Comprehensive Report: Relocation Project Management and Execution

Verified

Added on  2020/10/22

|18
|4164
|133
Report
AI Summary
This report details a project management plan for a company relocation, focusing on the objectives of cost reduction and profit enhancement. The report outlines the determination of project scope, including time and cost estimations, and proposes the use of the PRINCE2 methodology for effective project management. It covers project feasibility, management structures, roles and responsibilities, and includes a detailed project plan with resource allocation and timelines. The report also explores alternative project team structures, quality management procedures, and risk management strategies, addressing potential issues in the final stages. It concludes with an assessment of essential tasks and a discussion of project monitoring and appraisal, providing a comprehensive overview of the relocation project's planning, execution, and control.
Document Page
PROJECT
MANAGEMENT
Table of Contents
INTRODUCTION...........................................................................................................................1
ACTIVITY 1....................................................................................................................................1
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Determination of projects on the basis of appraisal of business objectives associated with
relocation................................................................................................................................1
Sub divisions of project and estimation of time and cost required for project.......................2
ACTIVITY 2....................................................................................................................................4
Suitable and relevant project methodology............................................................................4
Feasibility of project...............................................................................................................5
Structure for management and administration of project.......................................................5
Roles and responsibilities of Project Staff..............................................................................6
ACTIVITY 3....................................................................................................................................7
Detailed Project Plan..............................................................................................................7
ACTIVITY 4....................................................................................................................................8
Alternate Project Team Structures..........................................................................................8
Quality Management Procedures.........................................................................................10
Procedures for management of Project Change Proposals...................................................11
ACTIVITY 5..................................................................................................................................11
Risks and issues that may impede project............................................................................11
Issues and risks that may be encountered in final project stages.........................................12
Monitoring and appraising of the project activities..............................................................13
ACTIVITY 6..................................................................................................................................13
Assessment of essential project tasks to be completed in final stage...................................13
CONCLUSION..............................................................................................................................14
REFERENCES..............................................................................................................................15
Document Page
Document Page
INTRODUCTION
Project can be referred to as a group activity that is designed and implemented with an
aim to attain the desired outcomes. In this regard, project management is the utilisation of skills,
knowledge and competence for the successful formulation of project in an effective and efficient
manner. The present report is based upon the feasible implementation of a relocation project.
This report comprises of outcomes of project along with an appropriate methodology and
relevant human resource structure. Besides this, monitoring and controlling procedures are
included in accordance with the discovery of managerial aspects. Lastly, risk management is
covered together with essential steps for project execution.
ACTIVITY 1
Determination of projects on the basis of appraisal of business objectives associated with
relocation
An organisation intends to relocate itself to locations nearby Banbury, Oxfordshire. The
primary objective of this relocation project is to carry out reduction of cost and simultaneously
enabling increment of profitability by 10%.
Constant assessment and evaluation of operational procedures is necessary for the
success and growth of business. This examination should be carried out in accordance with the
suitable and relevant project management techniques while taking into account the trends of
company and the cost benefit analysis. The selected methodology for carrying out relocation
should have the capacity to increase the quality of project, thereby effectively driving it towards
the desired output by acting in compliance with organisational requirements. This will tend to
make the process of monitoring as well as controlling more easy and provide assistance to the
project manager to execute the relocation in a smaller time span with optimum utilisation of
resources. In context of the present project, organisational relocation is assessed and analysed to
effectively achieve the goal of business growth and expansion. In addition to this, it is essential
to constantly review the operations as well as processes of entity in order to identify suitable and
relevant projects for meeting the objectives of company. In this context, management can carry
out cost benefit analysis consequently leading to provision of detailed data about the relocation.
Besides this, resources, budget, accountability and the time frame of project need to be taken into
account while selecting a project. Furthermore, project manager can make arrangements for
1
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
alternate projects by way of which goals and objectives can be attained in the targeted course of
time. This fosters the execution of project on the right point of time.
Sub divisions of project and estimation of time and cost required for project
It is the responsibility of a project manager to lay emphasis upon the distribution of work
in order to ensure effective and efficient project completion. In project management, distribution
of tasks is regarded to be of prime importance. It is believed that if tasks are properly divided
into stages and assigned to associated departments, efficiency is fostered. To facilitate this, a
timescale will be constructed for relocation on the basis of Work Breakdown Structure. This will
serve as a guidance for the entity to execute all the project activities within the stipulated time
frame. The project manager will thus be able to identify the essential resources after listing of all
the operational tasks. For relocation, a number of resources will be required such as technology,
human and financial. Such resources will be adequately assigned to all the operational tasks with
an aim to increase the output. In addition to this, budget has been made for feasibly carrying out
the relocation, which is as follows:-
RESOURCE BUDGET (in €)
Land 224
Materials 335
Human Resources 221
TOTAL 780
2
Document Page
There are a number of resources which are key to relocation such as human, financial and
physical. Here, the project team needs training in order to carry out optimum utilisation as well
as allocation of resources. Besides this, communication will be set with the team and they will be
briefed about their accountability and responsibilities accordingly. Further, all the members will
report about their activities to project manager. Communication is also set by project manager
who enables smooth flow of information within the team.
3
Document Page
In relation to Critical Path, all the project activities will be executed within a time span of
26 days. This will ensure completion of activities within stipulated course of time.
ACTIVITY 2
Suitable and relevant project methodology
Relocation of company is a complex and challenging task as it is a largely standardised
procedure which requires huge investment. The below mentioned methodologies can be executed
for the formulation of project:-
Waterfall Project Management: This is a traditional approach which is used for handling
the project activities in a systematic and orderly manner. This kind of methodology is relevant
and suitable for large scale software development project.
Critical Chain Path: In contrast to the waterfall approach, this methodology emphasizes
upon tasks as well as schedules. This method seeks to allocate the resources to several
procedures regarded as being crucial. However, a sufficient quantum of resources is still left for
reassignment as per the requirements during the project tenure.
Prince2: This method, endorsed by British Government, is found to be process-oriented
seeking to divide project into multiple stages. These stages have their own set of procedures and
plans to be followed.
Agile Project Management: This project approach is generally opted when a project is
designed and devised for adoption of some changes. This is suitable for small software projects
or the projects with accelerated schedules of development.
For the current project of relocation, Prince2 methodology will be suitable and relevant as
this technique is associated with monitoring, management and control of project activities. It is a
process-oriented approach that aids in enhancing the overall performance. This also provides
assistance in achieving the organisational goals and objectives in a timely manner. By taking into
consideration the stages of this methodology, project manager can carry out assessment of
relocation elements and infrastructure so as to make sure that the activities are executed in a
desirable manner. Prince2 facilitates a common approach of team towards the work. This fosters
reduction in time required for selection of new employees.
4
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Feasibility of project
It is essential to assess the feasibility of every project. Feasibility can be referred to as the
analysis of scope or the potential of project. Through this study, management can undertake
effective decisions. The relocation project also needs to undergo feasibility analysis and thus,
this is carried out as follows:-
Financial Feasibility: This project is financially feasible as funds for this will be
generated from the available funds of company.
Technological Feasibility: While carrying out relocation, management will ensure that
adequate and relevant IT systems are adopted by business to facilitate increment in earning
capacity of organisation.
Risk Management: Prince2 methodology will be used in this project to ensure minimal
risk and the elimination of existing barriers or risks to ensure effective project performance.
Resource Feasibility: The project of relocation will optimally utilise the resources in
order to ensure the adequacy and sufficiency of resources.
Project Feasibility: This project is feasible as here efforts are taken to ensure that cost is
reduced and profitability is enhanced. Company holds necessary resources to efficiently execute
the relocation in a timely manner.
Structure for management and administration of project
PRINCE2 methodology has been taken into use for the current project. The description of
several stages of project for carrying out relocation of company office is given as follows:-
Project initiation: The beginning of project will comprise of planning for relocation of
company's office together with the analysis of solutions to ensure continuation of project. A
number of approaches will be used to carry out this analysis.
Direction of Project: This constitutes the procedure for monitoring and control of
relocation project so as to lead it towards a relevant direction.
Project Implementation: Here, planning is implemented in the project under the
jurisdiction of project manager.
Project control: This stage includes the constant examination as well as evaluation of
executed actions related with relocation so as to gain knowledge about the areas where
improvements can be incorporated.
5
Document Page
Management of Product delivery: The improvement actions decided upon in the
previous stage are scheduled throughout the overall planning procedure.
Project closet: This is the last stage of project wherein relocation of office will finally
take place and a test will be conducted for carrying out comparison of actual and desirable
outcomes.
(Source: PRINCE 2 Methodology, 2019)
Roles and responsibilities of Project Staff
Project Manager: The management as well as coordination of activities is carried out by
the Project Manager. They should have the ability to synchronise all the activities and reporting
the progress to senior executives. Also, they are responsible for making budget and delegating
the powers among team members. In this regard, the supervision of activities is an essential part
of the responsibilities of Project Manager.
6
Illustration 1: PRINCE 2 Methodology
Document Page
Top Management: The decision making powers in relation to execution of a project and
allocation of resources vests in the hands of top management.
Administrative Department: The personnel belonging to this unit is responsible for
executing the tasks stipulated by the top management of company.
Technical Personnel: The personnel belonging to this category within the project team is
responsible for carrying out a number of technical tests and for maintaining the system.
ACTIVITY 3
Detailed Project Plan
A project plan can be said to be an approved formal documentation that strives to render
a direction to complete a specific project. Also, it can be referred to as the sequential set of
activities that gives strategic direction to ensure the attainment of organisational goals and
objectives. The crucial elements of the relocation project of company’s office are briefly
described below:-
Value Proposition: The primary objective of an organisation is to carry out business
growth and expansion. Furthermore, it also targets to increase its profits and revenues in future
prospect. To execute this, technological approaches will be implemented to formulate the
relocation.
Sponsorship: The current project is being sponsored by Board of Directors and
management of company.
Accountability and responsibilities: All the team members will be accountable to Project
Manager. Each of the participants will be responsible for their piece of work. Further, the
execution of whole project will be under the jurisdiction of Project Manager.
Resource Allocation: The manager of company has to undertake the responsibility of
optimum utilisation of resources such that they are allocated to necessary activities only.
Time & Milestone: This is associated with procurement as well as hiring of labour force
for the purpose of executing relocation. This comprises of activities related to research and trend
analysis of labour marketplace.
7
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
ACTIVITY 4
Alternate Project Team Structures
The alternate team structures that can be considered by Project Manager for execution of
relocation are given below:-
Functional Structure
This project team structure is hierarchal in nature as here, the activities of sub-
departments are under the jurisdiction of main departments.
Figure 1: Hierarchal Project Structure
(Source: Hierarchal Project Structure, 2019)
Hybrid or Matrix Structure
This team structure is formulated by integrating the characteristics of project based and
functional structures. Here, correlation is set amidst activities such that better coordination can
be facilitated.
8
Document Page
Figure 2: Matrix Structure
(Source: Matrix Structure, 2019)
Project Based Structure
Here, an individual project team is separately developed consisting of experts from
diverse set of fields. Tasks are assigned to separate teams and are executed by experts.
Figure 3: Project Based Structure
(Source: Project Based Structure, 2019)
9
chevron_up_icon
1 out of 18
circle_padding
hide_on_mobile
zoom_out_icon
[object Object]