Project Management: Analysis of Royale Pizza Shop Renovation Project

Verified

Added on  2022/11/11

|18
|2574
|78
Project
AI Summary
This project management assignment analyzes the renovation of Royale Pizza, a shop located in Melbourne. The assignment begins with the preparation of a detailed project schedule, utilizing Gantt charts and the critical path method, and identifies key milestones, resources, and potential stress points. The project then moves on to budget creation, outlining direct and indirect costs, and assumptions made during the budgeting process. Following this, the assignment delves into project risk management, identifying potential risks such as schedule slippage and budget shortfalls, and proposes risk response strategies. The project utilizes tools and techniques such as root cause analysis, the Delphi method, and risk registers. The assignment also includes a detailed budget breakdown, a critical path analysis chart, and a risk register with qualitative and quantitative risk analyses. This comprehensive approach ensures the project's successful completion and is a great resource for students studying project management.
Document Page
Running head: PROJECT MANAGEMENT
Project management

Name of the Student

Name of the University

Author’s Note
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
1
PROJECT MANAGEMENT

Table of Contents

1.
Preparation of schedule.......................................................................................................2
1.1
Project schedule...........................................................................................................2
1.2
Relative merits of the methods, tools and techniques.................................................5
1.3
Comparison with the tools that are not used...............................................................6
1.4
Stress point on the critical path...................................................................................7
1.5
Tools and techniques used for the critical path...........................................................8
2. Budget
.................................................................................................................................... 8
2.1 Budget for the project
.......................................................................................................8
2.2 Assumptions that are made in preparing the budget
........................................................9
2.3 Actions required for controlling the cost
.........................................................................9
3. Project risk management
...................................................................................................... 10
3.1 Identification of tools and techniques that are used or risk management
......................10
3.2 Qualitative and quantitative risk analysis with risk response strategies for mitigating the

risk
........................................................................................................................................10
Bibliography
.............................................................................................................................14
Bibliography
.............................................................................................................................15
Document Page
2
PROJECT MANAGEMENT

1.
Preparation of schedule
1.1
Project schedule
The schedule which is prepared below for the renovation of the shop includes key

milestones as well as resources that are needed for the project.

WBS

ID

Activity

description

Precedence
Duration
estimate

Resources
Cost
Estimate

0
Renovation of
Royale Pizza

shop

6 mons
AU$
40,000.00

1
Design stage 1 mon AU$
5,000.00

1.1
Conducting
meeting with the

designer

1 day
Project management
consultant

AU$

200.00

1.2
Undertaking
sketch studies

2
4 days Designer, Project
management

consultant

AU$

300.00

1.3
Undertaking
preliminary

design for shop

renovation

3
5 days Designer AU$
1,500.00

1.4
Creating
detailed design

4
10 days Contractor,
Designer

AU$

3,000.00
Document Page
3
PROJECT MANAGEMENT

1.5
Milestone 1:
Getting approval

for the project

design that is

developed

5
0 days AU$ 0.00
2
Procurement
and delivery

phase

2 mons
AU$
18,000.00

2.1
Determining
suppliers and

other

construction

contractors

5
8 days Procurement
manager, Project

management

consultant, Project

manager

AU$

200.00

2.2

Recommending

vendors

8
5 days Procurement
manager, Project

management

consultant

AU$

300.00

2.3
Purchasing
orders and

executing

contracts

9
8 days Equipment suppliers AU$
7,000.00

2.4
Purchasing of
deep fryers,

boilers and dough

roller

10
9 days Equipment suppliers AU$
4,000.00
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
4
PROJECT MANAGEMENT

2.5
Managing
and expediting

delivery of goods

11
10 days Procurement
manager, Supervisor

AU$

6,500.00

2.6
Milestone 2:
Getting approval

for construction

phase

12
0 days AU$ 0.00
3
Construction
phase

1 mon
AU$
7,000.00

3.1
Undertaking
the work of

flooring

12
5 days Construction
manager, Contractor

AU$

2,000.00

3.2
Increasing the
capacity of

compressor

15
2 days Construction
manager, Supervisor

AU$

1,000.00

3.3
Removing the
rear area of the

shop

16
7 days Construction
manager, Contractor

AU$

2,000.00

3.4
Creating
additional dining

spaces

17
5 days Construction
manager, Supervisor

AU$

1,500.00

3.5
Undertaking
safety inspection

18
1 day Technical and safety
compliance

AU$

500.00

3.6
Milestone 3:
Completion of

19
0 days AU$ 0.00
Document Page
5
PROJECT MANAGEMENT

construction

phase

4
Installation
and painting

phase

2 mons
AU$
10,000.00

4.1
Installation of
exhaust system

19
7 days Installer AU$
1,000.00

4.2
Installation of
air conditioning

system

22
8 days Construction
manager,

Contractor, Installer

AU$

3,000.00

4.3
Painting 23 20 days Painter AU$
5,000.00

4.4
Installation of
needed software

and hardware

24
5 days Installer, Technical
and safety

compliance

AU$

1,000.00

4.5
Milestone 3:
Completion of

installation and

painting phase

25
0 days AU$ 0.00
Document Page
6
PROJECT MANAGEMENT

1.2
Relative merits of the methods, tools and techniques
Used Method

It is found that in order to create the project schedule, visual depiction method is used

for showcasing the Gantt chart. It is found that the Gantt chart helps in breaking each of the

project phases properly for successfully representing them as a horizontal bar (
Ong, Wang and
Zainon 2016).
Gantt charts are mainly used for successfully planning and scheduling the
project so that the project duration as well as the resources that are needed can be accessed.

Used tools

It is found that in order to create the project schedule, MS project software tool is mainly

used. This is a software tool that is mainly used by the project managers for developing

schedule as well as for assigning different types of resources to the task. In addition to this, with

the help of this tool, budget and workload of the project can be analyzed.

Used technique

Critical path method is used while developing the schedule for the renovation project as

critical path helps in uncovering the longest possible duration that is needed for executing the

project (
Kerzner 2017). In addition to this, the CPM method helps in marking the critical tasks
of the project and the project activities which may float. Furthermore, this method helps in

visualizing the entire flow of the project and helps in calculating the duration when all the

project dependencies as well as deliverables are known.

1.3
Comparison with the tools that are not used
It is found that the project used Gantt chart as the scheduling method instead of resource

oriented scheduling. This is because in resource oriented scheduling is used when there is

competition between the various tasks or components and provides knowledge only regarding
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7
PROJECT MANAGEMENT

the tasks however Gantt chart not only provides proper idea about the project but also helps in

planning and scheduling resources (
Hornstein 2015). In context to PM software tool, MS
project software tool is used for managing the project instead of excel. This is because with the

help of excel, it is quite difficult to manage complex project like renovation effectively but the

use of MS project helps in managing the Royale pizza shop renovation on time and quite

effectively. In addition to this, it is found that the project managers use critical path technique

instead of PERT technique (
Thomas and Ellis Jr 2017). This is because PERT only helps in
visualizing task flow within the project and assist in estimating the project timeline however

with the help of CPM, the longest possible timeline within the project can also be uncovered.
Document Page
8
PROJECT MANAGEMENT

1.4
Stress point on the critical path
The critical path that is provided below helps in reflecting the stress point for the

renovation project.

Figure 1: Critical path of the project

(Source: Created by Author)

1.5
Tools and techniques used for the critical path
It is found that critical path analysis chart tool can be used for showcasing the critical path

of the project. The main benefit of using this specific tool is that it helps in saving both time and

money and additionally helps in creating proper comparison with the actual and planned
Document Page
9
PROJECT MANAGEMENT

progress in the project. In addition to this, it helps in scheduling as well as controlling the

project activities.

2. Budget

2.1 Budget for the project

The figure that is given helps in depicting the total budget including the direct cost and

indirect cost which is required for the purpose of Royale Pizza Shop renovation.

Figure 2: Budget of the project

(Source: Created by Author)
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
10
PROJECT MANAGEMENT

2.2 Assumptions that are made in preparing the budget

It is found that accurate as well as precise cost assumption in the project are very much

critical for developing both the long term as well as short term budget. The various types of

assumption which are made for renovating the pizza shop are listed below:

Salaries: The salaries of the labours as well as managers are assumed as per the time for
which they are involved within the project (
Todorovic et al. 2015).
Materials: The raw materials cost which are needed for the renovation work are
assumed and included as direct cost within the total budget

Equipment cost: The budget for different types of equipment including dough roller,
chairs, fryers and other needs are assumed before the project.

2.3 Actions required for controlling the cost

The project managers take the following actions in order to control the cost of the

project quite effectively.

Tracking expenditure:
It is necessary to keep track on the actual cost for analyzing the
expenditure that is done on each of the phase of the project. This helps in tracking the periodic

targets which is mainly set out within the budget (
Badewi 2016).
Effective time management:
It is one of the important techniques that are helpful in
proper time management. This technique is mainly applied to different management areas for

successfully controlling the cost of the project.

Proper change control:
Project change control is helpful in analyzing the changes that
could occur during the project and this is due to the fact that each of the changes within the

project scope will impact the deadline of the project and further helps in increasing effort that is

needed (
Kerzner 2017).
Document Page
11
PROJECT MANAGEMENT

3. Project risk management

3.1 Identification of tools and techniques that are used or risk management

The various types of project risk management tools as well as techniques that are used in

the project are effectively elaborated:

Root cause analysis:
This is one of the common methods that are mainly used for
identifying the risks effectively. This root causes are properly utilized for additional risks in the

project (
Carvalho and Rabechini Junior 2015).
Delphi method:
The Delphi method is one of the forecasting procedure frameworks
that is based on the results of various rounds of questionnaire that is panel of experts.

Probability and impact matrix:
This matrix helps in properly determining different
types of risks that require immediate response. It is found that this can be further customized as

per the need of the project.

Risk register:
A risk register is one of the documents that is updated on a regular basis
within the entire life cycle of the project (
Hopkin 2018). It helps in identifying the risks quite
effectively that are mainly linked with the renovation project.