University Project: Royale Pizza Shop Renovation Project Management
VerifiedAdded on 2022/12/19
|16
|2463
|4
Project
AI Summary
This project management assignment analyzes the Royale Pizza shop renovation, detailing the project schedule, budget, and risk identification. The project schedule outlines a six-month timeline, breaking down tasks into phases: design, procurement/delivery, construction, and painting/installation. The budget, totaling $40,000, covers costs for each project activity, with assumptions made regarding equipment financing. Actions for budget control include tracking expenditure and proper resource management. Risk management techniques involve identifying risks using tools like Porter's five forces, evaluating effects, and mitigation strategies using SWOT analysis. The critical path is identified through Gantt charts and network diagrams. The assignment also includes a detailed breakdown of the project's Work Breakdown Structure (WBS), along with a discussion of the methods, tools and techniques used for effective project management, providing a comprehensive overview of the renovation project's planning and execution.

Running head: PROJECT MANAGEMENT
Royale Pizza Shop Renovation
Name of the Student
Name of the University
Author’s Note
Royale Pizza Shop Renovation
Name of the Student
Name of the University
Author’s Note
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1
PROJECT MANAGEMENT
Table of Contents
1. Project schedule.....................................................................................................................2
1.1 Preparation of a schedule.................................................................................................2
1.2 Discussion about the methods, tools and techniques.......................................................5
1.3 Critical path of the project................................................................................................6
1.4 Tools and techniques used...............................................................................................7
2. Project budget.........................................................................................................................7
2.1 Proper budget for the project............................................................................................7
2.2 Assumptions that are made in preparing budget............................................................10
2.3 Actions taken in controlling budget...............................................................................11
3. Risk identification................................................................................................................11
3.1 Identification of risk management techniques and tools................................................11
3.2 Risk response strategies for keeping risks on track.......................................................12
Bibliography.............................................................................................................................15
PROJECT MANAGEMENT
Table of Contents
1. Project schedule.....................................................................................................................2
1.1 Preparation of a schedule.................................................................................................2
1.2 Discussion about the methods, tools and techniques.......................................................5
1.3 Critical path of the project................................................................................................6
1.4 Tools and techniques used...............................................................................................7
2. Project budget.........................................................................................................................7
2.1 Proper budget for the project............................................................................................7
2.2 Assumptions that are made in preparing budget............................................................10
2.3 Actions taken in controlling budget...............................................................................11
3. Risk identification................................................................................................................11
3.1 Identification of risk management techniques and tools................................................11
3.2 Risk response strategies for keeping risks on track.......................................................12
Bibliography.............................................................................................................................15

2
PROJECT MANAGEMENT
1. Project schedule
1.1 Preparation of a schedule
The schedule that is developed for undertaking the renovation works reflects that
around 6 months of time is needed for successful completion of the project. The below
showcases the starting and ending date for each of the activity of the project.
WBS Task Name Duration Start Finish Predecessors Resource Names
0
Renovation of
Royale Pizza
shop
6 mons
Fri 01-
03-19
Thu 15-08-
19
1
Project
designing phase
1 mon
Fri 01-
03-19
Thu 28-03-
19
1.1
Determining
the requirements
of business
8 days
Fri 01-
03-19
Tue 12-03-
19
Project management
consultant
1.2
Developing
blueprint for
construction
11 days
Wed 13-
03-19
Wed 27-03-
19
2 Architect designer
1.3
Getting
approval for
construction
1 day
Thu 28-
03-19
Thu 28-03-
19
3 Project sponsor
1.4
Milestone 1:
Project design
complete
0 days
Thu 28-
03-19
Thu 28-03-
19
4
PROJECT MANAGEMENT
1. Project schedule
1.1 Preparation of a schedule
The schedule that is developed for undertaking the renovation works reflects that
around 6 months of time is needed for successful completion of the project. The below
showcases the starting and ending date for each of the activity of the project.
WBS Task Name Duration Start Finish Predecessors Resource Names
0
Renovation of
Royale Pizza
shop
6 mons
Fri 01-
03-19
Thu 15-08-
19
1
Project
designing phase
1 mon
Fri 01-
03-19
Thu 28-03-
19
1.1
Determining
the requirements
of business
8 days
Fri 01-
03-19
Tue 12-03-
19
Project management
consultant
1.2
Developing
blueprint for
construction
11 days
Wed 13-
03-19
Wed 27-03-
19
2 Architect designer
1.3
Getting
approval for
construction
1 day
Thu 28-
03-19
Thu 28-03-
19
3 Project sponsor
1.4
Milestone 1:
Project design
complete
0 days
Thu 28-
03-19
Thu 28-03-
19
4
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3
PROJECT MANAGEMENT
2
Project
procurement &
delivery phase
2 mons
Fri 29-
03-19
Thu 23-05-
19
2.1
Recognizing
different needs
and requirements
of the project
8 days
Fri 29-
03-19
Tue 09-04-
19
5
Project contractor,
Procurement manager
2.2
Suppliers of
the project are
identified
5 days
Wed 10-
04-19
Tue 16-04-
19
7
Procurement
manager, Additional
cost[1]
2.3
Proper
understanding
and knowledge
about price terms
10 days
Wed 17-
04-19
Tue 30-04-
19
8 Project sponsor
2.4
Purchase of
different types of
materials
12 days
Wed 01-
05-19
Thu 16-05-
19
9
Procurement
manager, Equipment
supply[1]
2.5
Getting
inspection as
well as receipt
5 days
Fri 17-
05-19
Thu 23-05-
19
10
Construction
manager, Shop
supervisor
2.6 Milestone 2:
Project
procurement &
delivery phase
0 days Thu 23-
05-19
Thu 23-05-
19
11
PROJECT MANAGEMENT
2
Project
procurement &
delivery phase
2 mons
Fri 29-
03-19
Thu 23-05-
19
2.1
Recognizing
different needs
and requirements
of the project
8 days
Fri 29-
03-19
Tue 09-04-
19
5
Project contractor,
Procurement manager
2.2
Suppliers of
the project are
identified
5 days
Wed 10-
04-19
Tue 16-04-
19
7
Procurement
manager, Additional
cost[1]
2.3
Proper
understanding
and knowledge
about price terms
10 days
Wed 17-
04-19
Tue 30-04-
19
8 Project sponsor
2.4
Purchase of
different types of
materials
12 days
Wed 01-
05-19
Thu 16-05-
19
9
Procurement
manager, Equipment
supply[1]
2.5
Getting
inspection as
well as receipt
5 days
Fri 17-
05-19
Thu 23-05-
19
10
Construction
manager, Shop
supervisor
2.6 Milestone 2:
Project
procurement &
delivery phase
0 days Thu 23-
05-19
Thu 23-05-
19
11
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4
PROJECT MANAGEMENT
completion
3
Project
construction
phase
1 mon
Fri 24-
05-19
Thu 20-06-
19
3.1
Completion
of flooring work
8 days
Fri 24-
05-19
Tue 04-06-
19
12
Construction
manager, Project
contractor, Project
manager
3.2
Enhancing
the capacity of
the compressor
4 days
Wed 05-
06-19
Mon 10-06-
19
14
Installer,
Construction manager
3.3
Undertaking
cleaning for the
kitchen area
5 days
Tue 11-
06-19
Mon 17-06-
19
15
Cleaner, Construction
manager
3.4
Buying the
required
resources and
materials
3 days
Tue 18-
06-19
Thu 20-06-
19
16
Project contractor,
Project manager
3.5
Milestone 3:
Project
construction
phase completion
0 days
Thu 20-
06-19
Thu 20-06-
19
17
PROJECT MANAGEMENT
completion
3
Project
construction
phase
1 mon
Fri 24-
05-19
Thu 20-06-
19
3.1
Completion
of flooring work
8 days
Fri 24-
05-19
Tue 04-06-
19
12
Construction
manager, Project
contractor, Project
manager
3.2
Enhancing
the capacity of
the compressor
4 days
Wed 05-
06-19
Mon 10-06-
19
14
Installer,
Construction manager
3.3
Undertaking
cleaning for the
kitchen area
5 days
Tue 11-
06-19
Mon 17-06-
19
15
Cleaner, Construction
manager
3.4
Buying the
required
resources and
materials
3 days
Tue 18-
06-19
Thu 20-06-
19
16
Project contractor,
Project manager
3.5
Milestone 3:
Project
construction
phase completion
0 days
Thu 20-
06-19
Thu 20-06-
19
17

5
PROJECT MANAGEMENT
4
Painting and
Installation
work
2 mons
Fri 21-
06-19
Thu 15-08-
19
4.1
Installing the
air conditioners
17 days
Fri 21-
06-19
Mon 15-07-
19
17
Technical manager,
Installer ,Technical
and safety
compliance
certification bodies
4.2
Completing
the dust free
painting
23 days
Tue 16-
07-19
Thu 15-08-
19
20 Installer
4.3
Milestone 4:
Completion of
Painting and
installation work
of the project
0 days
Thu 15-
08-19
Thu 15-08-
19
21
1.2 Discussion about the methods, tools and techniques
It is found that there are a number of methods, tools as well as techniques that are
mainly used in order to prepare the project schedule. It is analyzed that scheduling tool is
mainly utilized in order to prepare the schedule (Manole and Avramescu 2017). The project
scheduling tools helps in highlighting all the information related with the project at once
including the project date, duration, time as well as resources and also help in tracking the
progress of the project. In addition to this, the cost that is associated with the project is
mainly identified with the help of the project schedule and the scheduling tool further helps in
reducing complications that are mainly associated with the project. On the other hand, it is
PROJECT MANAGEMENT
4
Painting and
Installation
work
2 mons
Fri 21-
06-19
Thu 15-08-
19
4.1
Installing the
air conditioners
17 days
Fri 21-
06-19
Mon 15-07-
19
17
Technical manager,
Installer ,Technical
and safety
compliance
certification bodies
4.2
Completing
the dust free
painting
23 days
Tue 16-
07-19
Thu 15-08-
19
20 Installer
4.3
Milestone 4:
Completion of
Painting and
installation work
of the project
0 days
Thu 15-
08-19
Thu 15-08-
19
21
1.2 Discussion about the methods, tools and techniques
It is found that there are a number of methods, tools as well as techniques that are
mainly used in order to prepare the project schedule. It is analyzed that scheduling tool is
mainly utilized in order to prepare the schedule (Manole and Avramescu 2017). The project
scheduling tools helps in highlighting all the information related with the project at once
including the project date, duration, time as well as resources and also help in tracking the
progress of the project. In addition to this, the cost that is associated with the project is
mainly identified with the help of the project schedule and the scheduling tool further helps in
reducing complications that are mainly associated with the project. On the other hand, it is
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6
PROJECT MANAGEMENT
identified that critical path method can also be utilized for developing the project schedule
however critical path method is not used. It is analyzed that there are a number of benefits of
utilizing critical path method over the scheduling tool (Kerzner and Kerzner 2017). With the
help of the critical path method, the tasks that are needed to be executed are generally
prioritized. This is beneficial for the managers as the project team can be able to get idea
about the project plan effectively. In addition to this, it is analyzed that with the help of CPM
methods, the tasks and project activities are broken down into smaller activities for successful
project execution.
1.3 Critical path of the project
Figure 1: Critical path
(Source: Created by Author)
PROJECT MANAGEMENT
identified that critical path method can also be utilized for developing the project schedule
however critical path method is not used. It is analyzed that there are a number of benefits of
utilizing critical path method over the scheduling tool (Kerzner and Kerzner 2017). With the
help of the critical path method, the tasks that are needed to be executed are generally
prioritized. This is beneficial for the managers as the project team can be able to get idea
about the project plan effectively. In addition to this, it is analyzed that with the help of CPM
methods, the tasks and project activities are broken down into smaller activities for successful
project execution.
1.3 Critical path of the project
Figure 1: Critical path
(Source: Created by Author)
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7
PROJECT MANAGEMENT
1.4 Tools and techniques used
The various tools and techniques that are needed to be used for reflecting the critical
path are generally reflected below:
Gantt chart: The Gantt chart can be used in order to reflect the critical path for the
project. It is considered as one of the easiest way of scheduling tasks as well as tracking the
progress of the project quite effectively (Hornstein 2015).
Network diagram: Network diagram can also be used n order to showcase the
critical path of the project. The Network diagram helps in graphically representing the
network diagram for the project.
2. Project budget
2.1 Proper budget for the project
The budget plan that is prepared for the project generally helps in reflecting that the
renovation work will get completed within $40,000. The table below generally showcases the
budget that is required for the completion of each of the activities of the project.
WBS Task Name Duration Predecessors Resource Names Cost
0
Renovation of Royale
Pizza shop
6 mons $40,000.00
1
Project designing
phase
1 mon $5,000.00
1.1
Determining the
requirements of
business
8 days
Project management
consultant
$2,000.00
1.2 Developing 11 days 2 Architect designer $3,000.00
PROJECT MANAGEMENT
1.4 Tools and techniques used
The various tools and techniques that are needed to be used for reflecting the critical
path are generally reflected below:
Gantt chart: The Gantt chart can be used in order to reflect the critical path for the
project. It is considered as one of the easiest way of scheduling tasks as well as tracking the
progress of the project quite effectively (Hornstein 2015).
Network diagram: Network diagram can also be used n order to showcase the
critical path of the project. The Network diagram helps in graphically representing the
network diagram for the project.
2. Project budget
2.1 Proper budget for the project
The budget plan that is prepared for the project generally helps in reflecting that the
renovation work will get completed within $40,000. The table below generally showcases the
budget that is required for the completion of each of the activities of the project.
WBS Task Name Duration Predecessors Resource Names Cost
0
Renovation of Royale
Pizza shop
6 mons $40,000.00
1
Project designing
phase
1 mon $5,000.00
1.1
Determining the
requirements of
business
8 days
Project management
consultant
$2,000.00
1.2 Developing 11 days 2 Architect designer $3,000.00

8
PROJECT MANAGEMENT
blueprint for
construction
1.3
Getting approval
for construction
1 day 3 Project sponsor $0.00
1.4
Milestone 1:
Project design
complete
0 days 4 $0.00
2
Project
procurement &
delivery phase
2 mons $18,000.00
2.1
Recognizing
different needs and
requirements of the
project
8 days 5
Project contractor,
Procurement manager
$5,000.00
2.2
Suppliers of the
project are identified
5 days 7
Procurement
manager, Additional
cost[1]
$3,000.00
2.3
Proper
understanding and
knowledge about price
terms
10 days 8 Project sponsor $0.00
2.4
Purchase of
different types of
materials
12 days 9
Procurement
manager, Equipment
supply[1]
$8,000.00
2.5 Getting inspection 5 days 10 Construction $2,000.00
PROJECT MANAGEMENT
blueprint for
construction
1.3
Getting approval
for construction
1 day 3 Project sponsor $0.00
1.4
Milestone 1:
Project design
complete
0 days 4 $0.00
2
Project
procurement &
delivery phase
2 mons $18,000.00
2.1
Recognizing
different needs and
requirements of the
project
8 days 5
Project contractor,
Procurement manager
$5,000.00
2.2
Suppliers of the
project are identified
5 days 7
Procurement
manager, Additional
cost[1]
$3,000.00
2.3
Proper
understanding and
knowledge about price
terms
10 days 8 Project sponsor $0.00
2.4
Purchase of
different types of
materials
12 days 9
Procurement
manager, Equipment
supply[1]
$8,000.00
2.5 Getting inspection 5 days 10 Construction $2,000.00
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

9
PROJECT MANAGEMENT
as well as receipt
manager, Shop
supervisor
2.6
Milestone 2:
Project procurement &
delivery phase
completion
0 days 11 $0.00
3
Project
construction phase
1 mon $7,000.00
3.1
Completion of
flooring work
8 days 12
Construction
manager, Project
contractor, Project
manager
$3,000.00
3.2
Enhancing the
capacity of the
compressor
4 days 14
Installer,
Construction manager
$2,000.00
3.3
Undertaking
cleaning for the
kitchen area
5 days 15
Cleaner, Construction
manager
$1,000.00
3.4
Buying the
required resources and
materials
3 days 16
Project contractor,
Project manager
$1,000.00
3.5
Milestone 3:
Project construction
phase completion
0 days 17 $0.00
PROJECT MANAGEMENT
as well as receipt
manager, Shop
supervisor
2.6
Milestone 2:
Project procurement &
delivery phase
completion
0 days 11 $0.00
3
Project
construction phase
1 mon $7,000.00
3.1
Completion of
flooring work
8 days 12
Construction
manager, Project
contractor, Project
manager
$3,000.00
3.2
Enhancing the
capacity of the
compressor
4 days 14
Installer,
Construction manager
$2,000.00
3.3
Undertaking
cleaning for the
kitchen area
5 days 15
Cleaner, Construction
manager
$1,000.00
3.4
Buying the
required resources and
materials
3 days 16
Project contractor,
Project manager
$1,000.00
3.5
Milestone 3:
Project construction
phase completion
0 days 17 $0.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

10
PROJECT MANAGEMENT
4
Painting and
Installation work
2 mons $10,000.00
4.1
Installing the air
conditioners
17 days 17
Technical manager,
Installer, Technical
and safety
compliance
certification bodies
$6,000.00
4.2
Completing the
dust free painting
23 days 20 Installer $4,000.00
4.3
Milestone 4:
Completion of
Painting and
installation work of the
project
0 days 21 $0.00
2.2 Assumptions that are made in preparing budget
The different types of assumptions which the project manager generally makes in
order to develop the budget plan are generally elaborated below:
The money that is required for buying the air conditioner will be given by the project
owner instead of the contractor and thus the contractor does not need to spend money
on the air conditioner.
It is assumed that work that is associated with project renovation must get completed
within $40,000 without causing any type of financial issues and challenges in the
project.
PROJECT MANAGEMENT
4
Painting and
Installation work
2 mons $10,000.00
4.1
Installing the air
conditioners
17 days 17
Technical manager,
Installer, Technical
and safety
compliance
certification bodies
$6,000.00
4.2
Completing the
dust free painting
23 days 20 Installer $4,000.00
4.3
Milestone 4:
Completion of
Painting and
installation work of the
project
0 days 21 $0.00
2.2 Assumptions that are made in preparing budget
The different types of assumptions which the project manager generally makes in
order to develop the budget plan are generally elaborated below:
The money that is required for buying the air conditioner will be given by the project
owner instead of the contractor and thus the contractor does not need to spend money
on the air conditioner.
It is assumed that work that is associated with project renovation must get completed
within $40,000 without causing any type of financial issues and challenges in the
project.

11
PROJECT MANAGEMENT
2.3 Actions taken in controlling budget
The actions which are generally undertaken in order to control the budget of the
project are generally elaborated below:
Keeping track on the project budget: The budget expenditure can be controlled by
keeping track on the budget of the project so that any variance within the project can be
controlled quite successfully (Serrador and Turner 2015).
Proper resource management: Proper management of resources are generally
required for managing the resources effectively so that no extra expenditure will be done if
any shortfall occurs due to unavailability of resources. This not only helps in managing
resources but also assist in controlling budget.
3. Risk identification
3.1 Identification of risk management techniques and tools
The various types of tools as well as techniques which are mainly utilized in order to
manage the risks that are related with the construction work are generally reflected below:
Determination of risk: Porter’s five forces are considered as one of the systematic
tools that are general helpful in determining the risks that are associated with the project.
With the help of ort’s five force analysis, the risks that are associated finance, schedule as
well as management can be identified effectively.
Evaluation of the effect: It is quite important to utilize situational analysis in order to
evaluate the potential effects that are associated with the project risks (Kerzner and Kerzner
2017). With the identified risk, it is quite necessary to determine the consequence as well as
likelihood of the project that further helps in reflecting the rank of the risks that further helps
in proper risk management.
PROJECT MANAGEMENT
2.3 Actions taken in controlling budget
The actions which are generally undertaken in order to control the budget of the
project are generally elaborated below:
Keeping track on the project budget: The budget expenditure can be controlled by
keeping track on the budget of the project so that any variance within the project can be
controlled quite successfully (Serrador and Turner 2015).
Proper resource management: Proper management of resources are generally
required for managing the resources effectively so that no extra expenditure will be done if
any shortfall occurs due to unavailability of resources. This not only helps in managing
resources but also assist in controlling budget.
3. Risk identification
3.1 Identification of risk management techniques and tools
The various types of tools as well as techniques which are mainly utilized in order to
manage the risks that are related with the construction work are generally reflected below:
Determination of risk: Porter’s five forces are considered as one of the systematic
tools that are general helpful in determining the risks that are associated with the project.
With the help of ort’s five force analysis, the risks that are associated finance, schedule as
well as management can be identified effectively.
Evaluation of the effect: It is quite important to utilize situational analysis in order to
evaluate the potential effects that are associated with the project risks (Kerzner and Kerzner
2017). With the identified risk, it is quite necessary to determine the consequence as well as
likelihood of the project that further helps in reflecting the rank of the risks that further helps
in proper risk management.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 16
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.