This assignment presents a Project Control Plan prepared by a General Contractor for the Riverstone Two Office Building project. The plan is addressed to the Construction Manager and provides a comprehensive overview of project controls, including cost, schedule, submittals, documentation, quality control, and safety measures. The narrative details the organization of the construction project according to United States construction guidelines, with specific emphasis on cost management (labor, materials, equipment), schedule management, and quality assurance. The plan also includes an RFI (Request for Information) log, which documents clarifications and changes related to the project, such as material substitutions and design modifications. The assignment demonstrates the practical application of project management principles in a real-world construction scenario, ensuring efficient project execution and adherence to industry standards. The assignment also references the use of a construction submittal log and change order log to track project progress and modifications. Finally, the assignment includes citations from academic sources that support the concepts presented in the plan.
Document Page
Name:
Institution:
Unit:
Date:
From:
General Contractor;
Riverstone Construction Company.
P.O.Box 4567.
California, USA.
To
Construction Manager
Pacific Northwest Construction Company,
P. O. Box 6789,
California, United States
Date: 18th April 2020
Dear David Gunderson.
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
REF: RIVERSTONE TWO OFFICE BUILDING PROJECT CONTROL PLAN
Project overview
This construction project management plan narrative has been prepared for the construction of
the Riverstone Two Office Building Project on plot #1234, Pacific Northwest Area. The project
involves the construction of two office building buildings at Northwest corner of the intersection
with Washington Street, MA. Medium rise commercial buildings surround the construction site
the west, east and north
Construction involves the demolition of a low rise structure that was established as a site
demarcation, removal of bituminous pavement and abandonment of the existing utility services
within site. The construction of the two office building with a total of ten business rooms on a
hectare piece of land consists of the development of the perimeter wall that surrounds the office
buildings (Dogbegah et al, 26). And reconstruction of a well navigated bituminous pavement and
the construction of a parking garage with a minimum capacity of twenty-five private cars. Other
additional construction activities shall involve the installation of site lighting systems,
construction of a block perimeter wall to envelope the two office buildings and the construction
of a subsurface drainage system for the premises.
The construction manager shall be made aware of that the site abuts other commercial buildings
around its circumference and as such the construction means and methods utilized for the
construction project must consider the potential impact of construction activities to the
surrounding commercial structures (Navarrete et al, 68). The construction management plan
should include the following aspects
Document Page
Construction control systems
The organization of execution of this construction project shall be conducted in accordance with
the standards and regulation of United States construction guidelines relating to commercial
structures. The control systems described herein include
Overall construction cost
Before the start of o0f the construction works, the contractor is expected to prepare and provide
an exclusive construction cost of the project. The budget of the project should be detailed,
expressing the time intervals for the demand constructions progress of claims. Within the budget,
the constructor should explicitly and categorically outline the total labour cost for the project,
right from excavation processes to finishing construction processes just before commissioning of
the office buildings. The project costing should also include the machinery and equipment
acquisition expenses prior to the start of the construction project. The cost for construction
materials such as building blocks, sand, concrete should be included in the project budget (Ali,
11).
A construction manager should also provide a well-structured health and safety manual for the
construction process, detailing the safety measure to be incorporated during constructions. It is a
good practice for the contractor to present the construction schedule and timeframe outlining the
sequence of construction activities alongside construction submittals (Sacks et al, 25).
Quality in construction is paramount; therefore, the contractor is expected to submit explicit
measures that would ensure that quality construction practice is attained (Ottosson 89).
Document Page
RFI Log and RFI’s
Pacific Northwest Co. Ltd PacNort.Co.Ltd
456, Washington Street
California, U.S.
(231) 432-987
Email: pacificwestcons@gmail.com
RFI
PROJECT NAME RFI NUMBER
DATE OF
REQUEST
Riverstone Office Building Project
A6782 18/04/2020
PROJECT LOCATION PROJECT ID DRAWING ID
Northwest Area. California, USA R6-234B2
A02
RFI OVERVIEW SECTION(S) REFERENCED
Reception desk height and width in spec does not match initial
request
Fig-1-Reception.jpg
CHANGE IN COST CHANGE IN TIME
NO CHANGE NO CHANGE
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
X INCREASE IN COST $ 21,400 X INCREASE IN TIME # of Days = 4
DECREASE IN COST $ DECREASE IN TIME # of Days =
REQUEST / CLARIFICATION REQUIRED
1. Clarification regarding the substitutional use of concrete blocks
Instead of bricks
2. Change of the office lobby design
3. Request for site title deed
4. Description on-site work permit
5. Constructability of the site perimeter wall
NAME OF REQUESTING PARTY SIGNATURE
DATE OF
REQUEST
Frank Rodgers 18/04/2020
RESPONSE
Information request received, Will update promptly
NAME OF RESPONDING PARTY SIGNATURE
DATE OF
RESPONSE
John Jakolosai 20/04/2020
Document Page
RFI Log (Kozlovska et al, 713)
The contractor is expected to prepare and present all the construction submittal logs that are
essential in tracking major construction approvals. The submittal logs should also be
accompanied with construction transmittal documentation listing outline project documents
transferred to other companies or client.
There should be an attachment of all the construction changes implemented in the first month of
construction in a well-structured change order log. This should then be supported by an elaborate
narrative explaining in details the changes made during the construction period.
Document Page
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Work Cited
Ali, A Kamaruzzaman. "Cost performance for building construction projects in Klang
Valley." Journal of Building performance 11 (2015).
Dogbegah, R., D. Owusu-Manu, and Kamil Omoteso. "A principal component analysis of
project management competencies for the Ghanaian construction industry." Australasian
Journal of Construction Economics and Building, The 11.1 (2017): 26.
Kozlovska, Maria, Daniela Markova, and Marcela Spisakova. "Survey of Construction
Management Documentation Usage in Planning and Construction of Building
Project." Procedia Engineering 161 (2016): 711-715.
Navarrete, Pablo F., and William C. Cole. Planning, estimating, and control of chemical
construction projects. CRC Press, (2016) 66-71
Ottosson, Hans. Practical project management for building and construction. CRC Press,
(2014) 89.
Sacks, R., R. Navon, and E. Goldschmidt. "Building project model support for automated
labour monitoring." Journal of computing in civil engineering 17.1 (2013): 19-27.
chevron_up_icon
1 out of 8
circle_padding
hide_on_mobile
zoom_out_icon
logo.png

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]