This report details a student project focused on developing an early pedestrian detection system for the driving industry using IoT technology. The project aims to enhance road safety by preventing collisions, particularly when turning or reversing. The report includes an analysis of the project's background, goals, and objectives, as well as a comprehensive literature review. It outlines the project's requirements, specifications, and design, including the use of a thermal imaging camera, GY 271 compass, Arduino UNO, and Windows Azure for data storage and processing. The report also features a Gantt chart for project management, individual research approaches by team members, and a detailed budget. The project's design utilizes block diagrams to illustrate system architecture. The team's responsibilities are clearly defined, and the report addresses feedback from previous assignments, such as page numbering and citation issues. The document provides a detailed overview of the project's methodology, implementation, and expected outcomes, demonstrating the application of IoT technology to improve driving safety.
Document Page
Running head: REASEARCH MEATHODS AND PROJECT DESIGN
REASEARCH MEATHODS AND PROJECT DESIGN
Name of student
Name of university
Author’s note:
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
1
REASEARCH MEATHODS AND PROJECT DESIGN
Table of Contents
Comment updates...........................................................................................................2
Table of weekly activities..............................................................................................2
Responsibilities and roles of team members..................................................................3
Gantt chart......................................................................................................................6
Project design.................................................................................................................9
Project individual research approach...........................................................................11
Budget..........................................................................................................................15
Bibliography.................................................................................................................16
Document Page
2
REASEARCH MEATHODS AND PROJECT DESIGN
Comment updates
As per the feedback from the assignment 1, the page numbering was not done
properly which is majorly important for any document. The page number in the document
was required to be from the introduction that was the page number 1 and there was significant
feedback from the professor. The proper citation was missing from the introduction part
which has been briefly mentioned to practise to provide the proper recognition to the people
and the authors who have created the articles and the journals. In the research question
section there was another issue of the citation and the issue of citation missing. In the
research question section, the proper explanation of the research question was not provided
that is not acceptable as it does not provide the overview of what question is required for the
research and the reason why the document has been created. According to the professor, there
are several typing mistakes that are required to be corrected and it makes the document less
attractive and the credibility of the document is significantly decreased with constant
happening of the typing mistakes. Other than these sections, the document was above average
for presenting the report to the business manager.
Table of weekly activities
Weeks Activities
1 In the first week the groups had been formed. An approach was made to the
client regarding the various activities that would be included in the project.
2 All the team members were provided with the details of the client and the
introduction with client were done.
3 A meeting was conducted with the client. The evaluation of the background of
the project was done for the client.
4 The goal and the objective of the project was discussed and evaluated.
Document Page
3
REASEARCH MEATHODS AND PROJECT DESIGN
5 Work began on the requirements of the client and the analysis of the
requirements of the Pedestrian detection was done.
6 The project presentation and the functioning on the video presentation was done.
7 There was an efficient meeting with the discussion of assignment 2, and the
proper research methodology was determined.
Responsibilities and roles of team members
Name and student ID Week Responsibilities and the roles
Rajasekhar Polaka-
MIT173408
1
Initial activity of the group formation was done. Several
details of the client was gathered.
2 Worked on the individual topic of project.
3 Execution of the literature review was done.
4 Meeting with the client was done.
Name and student ID Week Responsibilities and the roles
Manisha Kolle-
MIT180076 1
The selection of the random group members was done
by subject coordinator and they were assigned to the
project.
2
The contacting to the group members was done for the
allocation of the specific time for the weekly client as
well as the supervisor meeting.
3 Commenced the preparation on the presentation on the
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
4
REASEARCH MEATHODS AND PROJECT DESIGN
project and also worked on the video.
4
Started the work on the assignment 2. The selection of
the topics was done.
5
The literature review has been submitted for the
assignment 1.
6
The preparation of the slides was done with help from
the supervisor.
Name and student ID Week Responsibilities and the roles
Praneeth Kumar
Desai Karanam-
MIT175014
1
The division of topics of the projects was divided
mutually among group from the assistance with
supervisor
2
The collection of the all the individual literature review
was done from group members
3 Submitted for grading
4 Initiated the presentation for the week 8
5 The finalisation of the video was done
Name and student ID Week Responsibilities and the roles
Chandrahas Reddy 1 Assisted in the compiling and the submitting the
Document Page
5
REASEARCH MEATHODS AND PROJECT DESIGN
Bumireddy-
MIT174741
literature review
2 Participated in the project supervisor meeting
3 Attended the supervisor meeting
4 Started on the working on assignment 2
Name and student ID Week Responsibilities and the roles
Madhu Kumar
Vattepu-
MIT173378
1
Had the meeting with the supervisor, narrowed the area
of the research
2 Initiated the working on the week 8 task
3
Working on the estimation of the project budget and the
project diagram
4 Individual research approach has been done
5
Literature review of each of the individuals was
circulated among the team members for getting the
feedback prior final submission of the final report
6
The scheduling was conducted for the client and the
supervisor meetings.
Gantt chart
WBS Task Name Duratio Start Finish Predecessors
Document Page
6
REASEARCH MEATHODS AND PROJECT DESIGN
n
0 Gnatt chart
144
days
Tue 19-03-19
Thu 03-10-
19
1 Research initiation phase 28 days Tue 19-03-19
Wed 24-04-
19
1.1 Process identification 4 days Tue 19-03-19 Fri 22-03-19
1.2
Appropriate identification of
employee
14 days Mon 25-03-19
Thu 11-04-
19
2
1.3
Investigation of standards and
the policies
5 days Mon 25-03-19 Fri 29-03-19 2
1.4 Justification of need of research 7 days Fri 12-04-19 Fri 19-04-19 4,3
1.5 Execution of feasibility study 3 days Mon 22-04-19
Wed 24-04-
19
5
2 Planning phase 68 days Mon 22-04-19
Wed 24-07-
19
2.1
Scope statement has been
defined
4 days Mon 22-04-19
Thu 25-04-
19
5
2.2 Large deliverables are divided 10 days Fri 26-04-19
Thu 09-05-
19
8
2.3 Identification of required tasks
for the production of
16 days Fri 10-05-19 Fri 31-05-19 9
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7
REASEARCH MEATHODS AND PROJECT DESIGN
deliverables
2.4 Task duration are defined 3 days Wed 17-07-19 Fri 19-07-19 10
2.5 Forecast the cost 3 days Mon 22-07-19
Wed 24-07-
19
11
3 execution phase 14 days Thu 25-07-19
Tue 13-08-
19
3.1 Following the developed plan 2 days Thu 25-07-19 Fri 26-07-19 12
3.2
Allocation of the tasks to the
team members
2 days Mon 29-07-19
Tue 30-07-
19
14
3.3 Effective monitoring of process 3 days Wed 31-07-19 Fri 02-08-19 15
3.4
Management of the contract
that is secured in the project
7 days Mon 05-08-19
Tue 13-08-
19
16
4 monitor and control 15 days Wed 14-08-19 Tue 03-09-
19
4.1 Evaluate research progress 8 days Wed 14-08-19 Fri 23-08-19 17
4.2 Measurement of quality of
deliverables
7 days Mon 26-08-19 Tue 03-09-
19
19
5 project closure 22 days Wed 04-09-19 Thu 03-10-
19
5.1 Ensure completion of the 8 days Wed 04-09-19 Fri 13-09-19 20
Document Page
8
REASEARCH MEATHODS AND PROJECT DESIGN
research deliverables
5.2
Close out the outstanding
contracts
7 days Mon 16-09-19
Tue 24-09-
19
22
5.3 Archive all paperwork 7 days Wed 25-09-19
Thu 03-10-
19
23
Figure: Gantt chart for the project
Source: (Created by author)
Document Page
9
REASEARCH MEATHODS AND PROJECT DESIGN
Project design
Figure: Project design using block diagram
Source: (Created by author)
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
10
REASEARCH MEATHODS AND PROJECT DESIGN
In the initial stages of the system of the IoT, the thermal camera has been used for the
detection of any kind of pedestrians on the side of the road and prevent the collision. The GY
271 compass has been used in the system which is the compass module that has been
designed for the low field magnetic sensing with the digital interface and it is ideal for
providing the precise heading information [2]. Both of these devices has been connected with
the Arduino UNO that is the open source microcontroller board that is based on the
Microchip ATmega328P microcontroller and it is developed by the Arduino.cc [3]. The
Arduino UNO utilises the Microchip ENC28J60 stand-alone Ethernet controller IC that
features the host for handing the requirements of the network protocol [4]. This data from the
microchip is displayed in the LCD using the router and it is also stored in the Windows Azure
for the further use.
Document Page
11
REASEARCH MEATHODS AND PROJECT DESIGN
Project individual research approach
Rajasekhar Polaka- MIT173408
Figure: project individual approach of Rajasekhar Polaka
Source: (Created by author)