure............................................................................13
Milestone...................................................................................................................................15
Activities and task......................................................................................................................15
Estimation for each event and task............................................................................................16
Project budget............................................................................................................................16
Part Four: Risk Analysis and Plan.............................................................................................17
Risk analysis plan......................................................................................................................17
Assumptions about the project...................................................................................................17
Framework for risk identification..............................................................................................17
2
Document Page
Strategy to manage these risks –................................................................................................19
Part Five: Quality Management Plan.............................................................................................20
Quality Management Plan.........................................................................................................20
A set of verification activities....................................................................................................21
A collection of validation activities...........................................................................................21
Part Six: Closure and Evaluation step...........................................................................................23
References......................................................................................................................................25
3
Document Page
Introduction
The functions of any organisation depend on the type of software which supports well in the
development and success of an organisation. To give satisfaction to the requirements of the
company, there are various who make development of the software to solve such problems. One
of the companies with the name Virtucon is the software development organisation who is
working with its client with the name Globex Corp which is a farm and agriculture-based
organisation. Globex Corp is having problem-related with the service alignment and billing
services which makes an impact on their operations. By understanding requirements of Globex
Corp, a separate team will be made by Virtucon to ensure that there will be a development of the
software which will be known as ‘Rapid-Bill’ according to the client’s needs.
The primary feature of this software is that it will support well in making provision of the
comfortable and convenient transaction of cash as per the order and needs of the customers who
are visiting Globex for placing the order. In this software, one innovative feature is also there
such as individual instruction and customisation of law which will be provided to the dealer in
relation with the function, quantity and quality of products.
4
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Project Description
In every project, there is a need for specific entitlements and specifications that will support in
fulfilling the needs and requirements of the customers properly. Virtucon developed the plan for
Globex Corp about the payments and finance operated by the Globex organisation. This project
will increase confidentiality, performance level and transparency. With the support of the
developed software, the digital and modern channels of payment will be opened like cash
management and online payments. This project will also support in managing the resources as
well as clients in an appropriate manner. The project also aims to provide effective managerial
and effective services which will help in increasing the organisation's performance. The entire
description of the project can be provided in the form of a table:
Name of the Project Rapid Bill software
Name of customer Globex Corp
Association of project ICT technology
Location Australia
Type of project Online service regarding payment
5
Document Page
Part One: MOV (Measurable Organisational Value)
Measurable Organisational Value is being considered as the primary goal of the project is being
utilised to make value description that the team's plan will be presented in front of the client.
Identification of desired influential area
Description in regards to the desired important area is being defined as follows:
Strategy Client/customers Finance Operations Social
As the Virtucon,
as well as
Globex, is being
planned for the
development of
the new project
in collaboration,
therefore there is
the much need
regarding the
development of
the strategy to
attain aims and
objectives.
With the help of
the developed
software that is
Rapid bill
payment, sellers
and buyers can
meet up on the
same platform,
and there will be
an increase in the
functions and
operations
regarding the
finance.
The develop
software, or the
system will
support well the
customers and
clients to deal
with the cash
transactions
conveniently and
efficiently.
As the developed
system is
automatic so
there will be
decidedly fewer
chances
regarding the
error. Apart from
this, there will be
proper
management of
sellers and
buyers as well as
their cash
transactions in an
appropriate
manner.
Proper increment
will be there in
the social
expression due to
the high increase
in the number of
customers who
will make use of
the software.
Value
Better: With the proper assistance of the rapid bill software, customers of the Globex
Corp will be able to make a cash payment in a convenient and fast manner regarding the
sale and purchase of grains. Customers can also meet directly with the sellers to make
deals.
6
Document Page
Faster: Globex Corp is currently facing issues in regards to cash handling and billing
services. They require such kind of system with the support of which payment can be
made quickly. With the help of this Rapid bill system, the customer can make payments
without going anywhere.
Metric
Targets
To make the development of the rapid bill software, there are various kinds of things which are
being targeted and can be described as follows:
There is the development of the first bill software to make increment in the automation
and transparency level in the finance sector and procedure regarding the Globex Corp.
The software will make a description of the increased integration's level regarding the
online channel as per the customer's perspective.
With the development of this software, there will also be increased in the communication
and interaction in the project with the software's accommodation.
Expectations of the Stakeholder
Stakeholders Expectations
Virtucon Consultancy The main work of the Virtucon Consultancy is
to develop the useful software which will
support well in the electric bill payment and in
carrying all the cash related activities.
Customer/ Clients They want their all needs and requirements to
be fulfilled regarding the cash transactions so
that they can be able to make payment rapidly.
Sponsors Require effective and efficient project which
will be valuable for customers so that they can
provide good sponsorship.
Globex Corporation To get the software as per the requirements and
needs that may solve their issues regarding the
billing.
Project Team The project team will be there to develop the
7
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
software as per the needs and requirements,
and they expect to get appreciation when the
project gets completed. They also want to get
proper coordination from Virtucon and
Globex.
Quantitative target
There is the expectation to solve issues regarding the billing within the 6 months with the
support of the software and to make an increase in the profit by 70 – 80%.
To make increment in the retention of the customers 90%.
To make the flow of the cash transactions easy by satisfying 90% of the customers.
To maximise the rate of interests by 10% within 5-6 months.
Timeframe for MOV
S. No. Task Name Duration
1 Analysis of the requirements of sellers as well
as buyers
Two days
2 Project’s Conceptualisation and initialisation to
achieve it
6 days
3 Presentation of the criteria to Virtucon 2 day
4 Execution and control of the plan 4 days
5 Implementation of the rapid bill system 8 days
6 System installation 5 days
7 Training to the staff of the Globex regarding the
software
2 days
8 Closure of the project which is carried out 1 day
9 System evaluation 2 days
10 Total 32 days
8
Document Page
Summary of MOV
The rapid bill software will be going to give proper support to the Globex Corp in solving issues
related to billing and to fulfil the needs and requirements of customers. With the help of this
system, customers will be able to make bill payments rapidly and efficiently. This system can be
accessed by visitors on tablets, mobile and notebooks. Payment can be created with the support
of different sources. Through the implementation of this system, Globex can manage the billing
functions properly. Only the valid customer who wants to purchase grains will be able to access
this system. Apart from this Globex will also be able to track the record regarding revenue which
is generated with the support of customers.
9
Document Page
Part Two: Scope
Scope
The main aim of the Globex is to solve the issues regarding the billing services and to align all
the related cash payments in an effective manner which will support customers to make payment
without any problems. This system will be developed for the customers of Riverina Region of
NSW, Australia. A contract has been developed between the Globex and Virtucon so that proper
management of all the billing services can be there in a suitable way. Virtucon will develop the
rapid bill software for the Globex and its customers by understanding its needs and requirements.
In this system there will be a provision of various features and functions which are described as
follows:
Rapid bill software will be developed by Virtucon which will be very supportive for the
smooth flow of cash transactions between Globex and Virtucon.
This software will also be able to provide customers with a platform where they can meet
sellers directly.
This system can be used on mobile, tablets, and notebooks by the customers and can be
accessed from any place of the world for communication and interaction.
In scope and out an extent
In scope items
Out scope items
# Item Name
1 NFC reader
2 Data storage
10
# Item Name
1 Barcode reader
2 System
3 Printer
4 Laptops
5 Mobiles
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Deliverables
Some of the significant things which must be delivered to the Globex can be defined as follows:
Overall plan regarding the project
Planning for the budget
Work Breakdown Structure
The milestone of the project
A global strategy for the proper administration of the project
Schedule of the project
Roles and responsibilities of the staff members
Planning regarding system development (Helmers, 2012)
Whole documentation process of user
Plan for the testing of the project
Acceptance criterion
There are different sort of measures which is being required to be fulfilled so that the Virtucon
can develop such kind of system which will help sellers and buyers to have a smooth transaction
of cash. This kind of acceptance criteria can be described as follows:
Access to this system is effortless as it can be done through mobiles, notebooks and
tablets.
All the billing and cash transaction operations will be done through the online
application.
Proper internet connectivity must be there every time to carry out operations.
With the proper use of this system, buyers can meet directly with the sellers and can have
dealings of cash.
List of resources
There are different kinds of resources that are generally needed for the development of the rapid
bill software and can be defined as follows:
People / Human resource: In this platform where there will provision of the timely
billing services, different kinds of qualified individuals will be required for the effective
and appropriate creation and development of the software in less time and cost. The
human resource that will be a part of the project must have proper skills and knowledge
11
Document Page
so that the project can be completed appropriately and effectively (Jagarlapudi and
Metamarket, 2012). Human resources will be required for different fields, and they can
be the manager of the project, technician, business analysts and many more which will be
described as follows:
# Human
Resources
Description
1 Project
administrator
When the project gets started, and till the time it gets
completed, the primary responsibility is there on the
administrator or manager of the plan who plays the
leading role in leading the whole project. For this
purpose, different kind of steps must be carried out
planning, execution, implementation and many other
things.
2 Analyst of the
business
Business analyst also has various responsibilities to make
a useful analysis of the whole company or project which
is being carried out. He is also responsible for integrating
the model of the company with the help of various
techniques (Kerzner & Kerzner, 2017).
3 Analyst for the
system
The primary role which is played by the system analyst is
to provide the use of technology which will be cost
effective.
4 The
architecture of
the entire
system
The primary duty which is being played by the architect
of the system is to give structure to the whole system to
fulfil the requirements and needs of the client. Proper
designing of the system is being done by architecture to
divide it into several components.
5 Application
developer
The application developer is the programmer who has the
duty regarding the development of the application. A
system can be adequately accessed by the customer with
the help of the application developer (Lorah et. al.,
(2014).