Project Management: Royale Pizza Renovation Project Assessment 1

Verified

Added on  2022/10/01

|5
|344
|4
Project
AI Summary
This document presents a project management assessment for the Royale Pizza renovation, focusing on Assessment 1. The assignment includes a detailed project plan, covering the project's goals, scope, and overall delivery life cycle. The project's goals are defined with measurable metrics. A comprehensive scope statement outlines deliverables, acceptance criteria, constraints, exclusions, and assumptions. The project delivery life cycle is described, including the chosen methodology, its stages, and processes for monitoring and controlling the project. The document also includes a work breakdown structure (WBS), schedule plan with milestones and due dates, and cost estimates. The project case study, focusing on Royale Pizza, is used to illustrate the application of project management principles. The document showcases a comprehensive approach to managing the Royale Pizza renovation project.
tabler-icon-diamond-filled.svg

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
Schedule Plan
Milestons Due Dates
Milestone 1: Design phase completion
Milestone 2: Completion of procurement and delivery phase
Milestone 3:Completion of construction phase
Milestone 3:Completion of construction phase
28-03-19
23-05-19
20-06-19
15-08-19
WBS
ID
Activity
Description Precedence Duration
Estimate
Resource Cost
Estimate
(base on
budget
plan)
0 Renovation of 6 mons $40,000.00
1 | P a g e
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Royale Pizza shop
1 Project design
phase
1 mon $5,000.00
1.1 Identification of
business needs
5 days Project management consultant $1,800.00
1.2 Proper design for
blueprint
2 13 days Designer $3,200.00
1.3 Providing
approval for the
project
3 2 days Sponsor $0.00
1.4 Milestone 1:
Design phase
completion
4 0 days $0.00
2 Procurement and
delivery phase
2 mons $18,000.00
2.1 Procurement need 5 10 days Contractor, Procurement manager $5,000.00
2 | P a g e
Document Page
identification
2.2 Project suppliers
identification
7 9 days Procurement manager, Additional cost[1] $6,000.00
2.3 Understanding the
price of the materials
8 7 days Sponsor $0.00
2.4 Material purchase 9 9 days Procurement manager, Equipment
supply[1]
$5,000.00
2.5 Receipt and
inspection
10 5 days Construction manager, Shop supervisor $2,000.00
2.6 Milestone 2:
Completion of
procurement and
deliver phase
11 0 days $0.00
3 Construction
phase
1 mon $7,000.00
3.1 Finishing the 12 8 days Construction manager, Contractor, Project $3,000.00
3 | P a g e
Document Page
flooring work manager
3.2 Compressor
capacity increment
14 4 days Installer, Construction manager $2,000.00
3.3 Proper cleaning
kitchen
15 5 days Cleaner, Construction manager $1,000.00
3.4 Buying of various
equipment’s
16 3 days Contractor, Project manager $1,000.00
3.5 Milestone
3:Completion of
construction phase
17 0 days $0.00
4 Painting or
installation
2 mons $10,000.00
4.1 Installation of air
condition
17 17 days Technical analyst, Installer $4,000.00
4.2 Dust free painting 20 23 days Installer $6,000.00
4.3 Milestone 4: 21 0 days $0.00
4 | P a g e
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Completion of
painting and
installation
5 | P a g e
chevron_up_icon
1 out of 5
circle_padding
hide_on_mobile
zoom_out_icon
logo.png

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]