Project Report: Re-design of Guest Tracker Application (ISY302)
VerifiedAdded on 2022/12/01
|18
|3297
|1
Report
AI Summary
This report details the re-design of a guest tracker application for a hotel, encompassing project planning and management aspects. The project, budgeted at $65,000 and scheduled for 66 days, includes a comprehensive work breakdown structure, project schedule, and risk management plan. The report outlines both functional and non-functional requirements, including user and system specifications. Key functional aspects include customer booking management, administrator controls, and report generation. System requirements emphasize modern technologies such as PHP, MySQL, HTML5, and responsive web design. The report also addresses user requirements, such as a consistent user interface, and incorporates features like data analytics and social media integration. The project aims to enhance the guest experience, increase bookings, and improve overall customer satisfaction, with a focus on user experience, security, and performance optimization.

Re-design of Guest Tracker Application
Report
9/16/2019
Report
9/16/2019
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Re-design of Guest Tracker Application
Table of Contents
Introduction......................................................................................................................3
Aim................................................................................................................................3
Project charter..................................................................................................................4
Work Breakdown Structure.............................................................................................6
Project schedule................................................................................................................8
Risk management..............................................................................................................9
Requirements of the website...........................................................................................10
Functional requirements.............................................................................................10
System requirements...................................................................................................11
Other requirements.................................................................................................11
User Requirements......................................................................................................11
Non-Functional requirements.....................................................................................13
Domain and security requirements.................................................................................13
Use-case Diagram........................................................................................................15
Conclusion.......................................................................................................................15
References.......................................................................................................................16
1
Table of Contents
Introduction......................................................................................................................3
Aim................................................................................................................................3
Project charter..................................................................................................................4
Work Breakdown Structure.............................................................................................6
Project schedule................................................................................................................8
Risk management..............................................................................................................9
Requirements of the website...........................................................................................10
Functional requirements.............................................................................................10
System requirements...................................................................................................11
Other requirements.................................................................................................11
User Requirements......................................................................................................11
Non-Functional requirements.....................................................................................13
Domain and security requirements.................................................................................13
Use-case Diagram........................................................................................................15
Conclusion.......................................................................................................................15
References.......................................................................................................................16
1

Re-design of Guest Tracker Application
Abstract
The project report is developed for the guest-tracker application project which is required to
be re-designed for the hotel. The report comprises of the project planning and management
aspects. The completion of the project will be done in 66 days and the total budget assigned
is $65,000. The information on the project requirements is also included in the report.
2
Abstract
The project report is developed for the guest-tracker application project which is required to
be re-designed for the hotel. The report comprises of the project planning and management
aspects. The completion of the project will be done in 66 days and the total budget assigned
is $65,000. The information on the project requirements is also included in the report.
2
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Re-design of Guest Tracker Application
Introduction
The report is developed for the project for the re-design of the guest tracker application of a
hotel. It is required for every business organization to have the enhanced web presence so that
the customers can easily access the application and carry out the specific operations. The user
interface and the look & feel of the application are also essential along with the
functionalities. The re-design of the guest tracker website will be done for the hotel so that it
may succeed in attracting increased number of guests.
Aim
The aim of the report is to provide the project management details for the project and
illustrate the requirements associated with the project.
3
Introduction
The report is developed for the project for the re-design of the guest tracker application of a
hotel. It is required for every business organization to have the enhanced web presence so that
the customers can easily access the application and carry out the specific operations. The user
interface and the look & feel of the application are also essential along with the
functionalities. The re-design of the guest tracker website will be done for the hotel so that it
may succeed in attracting increased number of guests.
Aim
The aim of the report is to provide the project management details for the project and
illustrate the requirements associated with the project.
3
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Re-design of Guest Tracker Application
Project charter
Project Charter
Project Name: Re-designing guest tracker
application
Project Manager: Name of the Project
Manager
Background: The project is being carried out so that the functionalities and the user
interface of the guest tracker application of the hotel is improved.
Objective: The objective of the project is to
enhance the functional and non-functional
aspects of the website for improved user
experience.
Success Criteria:
Completion of the project on time
and within budget
User acceptance during UAT phase
Zero defects at the time of go-live
(Sanchez & Serrano, 2019)
Deliverables: The following deliverables
will be included in the project:
Project Charter & Project Plan will
be delivered to provide the details of
the project management and
planning aspects.
Web Design: The UI aspects of the
guest tracker application will be
delivered.
Source Code: The source code of the
guest tracker website will be
delivered.
Project Reports: These will include
the reports on project risks, changes,
and progress.
Completion Report: It will cover the
inclusion of all the project activities.
Exclusion:
The re-design of the guest tracker website
will not include the other business areas
apart from customer bookings, interaction,
and management.
The project will also not include the
marketing of these developments and
changes.
Benefits Expected: The project will provide
the following benefits:
Enhancement in the customer
(Inter) Dependencies / Interfaces
There will be a number of interfaces that
will be involved. The user interface will be
4
Project charter
Project Charter
Project Name: Re-designing guest tracker
application
Project Manager: Name of the Project
Manager
Background: The project is being carried out so that the functionalities and the user
interface of the guest tracker application of the hotel is improved.
Objective: The objective of the project is to
enhance the functional and non-functional
aspects of the website for improved user
experience.
Success Criteria:
Completion of the project on time
and within budget
User acceptance during UAT phase
Zero defects at the time of go-live
(Sanchez & Serrano, 2019)
Deliverables: The following deliverables
will be included in the project:
Project Charter & Project Plan will
be delivered to provide the details of
the project management and
planning aspects.
Web Design: The UI aspects of the
guest tracker application will be
delivered.
Source Code: The source code of the
guest tracker website will be
delivered.
Project Reports: These will include
the reports on project risks, changes,
and progress.
Completion Report: It will cover the
inclusion of all the project activities.
Exclusion:
The re-design of the guest tracker website
will not include the other business areas
apart from customer bookings, interaction,
and management.
The project will also not include the
marketing of these developments and
changes.
Benefits Expected: The project will provide
the following benefits:
Enhancement in the customer
(Inter) Dependencies / Interfaces
There will be a number of interfaces that
will be involved. The user interface will be
4

Re-design of Guest Tracker Application
experience levels by at least 45%
Overall customer rating as 4.5 or
above on a scale of 5
Increase in bookings by 45%
the front-end of the guest-tracker
application and it will be designed using
responsive web design as the methodology.
The back-end will include the database and
it will be MySQL database.
The security interface will also be involved
for the purpose of the safety of the
application.
Assumptions:
It is assumed that the test data will be used
at the time of quality control and assurance.
It is also assumed that the production data
will be handled only by the Database
Administrator.
Constraints: The total schedule estimated
for the project is 66 days and there is no
scope of major re-works or delays. The
schedule is one of the major concerns.
The entire project activities are to be
completed under the budget of $65,000
which is also one of the constraints.
There are technological constraints that are
also applicable in terms of security
constraints and regulatory constraints for the
protection of the data and information sets
(Rose, 2013).
Timeframe
66 days
Cost estimate / Budget
$65,000
Dated approved / Sign-offs Project manager Sign off & Date
5
experience levels by at least 45%
Overall customer rating as 4.5 or
above on a scale of 5
Increase in bookings by 45%
the front-end of the guest-tracker
application and it will be designed using
responsive web design as the methodology.
The back-end will include the database and
it will be MySQL database.
The security interface will also be involved
for the purpose of the safety of the
application.
Assumptions:
It is assumed that the test data will be used
at the time of quality control and assurance.
It is also assumed that the production data
will be handled only by the Database
Administrator.
Constraints: The total schedule estimated
for the project is 66 days and there is no
scope of major re-works or delays. The
schedule is one of the major concerns.
The entire project activities are to be
completed under the budget of $65,000
which is also one of the constraints.
There are technological constraints that are
also applicable in terms of security
constraints and regulatory constraints for the
protection of the data and information sets
(Rose, 2013).
Timeframe
66 days
Cost estimate / Budget
$65,000
Dated approved / Sign-offs Project manager Sign off & Date
5
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Re-design of Guest Tracker Application
Work Breakdown Structure
WBS
Code Task Name Start Date Finish Date Duration Estimated
Cost
1
Re-designing website - Guest tracker
application 9/16/19 9/30/19 66 days $64,490.00
1.1 Project initiation 9/16/19 9/19/19 11 days $9,680.00
1.1.1 Study current website 9/16/19 9/24/19 4 days $2,880.00
1.1.2 Define re-designing elements Fri 9/20/19 Fri 9/27/19 3 days $1,920.00
1.1.3 Prepare requirements documents 9/25/19 9/30/19 3 days $4,080.00
1.1.4 Get approval 9/30/19 10/14/19 1 day $800.00
1.2 Project planning 10/1/19 Fri 10/4/19 10 days $17,120.00
1.2.1 Create work breakdown structure 10/1/19 Fri 10/4/19 4 days $3,200.00
1.2.2 Create budget plan 10/1/19 Fri 10/4/19 4 days $2,720.00
1.2.3 Create resource plan 10/1/19 Fri 10/4/19 4 days $3,200.00
1.2.4 Create risk management plan 10/1/19 Fri 10/11/19 4 days $3,200.00
1.2.5 Prepare final project plan 10/7/19 10/14/19 5 days $4,000.00
1.2.6 Get approval 10/14/19 12/10/19 1 day $800.00
1.3 Project execution 10/15/19 10/17/19 41 days $26,050.00
1.3.1 Take database backup 10/15/19 10/17/19 3 days $1,680.00
1.3.2 Create code backup 10/15/19 10/21/19 3 days $1,920.00
1.3.3 Finalize IDE Fri 10/18/19 10/23/19 2 days $1,360.00
1.3.4 Finalize database 10/22/19 11/6/19 2 days $1,120.00
1.3.5 Coding 10/24/19 11/12/19 10 days $6,890.00
1.3.6 Unit testing 11/7/19 12/3/19 4 days $2,080.00
1.3.7 Testing 11/13/19 Fri 11/15/19 15 days $7,800.00
1.3.7.1 Create test plans 11/13/19 11/21/19 3 days $1,560.00
1.3.7.2 System testing 11/18/19 11/28/19 4 days $2,080.00
1.3.7.3 UAT Fri 11/22/19 12/3/19 5 days $2,600.00
1.3.7.4 Prepare bugs report Fri 11/29/19 12/10/19 3 days $1,560.00
1.3.8 Resolve bugs 12/4/19 Fri 12/13/19 5 days $3,200.00
1.4 Project closure 12/11/19 Fri 12/13/19 3 days $6,400.00
1.4.1 Create manual 12/11/19 Fri 12/13/19 3 days $2,400.00
6
Work Breakdown Structure
WBS
Code Task Name Start Date Finish Date Duration Estimated
Cost
1
Re-designing website - Guest tracker
application 9/16/19 9/30/19 66 days $64,490.00
1.1 Project initiation 9/16/19 9/19/19 11 days $9,680.00
1.1.1 Study current website 9/16/19 9/24/19 4 days $2,880.00
1.1.2 Define re-designing elements Fri 9/20/19 Fri 9/27/19 3 days $1,920.00
1.1.3 Prepare requirements documents 9/25/19 9/30/19 3 days $4,080.00
1.1.4 Get approval 9/30/19 10/14/19 1 day $800.00
1.2 Project planning 10/1/19 Fri 10/4/19 10 days $17,120.00
1.2.1 Create work breakdown structure 10/1/19 Fri 10/4/19 4 days $3,200.00
1.2.2 Create budget plan 10/1/19 Fri 10/4/19 4 days $2,720.00
1.2.3 Create resource plan 10/1/19 Fri 10/4/19 4 days $3,200.00
1.2.4 Create risk management plan 10/1/19 Fri 10/11/19 4 days $3,200.00
1.2.5 Prepare final project plan 10/7/19 10/14/19 5 days $4,000.00
1.2.6 Get approval 10/14/19 12/10/19 1 day $800.00
1.3 Project execution 10/15/19 10/17/19 41 days $26,050.00
1.3.1 Take database backup 10/15/19 10/17/19 3 days $1,680.00
1.3.2 Create code backup 10/15/19 10/21/19 3 days $1,920.00
1.3.3 Finalize IDE Fri 10/18/19 10/23/19 2 days $1,360.00
1.3.4 Finalize database 10/22/19 11/6/19 2 days $1,120.00
1.3.5 Coding 10/24/19 11/12/19 10 days $6,890.00
1.3.6 Unit testing 11/7/19 12/3/19 4 days $2,080.00
1.3.7 Testing 11/13/19 Fri 11/15/19 15 days $7,800.00
1.3.7.1 Create test plans 11/13/19 11/21/19 3 days $1,560.00
1.3.7.2 System testing 11/18/19 11/28/19 4 days $2,080.00
1.3.7.3 UAT Fri 11/22/19 12/3/19 5 days $2,600.00
1.3.7.4 Prepare bugs report Fri 11/29/19 12/10/19 3 days $1,560.00
1.3.8 Resolve bugs 12/4/19 Fri 12/13/19 5 days $3,200.00
1.4 Project closure 12/11/19 Fri 12/13/19 3 days $6,400.00
1.4.1 Create manual 12/11/19 Fri 12/13/19 3 days $2,400.00
6
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Re-design of Guest Tracker Application
1.4.2 Document lesson learnt 12/11/19 12/12/19 3 days $2,400.00
1.4.3 Release resources 12/11/19 12/16/19 2 days $1,600.00
1.5 Go-Live 12/16/19 Fri 12/6/19 1 day $5,240.00
7
1.4.2 Document lesson learnt 12/11/19 12/12/19 3 days $2,400.00
1.4.3 Release resources 12/11/19 12/16/19 2 days $1,600.00
1.5 Go-Live 12/16/19 Fri 12/6/19 1 day $5,240.00
7

Re-design of Guest Tracker Application
Project schedule
The project schedule is illustrated with the aid of the Gantt chart which is shown in the
images below.
8
Project schedule
The project schedule is illustrated with the aid of the Gantt chart which is shown in the
images below.
8
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Re-design of Guest Tracker Application
Risk management
RISK MANAGEMENT
LOG
Project Name: Guest-
tracker
applicatio
n
Project Manager Name:
Project Description:
ID Current
Status
Risk
Category
Risk
Description
Risk
Impact
Proba
bility
of
Occur
rence
Risk
Rating
Risk
Response
Strategy
Response Strategy Assigned To
1 Open Technical The technical
tools, methods,
and equipment
may turn faulty
or there may be
issues around
configuration or
compatibility
High Low Moderate Transfer The risk shall be
managed by the
vendors of the
technical tools
Technical Lead
2 Open Requirem
ents
The frequent
changes in the
requirements
specifications
may lead to the
situation of
requirements
creep/inflation
(Brioso, 2015)
High Mode
rate
High Mitigation
&
Avoidance
The development
shall be done using
agile methods so
that there is always
scope for changes.
The collaboration
with the customers
shall also be done
to deal with the
risk.
Business Analyst
3 Open Design
Errors
There may be
issues in the
UI/UX design
aspects in terms
of consistency or
overall
appearance.
High High High Avoidance The use of
responsive web
design along with
HCI design
principles shall be
done.
Web Designer
4 Open Schedule/
Budget
Overrun
The project team
may not adhere
with the
estimated values
of the project
schedule or
project budget.
High Low Moderate Avoidance The tracking of the
project schedule
and budget shall be
done regularly
Project Manager
9
Risk management
RISK MANAGEMENT
LOG
Project Name: Guest-
tracker
applicatio
n
Project Manager Name:
Project Description:
ID Current
Status
Risk
Category
Risk
Description
Risk
Impact
Proba
bility
of
Occur
rence
Risk
Rating
Risk
Response
Strategy
Response Strategy Assigned To
1 Open Technical The technical
tools, methods,
and equipment
may turn faulty
or there may be
issues around
configuration or
compatibility
High Low Moderate Transfer The risk shall be
managed by the
vendors of the
technical tools
Technical Lead
2 Open Requirem
ents
The frequent
changes in the
requirements
specifications
may lead to the
situation of
requirements
creep/inflation
(Brioso, 2015)
High Mode
rate
High Mitigation
&
Avoidance
The development
shall be done using
agile methods so
that there is always
scope for changes.
The collaboration
with the customers
shall also be done
to deal with the
risk.
Business Analyst
3 Open Design
Errors
There may be
issues in the
UI/UX design
aspects in terms
of consistency or
overall
appearance.
High High High Avoidance The use of
responsive web
design along with
HCI design
principles shall be
done.
Web Designer
4 Open Schedule/
Budget
Overrun
The project team
may not adhere
with the
estimated values
of the project
schedule or
project budget.
High Low Moderate Avoidance The tracking of the
project schedule
and budget shall be
done regularly
Project Manager
9
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Re-design of Guest Tracker Application
10
10

Re-design of Guest Tracker Application
Requirements of the website
There are numerous requirements that are associated with the project of re-designing the
guest tracker application for the hotel. All of these requirements are relevant and have
significance of their own. It is required that the project team maintains focus on all the
requirements categories equally. This is because the inclusion of the functional aspects with
poor UI or performance or lack of security and vice versa will lead to the deterioration of the
end-user experience.
The details of the website requirements are included below.
Functional requirements
The functional requirements that the guest tracker application shall have are included in the
points below.
The user shall be able to log in to the guest tracker application as a customer or
administrator with valid credentials.
The customer shall be able to create the booking in the hotel by looking at the room
options as per the desired dates and availability (Alsaleh & Haron, 2016).
The customer shall be able to make the bookings, if available, and real-time updates
shall be sent by the system to the administrator.
The administrator shall make the following preferences as per the customer booking
requirements.
o The check-in/check-out details shall be mapped with the customer booking as
per the preference set by the customer.
o The room preference and allocation shall be done to the booking as per the
customer demands.
o The food preference and allocation shall be done to the booking as per the
customer demands.
The reports shall be generated by the administrator and the application of the filters
shall be done in terms of the desired report content.
11
Requirements of the website
There are numerous requirements that are associated with the project of re-designing the
guest tracker application for the hotel. All of these requirements are relevant and have
significance of their own. It is required that the project team maintains focus on all the
requirements categories equally. This is because the inclusion of the functional aspects with
poor UI or performance or lack of security and vice versa will lead to the deterioration of the
end-user experience.
The details of the website requirements are included below.
Functional requirements
The functional requirements that the guest tracker application shall have are included in the
points below.
The user shall be able to log in to the guest tracker application as a customer or
administrator with valid credentials.
The customer shall be able to create the booking in the hotel by looking at the room
options as per the desired dates and availability (Alsaleh & Haron, 2016).
The customer shall be able to make the bookings, if available, and real-time updates
shall be sent by the system to the administrator.
The administrator shall make the following preferences as per the customer booking
requirements.
o The check-in/check-out details shall be mapped with the customer booking as
per the preference set by the customer.
o The room preference and allocation shall be done to the booking as per the
customer demands.
o The food preference and allocation shall be done to the booking as per the
customer demands.
The reports shall be generated by the administrator and the application of the filters
shall be done in terms of the desired report content.
11
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 18
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.