This status report details the implementation of SAP S/4 HANA Business All-in-One in Yes Chemist Pty Ltd, covering the period from July 25, 2016, to October 7, 2016. The project aimed to streamline Yes Chemist's business operations with SAP, but faced delays primarily due to initial phase setbacks. The report outlines the project's overview, completed and pending tasks, risks, and issues encountered during the implementation. It highlights a schedule variance of 3.75 days and a cost variance of $2,340.00, emphasizing the importance of team coordination to mitigate delays. Effective team coordination is crucial for minimizing project delays, which can lead to variances in both schedule and cost. The report also includes figures and tables illustrating project statistics, delayed tasks, completed tasks, pending tasks, and variance analysis.
Document Page
VUIS CONSULTING PTY LTD
STATUS REPORT
PROJECT: Implementing SAP S/4 HANA Business All-in-One in Yes
Chemist Pty Ltd
Date: 05-06-2019
Produced by: [INSERT AUTHOR NAME AND JOB TITLE HERE]
Reporting period: Mon 25-07-16 to Fri 07-10-16
Project summary
The project aims in implementation of SAP to manage the business operations of Yes
Chemist. The SAP deployment project started in 25-07-16 and ended in Fri 07-10-16.
The entire project was divided into a number of phases for enforcing a better control
on the project. However, the project could not be completed as per the schedule
leading as few of the task in interim was delayed and it ended on Thu 13-10-16.
This status report is prepared to understand the project delays and to reflect on the
course of implementation of the project.
Project Overview
The overview of the project is indicated as follows-
Figure 1: Representing the Project Overview
The following template is for educational purposes only.
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Since the task 5, that is, develop project plan actually took 1 week to complete, the
milestone “Plan signed off”, is delayed to Wed 03-08-16. The status date of the project is set
to Wed 03-08-16.
Figure 2: The Status Date
The following figure provides an idea of the statistics of the project as per the set status
date-
Figure 3: The project Statistics
Late Tasks
The tasks that are delayed are indicated as follows-
VUIS Consulting Project Status Meeting Page 2
[Insert Author name here]
Document Page
VUIS Consulting Project Status Meeting Page 3
[Insert Author name here]
Document Page
Figure 4: The Delayed Tasks
Completed tasks
The tasks and the milestone that are 100% complete till date are indicated as follows-
Figure 5: Representing the Tasks that are completed
Pending tasks
The list of tasks that are still pending are indicated in the figure below-
Figure 6: Representing the Pending Tasks
Risk and Issues
The SAP project in Yes Chemist was although implemented as the plan, the major issue that
was faced in the project was delay. The delay was faced in the initial phase of the project
that affected the entire schedule. In order to complete the task on the planned time, it is
essential to invest on the coordination among the team members. An effective team
VUIS Consulting Project Status Meeting Page 4
[Insert Author name here]
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
coordination can help in minimizing the project delays. The delays in the project lead to
variance in the schedule and the cost, which are indicated as follows-
Figure 7: The total Variance
The figure above indicates the variance of the project. It is observed that the variance is of
3.75 days. The cost table below identifies the cost variance of the project.
VUIS Consulting Project Status Meeting Page 5
[Insert Author name here]
Document Page
Figure 8: Showing the Cost Variance
From the figure above, it can be identified that the cost variance in the project is $2,340.00.
VUIS Consulting Project Status Meeting Page 6