Mechanical Engineering Project Report: Riyadh Refinery Clean Fuels
VerifiedAdded on 2021/04/21
|7
|1778
|20
Report
AI Summary
This report details the Riyadh Refinery Clean Transportation of Fuels project, executed by Saudi ARAMCO with Samsung as the contractor and Al Husam General Contracting LLC as the subcontractor, from February 2015 to February 2016. The author served as a QC Inspector (Piping), responsible for ensuring quality control of materials, workmanship, and procedures. The project aimed to transport clean refinery fuels, maintain fuel quality, and ensure a safe environment. The report outlines the author's responsibilities, including inspection, quality assurance, and coordination with project stakeholders. It discusses engineering skills applied, issues encountered (design and hydrostatic testing), and solutions implemented. The project's success was attributed to innovative work practices, daily meetings, and a focus on quality. The report concludes with an overview of the project, the author's contributions, and an emphasis on continuous quality improvement.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.

CE 3.1 Project Information
Name of the project: Riyadh Refinery Clean Transportation of Fuels
Location of the project: Riyadh, Kingdom of Saudi Arabia
Project Duration: From February of 2015 to February 2016
Organization: Saudi ARAMCO
Role and Designation during the time: QC Inspector (Piping)
CE 3.2 Organizational Background
This project was executed by Saudi ARAMCO organization and the contractor of this
project was Samsung. The subcontractor of this project was Al Husam General Contracting
LLC and it was located in Riyadh, Kingdom of Saudi Arabia. This project started from
February of 2015 and ended in February of 2016. Al Husam General Contracting LLC is the
subcontractor of this project and has a unique position to provide its customers with
outstanding products and services. It is the effect of continuous innovation and improvement
with high level of quality. The quality of life is improved by giving extremely higher value
solutions to protect the flow of energy and water. The organizational vision is simply to lead
the construction business and to be the leader in the proper construction of several
infrastructures. It is also leading in oil and gas industry and manufacturing pipelines that
include tank construction engineering works. This project was extremely important for my
professional career and I was happy that I was able to execute the project properly and fulfill
my responsibilities and duties perfectly.
Name of the project: Riyadh Refinery Clean Transportation of Fuels
Location of the project: Riyadh, Kingdom of Saudi Arabia
Project Duration: From February of 2015 to February 2016
Organization: Saudi ARAMCO
Role and Designation during the time: QC Inspector (Piping)
CE 3.2 Organizational Background
This project was executed by Saudi ARAMCO organization and the contractor of this
project was Samsung. The subcontractor of this project was Al Husam General Contracting
LLC and it was located in Riyadh, Kingdom of Saudi Arabia. This project started from
February of 2015 and ended in February of 2016. Al Husam General Contracting LLC is the
subcontractor of this project and has a unique position to provide its customers with
outstanding products and services. It is the effect of continuous innovation and improvement
with high level of quality. The quality of life is improved by giving extremely higher value
solutions to protect the flow of energy and water. The organizational vision is simply to lead
the construction business and to be the leader in the proper construction of several
infrastructures. It is also leading in oil and gas industry and manufacturing pipelines that
include tank construction engineering works. This project was extremely important for my
professional career and I was happy that I was able to execute the project properly and fulfill
my responsibilities and duties perfectly.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

CE 3.3 Project Background
CE 3.3.1 Characteristics of the project
This project of Riyadh Refinery Clean Transportation of Fuels started in the month of
February in 2015 and ended in the month of February in 2016. Construction and Procurement
of steel structure, underground and above ground, piping works for the Riyadh refinery clean
transportation project. The specification requirements for the underground piping works for
fiber glass pipe intended for use in gravity flow systems for conveying sewage, storm water
and some chemical and industrial wastes. All pipes, joints, fittings, couplings and spools
under the standards of ASTM D 3262. Pipe and coupling shall be filament wound using
polyster, vinylester or epoxy resin and fiber glass reinforcement.
CE 3.3.2 Objectives developed for the project
This project of Riyadh Refinery Clean Transportation of Fuels had some of the major
objectives. The objectives are given below:
To transport clean refinery fuels.
To maintain fuel quality.
To inspect whether the project environment is safe or not.
CE 3.3.3 My area of work
This project helped me to expose an unbelievable journey of professionalism. I
received well appreciation from my team members and seniors and was associated from the
starting of the project until completion, testing and even commission of the same. My area of
work was to inspect the quality control of all the products and services. I ensured that quality
of services and products are up to the mark, so that the client is happy with our products.
CE 3.3.1 Characteristics of the project
This project of Riyadh Refinery Clean Transportation of Fuels started in the month of
February in 2015 and ended in the month of February in 2016. Construction and Procurement
of steel structure, underground and above ground, piping works for the Riyadh refinery clean
transportation project. The specification requirements for the underground piping works for
fiber glass pipe intended for use in gravity flow systems for conveying sewage, storm water
and some chemical and industrial wastes. All pipes, joints, fittings, couplings and spools
under the standards of ASTM D 3262. Pipe and coupling shall be filament wound using
polyster, vinylester or epoxy resin and fiber glass reinforcement.
CE 3.3.2 Objectives developed for the project
This project of Riyadh Refinery Clean Transportation of Fuels had some of the major
objectives. The objectives are given below:
To transport clean refinery fuels.
To maintain fuel quality.
To inspect whether the project environment is safe or not.
CE 3.3.3 My area of work
This project helped me to expose an unbelievable journey of professionalism. I
received well appreciation from my team members and seniors and was associated from the
starting of the project until completion, testing and even commission of the same. My area of
work was to inspect the quality control of all the products and services. I ensured that quality
of services and products are up to the mark, so that the client is happy with our products.

CE 3.3.4 Project Group
Figure 1: Team Members Associated with the project
CE 3.3.5 My responsibilities throughout the project
I had various responsibilities in this project. My main responsibilities included
checking and directing the plan and program of QA/QC and thus guaranteeing the fused
materials on the development ventures. Moreover, I even guaranteed that the work was
completed as needed in the agreement and met or surpassed the needed characteristics. I also
guaranteed the sufficient materials nature, workmanship and procedures in the undertaking
work.
My next responsibility was to help the Quality Control Engineer and Quality
Assurance, for example, the checking of steel fortification similar in the development
drawing and to issue the materials for the acceptance of report for the materials. I even kept
up measures of security, and agreed to the Company’s Environment management system,
SiteManagerQCManagersafetyManagerConstructionManagerQCInspector(ME)
Figure 1: Team Members Associated with the project
CE 3.3.5 My responsibilities throughout the project
I had various responsibilities in this project. My main responsibilities included
checking and directing the plan and program of QA/QC and thus guaranteeing the fused
materials on the development ventures. Moreover, I even guaranteed that the work was
completed as needed in the agreement and met or surpassed the needed characteristics. I also
guaranteed the sufficient materials nature, workmanship and procedures in the undertaking
work.
My next responsibility was to help the Quality Control Engineer and Quality
Assurance, for example, the checking of steel fortification similar in the development
drawing and to issue the materials for the acceptance of report for the materials. I even kept
up measures of security, and agreed to the Company’s Environment management system,
SiteManagerQCManagersafetyManagerConstructionManagerQCInspector(ME)

health, and al so the Safety Management System necessities, and took the company measures
of Quality according to the system of Company Quality prerequisites. GRE pipe were utilized
as the part of High weight covered Header line and stream line in PDO, oil and Gas gathering
station and stream line area. GRE materials were deep rooted, decreased keep up cost and
high weight in Oil and Gas streamline. I even introduced and joined the GRE pipe funnel to
the pipe by utilizing less time and use of less number of pipes.
My other responsibility was to check the pipe creation part, to guarantee weight
appraisals with material declaration and to check other related materials. I also assessed
Adhesive, Epoxy string past lapse date, and kept in legitimate pressing with fitting
temperature away region. I also watched the pressing material rundown and materials
testament. The GRE pipe to pipe strung was joined for adding to the cement and Epoxy.
My next responsibility was to assess string joint pipe according to PDO. I also
approved QCP and QWP particular through the affirmed PDO hydro test methodology and
executed hydro test Witness and audit relationship with PDO delegates. I also supported the
quality control reports, for example, ERD, PDO determinations, QCP and QWPS and
gathered the test packs according to PDO necessities, acquired the endorsement by PDO
QA/QC. I even co-ordinated with the Site trough and works co-organizer/SrQCin with
regards to quality assignment. I even attended co-appointment gatherings, and informed the
status with respect to the quality issues amid site audit gatherings, talked about the execution
of agreement quality arrangement and suggested changes.
I provided criticism to the QA/QC administrator of all quality related assignments
including and prepared requirements for the QA/QC staff. I took an interest in the HSE
gatherings and made the HSE culture among QA/QC work force. I also notified any non-
conformance recognized amid site assessment, prescribed remedial measures to site
of Quality according to the system of Company Quality prerequisites. GRE pipe were utilized
as the part of High weight covered Header line and stream line in PDO, oil and Gas gathering
station and stream line area. GRE materials were deep rooted, decreased keep up cost and
high weight in Oil and Gas streamline. I even introduced and joined the GRE pipe funnel to
the pipe by utilizing less time and use of less number of pipes.
My other responsibility was to check the pipe creation part, to guarantee weight
appraisals with material declaration and to check other related materials. I also assessed
Adhesive, Epoxy string past lapse date, and kept in legitimate pressing with fitting
temperature away region. I also watched the pressing material rundown and materials
testament. The GRE pipe to pipe strung was joined for adding to the cement and Epoxy.
My next responsibility was to assess string joint pipe according to PDO. I also
approved QCP and QWP particular through the affirmed PDO hydro test methodology and
executed hydro test Witness and audit relationship with PDO delegates. I also supported the
quality control reports, for example, ERD, PDO determinations, QCP and QWPS and
gathered the test packs according to PDO necessities, acquired the endorsement by PDO
QA/QC. I even co-ordinated with the Site trough and works co-organizer/SrQCin with
regards to quality assignment. I even attended co-appointment gatherings, and informed the
status with respect to the quality issues amid site audit gatherings, talked about the execution
of agreement quality arrangement and suggested changes.
I provided criticism to the QA/QC administrator of all quality related assignments
including and prepared requirements for the QA/QC staff. I took an interest in the HSE
gatherings and made the HSE culture among QA/QC work force. I also notified any non-
conformance recognized amid site assessment, prescribed remedial measures to site
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

supervisors and led reviews and development for confirming the powerful usage of
recognized restorative and preventive activities.
CE 3.4 Distinctive Activity
CE 3.4.1 Engineering knowledge and skills applied in the project
Mechanical engineering skills and knowledge are important for this project and I have
applied all of them successfully. These core-engineering skills helped me to fulfil my
responsibilities with perfection. I have applied my power of critical thinking and problem
solving capabilities. Moreover, I have even used my computer and linguistic proficiencies in
this project.
CE 3.4.2 Identified issues and their solutions
3.4.2.1 Issues
Two important issues were faced in the project and they are given below:
i) The very first issue faced in this project was related to the design of the project. The
issues that were solely associated with design of piping, fabrication, installation, testing and
pre commissioning were faced in this project.
ii) The second issue that I faced in the project was in the initial stage of hydrostatic
test. The main problem was during evaluating the highlights for guaranteeing that the pipeline
was piggable. All the unpiggable components were ought to be evacuated or supplanted for
hindering the section of dewatering.
3.4.2.2 Solutions
I suggested relevant solutions to the problems. The solutions to the issues are as
follows:
recognized restorative and preventive activities.
CE 3.4 Distinctive Activity
CE 3.4.1 Engineering knowledge and skills applied in the project
Mechanical engineering skills and knowledge are important for this project and I have
applied all of them successfully. These core-engineering skills helped me to fulfil my
responsibilities with perfection. I have applied my power of critical thinking and problem
solving capabilities. Moreover, I have even used my computer and linguistic proficiencies in
this project.
CE 3.4.2 Identified issues and their solutions
3.4.2.1 Issues
Two important issues were faced in the project and they are given below:
i) The very first issue faced in this project was related to the design of the project. The
issues that were solely associated with design of piping, fabrication, installation, testing and
pre commissioning were faced in this project.
ii) The second issue that I faced in the project was in the initial stage of hydrostatic
test. The main problem was during evaluating the highlights for guaranteeing that the pipeline
was piggable. All the unpiggable components were ought to be evacuated or supplanted for
hindering the section of dewatering.
3.4.2.2 Solutions
I suggested relevant solutions to the problems. The solutions to the issues are as
follows:

i) For the very first issue, I received and answered site RFI’s problems during
erection. I resolved the issue of piping in time that was arising between the EPC contractors,
vendors, sib contractors and all other interfaces. I carried out final inspection of installed
piping and inline equipments, produced punch lists and also supervised the completion of
remedial works. I even tracked and reported to the installed commodities and monitored the
performance of the contractor for piping and installation system. I suggested to take
necessary actions for achieving the design goals of the company and thus meeting the
specification requirements.
ii) For the second issue, I had the strategy for expelling and spooling. It is a
component for hydrostatic weight testing and is utilized at highlights. Moreover, the valve
shell test weights might be tried for the new establishments. This would have recommended
high test weights and would have expected to be tried independently. When this test pressure
was built up, the administrators should consider that the greatest weight control point. All the
existing pipeline tests contained segments that were composed and introduced for meeting
earlier code pre requisites. Various establishments incorporated the principle expansions,
migrations and repairs.
CE 3.4.3 Plan to produce creative and innovative work
Our plan in this project was to provide best quality work in the most innovative
manner. We met up in daily meetings for discussing our shortcomings and also maintained
the quality of the products. As we had made this plan, our project was a huge success and we
did not face any losses.
erection. I resolved the issue of piping in time that was arising between the EPC contractors,
vendors, sib contractors and all other interfaces. I carried out final inspection of installed
piping and inline equipments, produced punch lists and also supervised the completion of
remedial works. I even tracked and reported to the installed commodities and monitored the
performance of the contractor for piping and installation system. I suggested to take
necessary actions for achieving the design goals of the company and thus meeting the
specification requirements.
ii) For the second issue, I had the strategy for expelling and spooling. It is a
component for hydrostatic weight testing and is utilized at highlights. Moreover, the valve
shell test weights might be tried for the new establishments. This would have recommended
high test weights and would have expected to be tried independently. When this test pressure
was built up, the administrators should consider that the greatest weight control point. All the
existing pipeline tests contained segments that were composed and introduced for meeting
earlier code pre requisites. Various establishments incorporated the principle expansions,
migrations and repairs.
CE 3.4.3 Plan to produce creative and innovative work
Our plan in this project was to provide best quality work in the most innovative
manner. We met up in daily meetings for discussing our shortcomings and also maintained
the quality of the products. As we had made this plan, our project was a huge success and we
did not face any losses.

CE 3.5 Project Review
CE 3.5.1 Project Overview
This project was executed with the purpose of producing refinery oil with good
quality. The owner of this project was ARAMCO, the contractor was TECHNIP and the sub
contractor was Al Husam General Contracting LLC. The location of the project was in
Riyadh. This project was also completed within budget and did not incur more expenses.
CE 3.5.2 My contribution to work
In this project, as a QC team we had to discover the deficiency of value administration
of big business. At that point, to gain ground through the exploration, to enhance the nature
of item, work, and administration, while reinforcing the overall quality administration
framework, I raised the general level of value administration. I even set up the corporate
picture and fortified aggressiveness, the nature of development that required consistent
change. I even made surveys of the development association. It had been exposed that the
framework of quality administration could easily guarantee about the reasonable portion of
undertaking resources, and influenced the undertaking to keep going over the destinations of
preconcert quality, for accomplishing the overall impact of the quality control of task. I even
ensured the awareness of value control in the period of undertaking quality arrangement
ought to be fortified, and put emphasis on the assessment after completing process control of
pre-development.
CE 3.5.1 Project Overview
This project was executed with the purpose of producing refinery oil with good
quality. The owner of this project was ARAMCO, the contractor was TECHNIP and the sub
contractor was Al Husam General Contracting LLC. The location of the project was in
Riyadh. This project was also completed within budget and did not incur more expenses.
CE 3.5.2 My contribution to work
In this project, as a QC team we had to discover the deficiency of value administration
of big business. At that point, to gain ground through the exploration, to enhance the nature
of item, work, and administration, while reinforcing the overall quality administration
framework, I raised the general level of value administration. I even set up the corporate
picture and fortified aggressiveness, the nature of development that required consistent
change. I even made surveys of the development association. It had been exposed that the
framework of quality administration could easily guarantee about the reasonable portion of
undertaking resources, and influenced the undertaking to keep going over the destinations of
preconcert quality, for accomplishing the overall impact of the quality control of task. I even
ensured the awareness of value control in the period of undertaking quality arrangement
ought to be fortified, and put emphasis on the assessment after completing process control of
pre-development.
1 out of 7

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.