Project Management: Refurbishing Heathrow Terminal 1 Analysis
VerifiedAdded on 2020/04/21
|20
|4081
|79
Project
AI Summary
This project examines the refurbishment of Heathrow Airport Terminal 1, a significant undertaking given the terminal's age and operational constraints. The project scope encompasses the renovation of baggage and check-in areas, with the goal of completing the project on time and within budget while minimizing disruptions to travelers. The project charter outlines the project overview, duration (211 days), and a budget estimate of £57.6 million, detailing costs across various project phases. Stakeholders are identified, including internal (project manager, planner, HR) and external (suppliers, government) parties, along with their roles and responsibilities. The project acknowledges and addresses potential risks. The project is broken down into phases of initiation, planning, execution, and closure. The project includes comprehensive resource, financial, quality, acceptance, communication, and procurement plans. It also highlights key assumptions, such as adherence to timelines and budgets, and constraints, including time, cost, and scope limitations. The project also provides detailed timelines and budget breakdowns for each phase of the project.

Running head: REFURBISHING HEATHROW TERMINAL
Project Name: Refurbishing Heathrow Terminal
Name of the Student
Name of the University
Author’s Note
Project Name: Refurbishing Heathrow Terminal
Name of the Student
Name of the University
Author’s Note
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1
REFURBISHING HEATHROW TERMINAL
Table of Contents
Introduction......................................................................................................................................2
1. Discussion....................................................................................................................................2
1.1 Project scope..........................................................................................................................2
1.2. Project charter.......................................................................................................................3
1.2.1 Project overview.............................................................................................................3
1.2.2 Duration..........................................................................................................................3
1.2.3 Budget estimate..............................................................................................................5
1.2.4 Assumptions and Constraints.......................................................................................10
1.3 Project Stakeholders............................................................................................................11
1.3.1 Roles and responsibilities of the stakeholders..............................................................11
1.4. Project risks........................................................................................................................14
Conclusion.....................................................................................................................................21
Bibliography..................................................................................................................................22
REFURBISHING HEATHROW TERMINAL
Table of Contents
Introduction......................................................................................................................................2
1. Discussion....................................................................................................................................2
1.1 Project scope..........................................................................................................................2
1.2. Project charter.......................................................................................................................3
1.2.1 Project overview.............................................................................................................3
1.2.2 Duration..........................................................................................................................3
1.2.3 Budget estimate..............................................................................................................5
1.2.4 Assumptions and Constraints.......................................................................................10
1.3 Project Stakeholders............................................................................................................11
1.3.1 Roles and responsibilities of the stakeholders..............................................................11
1.4. Project risks........................................................................................................................14
Conclusion.....................................................................................................................................21
Bibliography..................................................................................................................................22

2
REFURBISHING HEATHROW TERMINAL
Introduction
The project reflects on “Refurbishing Heathrow Airport Terminal 1”, which is one of the
largest international airports in the world. The main aim of the project is to complete
refurbishment of Heathrow airport terminal 1 on proper time and budget, without creating
disruptions to the public who are travelling. It is identified that the Terminal 1 of Heathrow
Airport is 40 years old and it was only utilized for short-distance European flights. Therefore, it
is analyzed that the Terminal 1 of the Heathrow Airport needs refurbishment in order to resolve
issues that mainly occur due to its outdated infrastructure. In the year 2004, BAA airport was
mainly tasked with the refurbishment of Terminal 1 of the Heathrow Airport. During
refurbishment of the airport, the terminal was kept opened to 20 million annual travelers. It is
identified that the project team needs to resolve number of challenges as well as unexpected
problems that mainly occurs during refurbishment.
The paper elaborates scope, budget as well as time that is needed for completing the
project. The paper also identifies the stakeholders who are associated with the project. It is
identified that the project faces number of risks which must be resolved properly.
1. Discussion
1.1 Project scope
The scope of the project is categorized into in-scope and out-scope. The in-scope of the
project includes refurbishment of Heathrow Airport Terminal 1, renovation of baggage and
check in-areas, critique project planning and initiation phase, completion of project on time and
budget and no disruption to the public who are travelling. On the other out scope of the project
REFURBISHING HEATHROW TERMINAL
Introduction
The project reflects on “Refurbishing Heathrow Airport Terminal 1”, which is one of the
largest international airports in the world. The main aim of the project is to complete
refurbishment of Heathrow airport terminal 1 on proper time and budget, without creating
disruptions to the public who are travelling. It is identified that the Terminal 1 of Heathrow
Airport is 40 years old and it was only utilized for short-distance European flights. Therefore, it
is analyzed that the Terminal 1 of the Heathrow Airport needs refurbishment in order to resolve
issues that mainly occur due to its outdated infrastructure. In the year 2004, BAA airport was
mainly tasked with the refurbishment of Terminal 1 of the Heathrow Airport. During
refurbishment of the airport, the terminal was kept opened to 20 million annual travelers. It is
identified that the project team needs to resolve number of challenges as well as unexpected
problems that mainly occurs during refurbishment.
The paper elaborates scope, budget as well as time that is needed for completing the
project. The paper also identifies the stakeholders who are associated with the project. It is
identified that the project faces number of risks which must be resolved properly.
1. Discussion
1.1 Project scope
The scope of the project is categorized into in-scope and out-scope. The in-scope of the
project includes refurbishment of Heathrow Airport Terminal 1, renovation of baggage and
check in-areas, critique project planning and initiation phase, completion of project on time and
budget and no disruption to the public who are travelling. On the other out scope of the project
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3
REFURBISHING HEATHROW TERMINAL
does not provide training facility to the workers of the organization and the scope creep for the
project quality is not maintained.
1.2. Project charter
1.2.1 Project overview
It is identified that terminal 1 of Heathrow Airport needs refurbishment as the terminal is
40 years old and its infrastructure is outdated. BAA Airport Ltd. was mainly tasked with the
refurbishment in order to update the infrastructure of the terminal. As the project manager wants
to complete the entire project on proper time and budget without creating disruption for the
people who are travelling therefore the terminal was kept opened to 20 million annual travelers.
It is identified that the successful completion of this project is considered as an enabler in order
to complete the transformation properly. There are numerous factors that are mainly associated
with the project which creates issue for the project and helps in making success one of the big
challenges..
1.2.2 Duration
The time that is needed for completing the project successfully is around 211 days. The
table below shows the duration that is needed for completing each of the project activity. In
addition to this, the table below also reflects the initiation as well as ending date of the project
activity.
WBS Task Name Duration Start Finish
0
Refurbishing Heathrow
Airport Terminal
211 days Tue 10/16/07 Tue 9/2/08
1 Project initiation phase 84 days Tue 10/16/07 Fri 3/7/08
REFURBISHING HEATHROW TERMINAL
does not provide training facility to the workers of the organization and the scope creep for the
project quality is not maintained.
1.2. Project charter
1.2.1 Project overview
It is identified that terminal 1 of Heathrow Airport needs refurbishment as the terminal is
40 years old and its infrastructure is outdated. BAA Airport Ltd. was mainly tasked with the
refurbishment in order to update the infrastructure of the terminal. As the project manager wants
to complete the entire project on proper time and budget without creating disruption for the
people who are travelling therefore the terminal was kept opened to 20 million annual travelers.
It is identified that the successful completion of this project is considered as an enabler in order
to complete the transformation properly. There are numerous factors that are mainly associated
with the project which creates issue for the project and helps in making success one of the big
challenges..
1.2.2 Duration
The time that is needed for completing the project successfully is around 211 days. The
table below shows the duration that is needed for completing each of the project activity. In
addition to this, the table below also reflects the initiation as well as ending date of the project
activity.
WBS Task Name Duration Start Finish
0
Refurbishing Heathrow
Airport Terminal
211 days Tue 10/16/07 Tue 9/2/08
1 Project initiation phase 84 days Tue 10/16/07 Fri 3/7/08
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4
REFURBISHING HEATHROW TERMINAL
1.1 Developing business case 22 days Tue 10/16/07 Mon 11/19/07
1.2 undertaking feasibility study 24 days Tue 11/20/07 Fri 12/21/07
1.3
Establishing the terms of
references
18 days Mon 12/24/07 Fri 1/25/08
1.4 Setting up a project office 28 days Mon 12/24/07 Wed 1/30/08
1.5 Performing phase review 20 days Mon 1/28/08 Fri 3/7/08
2 Planning phase 64 days Mon 1/28/08 Thu 4/24/08
2.1 Creating resource plan 32 days Mon 1/28/08 Tue 3/11/08
2.2 Creating financial plan 33 days Thu 1/31/08 Mon 3/17/08
2.3 Creating quality plan 35 days Thu 1/31/08 Wed 3/19/08
2.4 Creating acceptance plan 34 days Mon 3/10/08 Thu 4/24/08
2.5 Creating communication plan 27 days Mon 3/10/08 Tue 4/15/08
2.6 Creating procurement plan 30 days Wed 3/12/08 Tue 4/22/08
2.7 Contracting with the suppliers 32 days Wed 3/12/08 Thu 4/24/08
2.8 Performing phase review 27 days Tue 3/18/08 Wed 4/23/08
3 Project execution phase 119 days Thu 3/20/08 Tue 9/2/08
3.1 Building deliverables 40 days Thu 3/20/08 Wed 5/14/08
3.2 Monitoring and control 100 days Wed 4/16/08 Tue 9/2/08
3.2.1
Performing time
management
44 days Fri 4/25/08 Wed 6/25/08
3.2.2 Performing cost management 45 days Wed 4/16/08 Tue 6/17/08
3.2.3 Performing quality 48 days Wed 4/23/08 Fri 6/27/08
REFURBISHING HEATHROW TERMINAL
1.1 Developing business case 22 days Tue 10/16/07 Mon 11/19/07
1.2 undertaking feasibility study 24 days Tue 11/20/07 Fri 12/21/07
1.3
Establishing the terms of
references
18 days Mon 12/24/07 Fri 1/25/08
1.4 Setting up a project office 28 days Mon 12/24/07 Wed 1/30/08
1.5 Performing phase review 20 days Mon 1/28/08 Fri 3/7/08
2 Planning phase 64 days Mon 1/28/08 Thu 4/24/08
2.1 Creating resource plan 32 days Mon 1/28/08 Tue 3/11/08
2.2 Creating financial plan 33 days Thu 1/31/08 Mon 3/17/08
2.3 Creating quality plan 35 days Thu 1/31/08 Wed 3/19/08
2.4 Creating acceptance plan 34 days Mon 3/10/08 Thu 4/24/08
2.5 Creating communication plan 27 days Mon 3/10/08 Tue 4/15/08
2.6 Creating procurement plan 30 days Wed 3/12/08 Tue 4/22/08
2.7 Contracting with the suppliers 32 days Wed 3/12/08 Thu 4/24/08
2.8 Performing phase review 27 days Tue 3/18/08 Wed 4/23/08
3 Project execution phase 119 days Thu 3/20/08 Tue 9/2/08
3.1 Building deliverables 40 days Thu 3/20/08 Wed 5/14/08
3.2 Monitoring and control 100 days Wed 4/16/08 Tue 9/2/08
3.2.1
Performing time
management
44 days Fri 4/25/08 Wed 6/25/08
3.2.2 Performing cost management 45 days Wed 4/16/08 Tue 6/17/08
3.2.3 Performing quality 48 days Wed 4/23/08 Fri 6/27/08

5
REFURBISHING HEATHROW TERMINAL
management
3.2.4
Performing change
management
50 days Fri 4/25/08 Thu 7/3/08
3.2.5
Performing communication
management
54 days Thu 4/24/08 Tue 7/8/08
3.2.6 Performing risk management 57 days Thu 5/15/08 Fri 8/1/08
3.2.7
Performing issue
management
48 days Thu 6/26/08 Mon 9/1/08
3.2.8
Performing procurement
management
49 days Thu 6/26/08 Tue 9/2/08
3.2.9
Performing acceptance
management
46 days Wed 6/18/08 Wed 8/20/08
3.2.10 Performing phase review 45 days Wed 6/18/08 Tue 8/19/08
4 Closure phase 22 days Mon 6/30/08 Tue 7/29/08
4.1 Stakeholder sign off 22 days Mon 6/30/08 Tue 7/29/08
4.2 Performing project closure 12 days Fri 7/4/08 Mon 7/21/08
4.3 Reviewing project completion 6 days Wed 7/9/08 Wed 7/16/08
1.2.3 Budget estimate
The estimated budget that is needed for completing the project is around 57.6 million.
The table below reflects that the budget that is needed for completing the activities of the project
with the help of project stakeholders is around £5,943,960.00 however the remaining budget is
utilized for the materials of the project or for other activities that are quite necessary for
REFURBISHING HEATHROW TERMINAL
management
3.2.4
Performing change
management
50 days Fri 4/25/08 Thu 7/3/08
3.2.5
Performing communication
management
54 days Thu 4/24/08 Tue 7/8/08
3.2.6 Performing risk management 57 days Thu 5/15/08 Fri 8/1/08
3.2.7
Performing issue
management
48 days Thu 6/26/08 Mon 9/1/08
3.2.8
Performing procurement
management
49 days Thu 6/26/08 Tue 9/2/08
3.2.9
Performing acceptance
management
46 days Wed 6/18/08 Wed 8/20/08
3.2.10 Performing phase review 45 days Wed 6/18/08 Tue 8/19/08
4 Closure phase 22 days Mon 6/30/08 Tue 7/29/08
4.1 Stakeholder sign off 22 days Mon 6/30/08 Tue 7/29/08
4.2 Performing project closure 12 days Fri 7/4/08 Mon 7/21/08
4.3 Reviewing project completion 6 days Wed 7/9/08 Wed 7/16/08
1.2.3 Budget estimate
The estimated budget that is needed for completing the project is around 57.6 million.
The table below reflects that the budget that is needed for completing the activities of the project
with the help of project stakeholders is around £5,943,960.00 however the remaining budget is
utilized for the materials of the project or for other activities that are quite necessary for
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6
REFURBISHING HEATHROW TERMINAL
executing the project successfully. Moreover, it is analyzed that the budget of the project must be
monitored properly in order to complete the various activities of the project successfully within
time.
Task Name Duration Start Finish Cost
Refurbishing Heathrow
Airport Terminal 1
project
211 days Tue 10/16/07 Tue 8/5/08 £5,943,960.00
Project initiation
phase
84 days Tue 10/16/07 Fri 2/8/08 £709,080.00
Developing business
case
22 days Tue 10/16/07 Wed 11/14/07 £144,320.00
undertaking feasibility
study
24 days Thu 11/15/07 Tue 12/18/07 £97,920.00
Establishing the
terms of references
18 days Wed 12/19/07 Fri 1/11/08 £163,000.00
Setting up a project
office
28 days Wed 12/19/07 Fri 1/25/08 £175,840.00
Performing phase
review
20 days Mon 1/14/08 Fri 2/8/08 £128,000.00
Planning phase 70 days Mon 1/14/08 Fri 4/18/08 £1,632,840.00
Creating resource
plan
32 days Mon 1/14/08 Tue 2/26/08 £197,120.00
REFURBISHING HEATHROW TERMINAL
executing the project successfully. Moreover, it is analyzed that the budget of the project must be
monitored properly in order to complete the various activities of the project successfully within
time.
Task Name Duration Start Finish Cost
Refurbishing Heathrow
Airport Terminal 1
project
211 days Tue 10/16/07 Tue 8/5/08 £5,943,960.00
Project initiation
phase
84 days Tue 10/16/07 Fri 2/8/08 £709,080.00
Developing business
case
22 days Tue 10/16/07 Wed 11/14/07 £144,320.00
undertaking feasibility
study
24 days Thu 11/15/07 Tue 12/18/07 £97,920.00
Establishing the
terms of references
18 days Wed 12/19/07 Fri 1/11/08 £163,000.00
Setting up a project
office
28 days Wed 12/19/07 Fri 1/25/08 £175,840.00
Performing phase
review
20 days Mon 1/14/08 Fri 2/8/08 £128,000.00
Planning phase 70 days Mon 1/14/08 Fri 4/18/08 £1,632,840.00
Creating resource
plan
32 days Mon 1/14/08 Tue 2/26/08 £197,120.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7
REFURBISHING HEATHROW TERMINAL
Creating financial
plan
33 days Mon 1/28/08 Wed 3/12/08 £208,560.00
Creating quality plan 35 days Mon 1/28/08 Fri 3/14/08 £225,400.00
Creating acceptance
plan
34 days Mon 2/11/08 Thu 3/27/08 £142,800.00
Creating
communication plan
27 days Mon 2/11/08 Tue 3/18/08 £233,280.00
Creating procurement
plan
30 days Wed 2/27/08 Tue 4/8/08 £198,000.00
Contracting with the
suppliers
32 days Wed 2/27/08 Thu 4/10/08 £207,360.00
Performing phase
review
27 days Thu 3/13/08 Fri 4/18/08 £220,320.00
Project execution
phase
102 days Mon 3/17/08 Tue 8/5/08 £3,508,920.00
Building deliverables 40 days Mon 3/17/08 Fri 5/9/08 £257,600.00
Monitoring and
control
100 days Wed 3/19/08 Tue 8/5/08 £3,251,320.00
Performing time
management
44 days Fri 3/28/08 Wed 5/28/08 £360,800.00
Performing cost
management
45 days Wed 3/19/08 Tue 5/20/08 £293,400.00
Performing quality 48 days Wed 4/9/08 Fri 6/13/08 £289,920.00
REFURBISHING HEATHROW TERMINAL
Creating financial
plan
33 days Mon 1/28/08 Wed 3/12/08 £208,560.00
Creating quality plan 35 days Mon 1/28/08 Fri 3/14/08 £225,400.00
Creating acceptance
plan
34 days Mon 2/11/08 Thu 3/27/08 £142,800.00
Creating
communication plan
27 days Mon 2/11/08 Tue 3/18/08 £233,280.00
Creating procurement
plan
30 days Wed 2/27/08 Tue 4/8/08 £198,000.00
Contracting with the
suppliers
32 days Wed 2/27/08 Thu 4/10/08 £207,360.00
Performing phase
review
27 days Thu 3/13/08 Fri 4/18/08 £220,320.00
Project execution
phase
102 days Mon 3/17/08 Tue 8/5/08 £3,508,920.00
Building deliverables 40 days Mon 3/17/08 Fri 5/9/08 £257,600.00
Monitoring and
control
100 days Wed 3/19/08 Tue 8/5/08 £3,251,320.00
Performing time
management
44 days Fri 3/28/08 Wed 5/28/08 £360,800.00
Performing cost
management
45 days Wed 3/19/08 Tue 5/20/08 £293,400.00
Performing quality 48 days Wed 4/9/08 Fri 6/13/08 £289,920.00

8
REFURBISHING HEATHROW TERMINAL
management
Performing change
management
50 days Fri 4/11/08 Thu 6/19/08 £310,000.00
Performing
communication
management
54 days Mon 4/21/08 Thu 7/3/08 £336,960.00
Performing risk
management
57 days Mon 5/12/08 Tue 7/29/08 £373,920.00
Performing issue
management
48 days Thu 5/29/08 Mon 8/4/08 £309,120.00
Performing
procurement management
49 days Thu 5/29/08 Tue 8/5/08 £403,760.00
Performing
acceptance management
46 days Wed 5/21/08 Wed 7/23/08 £296,240.00
Performing phase
review
45 days Wed 5/21/08 Tue 7/22/08 £277,200.00
Closure phase 22 days Mon 6/16/08 Tue 7/15/08 £93,120.00
Stakeholder sign off 22 days Mon 6/16/08 Tue 7/15/08 £52,800.00
Performing project
closure
12 days Fri 6/20/08 Mon 7/7/08 £25,920.00
Reviewing project
completion
6 days Fri 7/4/08 Fri 7/11/08 £14,400.00
REFURBISHING HEATHROW TERMINAL
management
Performing change
management
50 days Fri 4/11/08 Thu 6/19/08 £310,000.00
Performing
communication
management
54 days Mon 4/21/08 Thu 7/3/08 £336,960.00
Performing risk
management
57 days Mon 5/12/08 Tue 7/29/08 £373,920.00
Performing issue
management
48 days Thu 5/29/08 Mon 8/4/08 £309,120.00
Performing
procurement management
49 days Thu 5/29/08 Tue 8/5/08 £403,760.00
Performing
acceptance management
46 days Wed 5/21/08 Wed 7/23/08 £296,240.00
Performing phase
review
45 days Wed 5/21/08 Tue 7/22/08 £277,200.00
Closure phase 22 days Mon 6/16/08 Tue 7/15/08 £93,120.00
Stakeholder sign off 22 days Mon 6/16/08 Tue 7/15/08 £52,800.00
Performing project
closure
12 days Fri 6/20/08 Mon 7/7/08 £25,920.00
Reviewing project
completion
6 days Fri 7/4/08 Fri 7/11/08 £14,400.00
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

9
REFURBISHING HEATHROW TERMINAL
1.2.4 Assumptions and Constraints
Assumptions: The assumptions that are made in this project are as follows:
The project of refurbishing the Terminal 1 of the airport must be completed within the
estimated time and budget
The project does not create any type of disruption for the people who are travelling
The project must follow the scope in order to achieve the goals as well as objectives
of the project.
The complexities of the project will be resolved and the project will be helpful in
providing proper travelling experience to the people.
Constraints: The constraints of the project are as follows:
Time: The time that is estimated by the project must be utilized for completing the entire
project successfully within the estimated time and budget. If the project is completed within the
estimated time then the chances of occurring financial pressure on the organization also reduces.
Cost: The project must e completed successfully within the budget that is estimated. It is
quite important to complete their project within the estimated budget in order to avoid different
types of financial challenges.
Scope: The project must follow the scope while proceeding with the execution of the
project. If the scope of the project is followed then the project will be able to achieve its goals as
well as objectives. If the scope of the project is not maintained then it will be quite difficult for
the project managers to complete the entire project within the estimated time and budget.
REFURBISHING HEATHROW TERMINAL
1.2.4 Assumptions and Constraints
Assumptions: The assumptions that are made in this project are as follows:
The project of refurbishing the Terminal 1 of the airport must be completed within the
estimated time and budget
The project does not create any type of disruption for the people who are travelling
The project must follow the scope in order to achieve the goals as well as objectives
of the project.
The complexities of the project will be resolved and the project will be helpful in
providing proper travelling experience to the people.
Constraints: The constraints of the project are as follows:
Time: The time that is estimated by the project must be utilized for completing the entire
project successfully within the estimated time and budget. If the project is completed within the
estimated time then the chances of occurring financial pressure on the organization also reduces.
Cost: The project must e completed successfully within the budget that is estimated. It is
quite important to complete their project within the estimated budget in order to avoid different
types of financial challenges.
Scope: The project must follow the scope while proceeding with the execution of the
project. If the scope of the project is followed then the project will be able to achieve its goals as
well as objectives. If the scope of the project is not maintained then it will be quite difficult for
the project managers to complete the entire project within the estimated time and budget.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

10
REFURBISHING HEATHROW TERMINAL
1.3 Project Stakeholders
The stakeholders of the project are mainly categorized into internal stakeholders as well
as external stakeholders.
Internal stakeholders
The internal stakeholders of the project includes project manager, project planner, human
resource manager, project analyst, contractor, project team as well as sponsor
External stakeholders
The external stakeholders of the project includes suppliers, local communities, government
as well as creditor
1.3.1 Roles and responsibilities of the stakeholders
1.3.1.1 Internal stakeholders
Project manager
The project managers are the person who takes the responsibility of initiating, planning
designing, executing as well as monitoring and controlling the entire project. They have the
responsibility of preparing as well as maintaining the project stages as well as various types of
exception plans as needed. They also engage in maintaining an awareness of potential
interdependencies with different projects as well as with their impact. In addition to this, they are
also responsible of identifying as well as obtaining both advice as well as support that is needed
in order to plan, manage as well as control the project effectively.
Project planner
REFURBISHING HEATHROW TERMINAL
1.3 Project Stakeholders
The stakeholders of the project are mainly categorized into internal stakeholders as well
as external stakeholders.
Internal stakeholders
The internal stakeholders of the project includes project manager, project planner, human
resource manager, project analyst, contractor, project team as well as sponsor
External stakeholders
The external stakeholders of the project includes suppliers, local communities, government
as well as creditor
1.3.1 Roles and responsibilities of the stakeholders
1.3.1.1 Internal stakeholders
Project manager
The project managers are the person who takes the responsibility of initiating, planning
designing, executing as well as monitoring and controlling the entire project. They have the
responsibility of preparing as well as maintaining the project stages as well as various types of
exception plans as needed. They also engage in maintaining an awareness of potential
interdependencies with different projects as well as with their impact. In addition to this, they are
also responsible of identifying as well as obtaining both advice as well as support that is needed
in order to plan, manage as well as control the project effectively.
Project planner

11
REFURBISHING HEATHROW TERMINAL
The project planners are the people who are mainly responsible of defining as well as
developing the various objectives as well as goals of the project. They also engage in analyzing
as well as monitoring the effectiveness of the project for attaining the milestones of the project.
They are also responsible of planning, co-coordinating as well as monitoring activities that are
mainly assigned for developing and implementing processes, procedures and the systems of the
project. Additionally, it is identified that the project planner also helps in overseeing schedules as
well as helps in planning risk management plan in order provide proper and serious warnings to
the results that mainly hinders the success of the project.
Human Resource manager
The human resource managers are the persons who are responsible of determining the
resources that are needed in project. They also engages in creating proper directory for the
project team and assists in creating job description for the project stakeholders as well as project
team member. They also make sure that all the project roles as well as responsibilities are
properly assigned to the team members of the project. In addition to this, the human resource
manager is also responsible of understanding the project team member so that they can provide
them proper help as well as support for completing the responsibilities and roles that are
assigned.
Project analyst
Project analyst is the person who is mainly responsible of working on the projects of the
project manager. It is identified that the project analyst mainly engages in taking proper decision
on different types of critical decisions. They are also responsible of creating, disbursing as well
as managing reports that are mainly related with the project. Additionally, they also help in
REFURBISHING HEATHROW TERMINAL
The project planners are the people who are mainly responsible of defining as well as
developing the various objectives as well as goals of the project. They also engage in analyzing
as well as monitoring the effectiveness of the project for attaining the milestones of the project.
They are also responsible of planning, co-coordinating as well as monitoring activities that are
mainly assigned for developing and implementing processes, procedures and the systems of the
project. Additionally, it is identified that the project planner also helps in overseeing schedules as
well as helps in planning risk management plan in order provide proper and serious warnings to
the results that mainly hinders the success of the project.
Human Resource manager
The human resource managers are the persons who are responsible of determining the
resources that are needed in project. They also engages in creating proper directory for the
project team and assists in creating job description for the project stakeholders as well as project
team member. They also make sure that all the project roles as well as responsibilities are
properly assigned to the team members of the project. In addition to this, the human resource
manager is also responsible of understanding the project team member so that they can provide
them proper help as well as support for completing the responsibilities and roles that are
assigned.
Project analyst
Project analyst is the person who is mainly responsible of working on the projects of the
project manager. It is identified that the project analyst mainly engages in taking proper decision
on different types of critical decisions. They are also responsible of creating, disbursing as well
as managing reports that are mainly related with the project. Additionally, they also help in
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 20
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.