This project plan, prepared by VUIS Consulting, details the integration of SAP into Yes Chemist's existing operations. The plan encompasses the project's scope, including aims, objectives, deliverables, and quality standards. It presents a comprehensive business case, justifying the project through identified needs and expected benefits, while also acknowledging potential drawbacks. The plan outlines a detailed project schedule, utilizing a Gantt chart to illustrate tasks, phases, and dependencies. It also allocates resources and provides a budget overview. Moreover, the plan addresses potential risks, proposing mitigation strategies, and establishes a communication plan to ensure effective information flow among stakeholders. The overall goal is to improve Yes Chemist's operational efficiency and data management through the successful implementation of SAP.

VUIS CONSULTING PTY LTD.
PROJECT PLAN [1]
[Integration of SAP in Yes Chemist]
[02-06-2019]
[INSERT AUTHOR NAME HERE]
[Project Manager]
[INSERT AUTHOR EMAIL HERE]
PROJECT PLAN [1]
[Integration of SAP in Yes Chemist]
[02-06-2019]
[INSERT AUTHOR NAME HERE]
[Project Manager]
[INSERT AUTHOR EMAIL HERE]
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

CONTENTS
Glossary............................................................................................................................. 3
Introduction......................................................................................................................... 4
Project scope......................................................................................................................4
Business case..................................................................................................................... 5
Project Schedule and Approach (Rollout strategy)..............................................................6
Resources........................................................................................................................ 10
Budget.............................................................................................................................. 12
Risk................................................................................................................................... 14
Communication................................................................................................................. 15
Summary.......................................................................................................................... 16
VUIS Consulting Project Plan Page 2
[Insert Author name here]
Glossary............................................................................................................................. 3
Introduction......................................................................................................................... 4
Project scope......................................................................................................................4
Business case..................................................................................................................... 5
Project Schedule and Approach (Rollout strategy)..............................................................6
Resources........................................................................................................................ 10
Budget.............................................................................................................................. 12
Risk................................................................................................................................... 14
Communication................................................................................................................. 15
Summary.......................................................................................................................... 16
VUIS Consulting Project Plan Page 2
[Insert Author name here]

Glossary
Term Definition
Project Risks An uncertain event or a condition that can hamper the normal execution of
a project is termed as project Risk
Business
Case
A business case describes whether a project is justified or not and also
provides an idea of the expected benefits.
VUIS Consulting Project Plan Page 3
[Insert Author name here]
Term Definition
Project Risks An uncertain event or a condition that can hamper the normal execution of
a project is termed as project Risk
Business
Case
A business case describes whether a project is justified or not and also
provides an idea of the expected benefits.
VUIS Consulting Project Plan Page 3
[Insert Author name here]
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Introduction
The report introduces the readers to the case study of integration of SAP in Yes Chemist.
The purpose behind undertaking this project and integration SAP in the already existing
internal operation system of Yes Chemist, is to address the issues related to management
as well as operations of similar issues that is being experienced by the staffs of the
organization. The yes Chemist pharmacy chain started off with a family business and it
gradually expanded into a huge business. With the increase in the size of the business it is
gradually becoming difficult for the staffs and the owners of the business to keep a track of
the business processes and the important operations of the organization. The project is been
given to VUISC, who will be in charge of preparation of a realistic and achievable project.
The plan involves estimation of the project scope, the project business case, the schedule
consideration of the project along with the budget. This is a high budget project, which
involve SAP integration with the current manual operations of Yes Chemist. The particular
project plan that is prepared, identifies the critical risks that can affect the execution of the
SAP integration project in Yes Chemist. Since this is a complex project, it is necessary for
the VUISC team to maintain a good communication among the other team members so that
the issues faced are communicated on time. The plan identifies an effective communication
strategy that is needed for the project. The details of the communication plan that is
developed for the SAP integration project is elaborated in the sections below.
Project scope
The part of project planning that deals with the determination along with the documentation
of the specific goals and the deliverables of an undertaken project is considered as the
scope of a project. While identification of the project scope, the features, functions, tasks and
the deadline are estimated along with the estimation of the work that is needed to be
achieved in this project.
Project Aim: The SAP integration project is Yes Chemist is being undertaken by VUICS,
with and aim of eliminating or lessening the operational problems that the pharmacy is
facing.
Project Objectives: The objective of this particular SAP project is indicated as follows-
To provide a clear understanding of the operational issues of the organization
To identify an effective approach of addressing the operational issues
To develop a plan for SAP integration in the existing manual system of yes Chemist
To provide training to the staffs of the Yes chemist on the usage of the new system
that is developed
The deliverables and the quality standard set for the deliverables is indicated as follows-
Project Deliverables Quality Standard
Server Room demolition and preparation for New
System
This entire task is needed to be completed within
the time of fifteen days
The Conversion of the Data that exists The conversion of data need to follow the legacy
data structure
Integration of SAP This should be followed by a detailed Testing
VUIS Consulting Project Plan Page 4
[Insert Author name here]
The report introduces the readers to the case study of integration of SAP in Yes Chemist.
The purpose behind undertaking this project and integration SAP in the already existing
internal operation system of Yes Chemist, is to address the issues related to management
as well as operations of similar issues that is being experienced by the staffs of the
organization. The yes Chemist pharmacy chain started off with a family business and it
gradually expanded into a huge business. With the increase in the size of the business it is
gradually becoming difficult for the staffs and the owners of the business to keep a track of
the business processes and the important operations of the organization. The project is been
given to VUISC, who will be in charge of preparation of a realistic and achievable project.
The plan involves estimation of the project scope, the project business case, the schedule
consideration of the project along with the budget. This is a high budget project, which
involve SAP integration with the current manual operations of Yes Chemist. The particular
project plan that is prepared, identifies the critical risks that can affect the execution of the
SAP integration project in Yes Chemist. Since this is a complex project, it is necessary for
the VUISC team to maintain a good communication among the other team members so that
the issues faced are communicated on time. The plan identifies an effective communication
strategy that is needed for the project. The details of the communication plan that is
developed for the SAP integration project is elaborated in the sections below.
Project scope
The part of project planning that deals with the determination along with the documentation
of the specific goals and the deliverables of an undertaken project is considered as the
scope of a project. While identification of the project scope, the features, functions, tasks and
the deadline are estimated along with the estimation of the work that is needed to be
achieved in this project.
Project Aim: The SAP integration project is Yes Chemist is being undertaken by VUICS,
with and aim of eliminating or lessening the operational problems that the pharmacy is
facing.
Project Objectives: The objective of this particular SAP project is indicated as follows-
To provide a clear understanding of the operational issues of the organization
To identify an effective approach of addressing the operational issues
To develop a plan for SAP integration in the existing manual system of yes Chemist
To provide training to the staffs of the Yes chemist on the usage of the new system
that is developed
The deliverables and the quality standard set for the deliverables is indicated as follows-
Project Deliverables Quality Standard
Server Room demolition and preparation for New
System
This entire task is needed to be completed within
the time of fifteen days
The Conversion of the Data that exists The conversion of data need to follow the legacy
data structure
Integration of SAP This should be followed by a detailed Testing
VUIS Consulting Project Plan Page 4
[Insert Author name here]
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Training the Staffs All the staffs of Yes Chemist are to be provided
with a formal training after the go-live of the
existing system.
The identification of the scope and the deliverables of the project by Yes Chemist is
subjected to certain critical assumptions, which are as follows-
1. The project team will not face any difficulty in securing funding for the project
2. The staffs of Yes Chemist will be interested in taking the needed training
There are certain constraints linked with the delivery and the execution of the project. These
constraints are indicated as follows-
1. The associated maintenance of the system to be developed is only limited to 14 days after
the end of the project
2. There is a time constraint of 15 days for the preparation of the server room.
Business case
Business case of the project is generally prepared to provide the justification of the project to
the funding sources of the project. The business needs of this project is related to the
reducing of loses of Yes Chemist pharmacy due to the inefficiency of the existing system of
the company. The project is highly needed for yes chemist as it aims in reducing the
operational weaknesses and improve the process of data management. With the integration
of the SAP HANA, it is possible for the pharmacy to control all their internal operations in an
effective manner. The benefits that the pharmacy is expected to achieve from the project is
indicated in the table that follows-
Benefits Measure of the Benefits
The operational efficiency of the pharmacy will be
restored
An increase in efficiency of 30 % in 3 months
Better management of the data would be possible Data management is improved by 25% in 3
months
The cost of managing the internal operations will
be reduced
The cost of operations management is reduced
by 30% in six months
The project, although will provide certain integral benefit to the organization, there are a
number of dis benefit of the proposed system as well, which are indicated as follows-
1. With the upgrade of the system, there are high chances of the reduction of the
production.
2. Without proper training, the staffs may not understand the operations,
VUIS Consulting Project Plan Page 5
[Insert Author name here]
with a formal training after the go-live of the
existing system.
The identification of the scope and the deliverables of the project by Yes Chemist is
subjected to certain critical assumptions, which are as follows-
1. The project team will not face any difficulty in securing funding for the project
2. The staffs of Yes Chemist will be interested in taking the needed training
There are certain constraints linked with the delivery and the execution of the project. These
constraints are indicated as follows-
1. The associated maintenance of the system to be developed is only limited to 14 days after
the end of the project
2. There is a time constraint of 15 days for the preparation of the server room.
Business case
Business case of the project is generally prepared to provide the justification of the project to
the funding sources of the project. The business needs of this project is related to the
reducing of loses of Yes Chemist pharmacy due to the inefficiency of the existing system of
the company. The project is highly needed for yes chemist as it aims in reducing the
operational weaknesses and improve the process of data management. With the integration
of the SAP HANA, it is possible for the pharmacy to control all their internal operations in an
effective manner. The benefits that the pharmacy is expected to achieve from the project is
indicated in the table that follows-
Benefits Measure of the Benefits
The operational efficiency of the pharmacy will be
restored
An increase in efficiency of 30 % in 3 months
Better management of the data would be possible Data management is improved by 25% in 3
months
The cost of managing the internal operations will
be reduced
The cost of operations management is reduced
by 30% in six months
The project, although will provide certain integral benefit to the organization, there are a
number of dis benefit of the proposed system as well, which are indicated as follows-
1. With the upgrade of the system, there are high chances of the reduction of the
production.
2. Without proper training, the staffs may not understand the operations,
VUIS Consulting Project Plan Page 5
[Insert Author name here]

3. A high implementation cost is needed.
The above discussed points indicate the benefits and the dis-benefits of the SAP integration
project.
Project Schedule and Approach (Rollout strategy)
An effective project implementation approach is needed to be identified for ascrtaining that
the project is prepared as per plan. For successful integration of SAP to Yes chemist, certain
tasks and phases are identified. The phases and the task are indicated as follows-
VUIS Consulting Project Plan Page 6
[Insert Author name here]
The above discussed points indicate the benefits and the dis-benefits of the SAP integration
project.
Project Schedule and Approach (Rollout strategy)
An effective project implementation approach is needed to be identified for ascrtaining that
the project is prepared as per plan. For successful integration of SAP to Yes chemist, certain
tasks and phases are identified. The phases and the task are indicated as follows-
VUIS Consulting Project Plan Page 6
[Insert Author name here]
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

VUIS Consulting Project Plan Page 7
[Insert Author name here]
[Insert Author name here]
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

The Gantt chart of the SAP integration project, indicating the entire schedule is represented
in the figure below-
VUIS Consulting Project Plan Page 8
[Insert Author name here]
in the figure below-
VUIS Consulting Project Plan Page 8
[Insert Author name here]

VUIS Consulting Project Plan Page 9
[Insert Author name here]
[Insert Author name here]
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Figure 1: The Gantt Chart of Sap Integration Project
The above Gantt chart represents the schedule activities of the project; the tasks shown in
red indicate the critical tasks of the project.
Resources
Appropriate estimation of the resources, critically determine the project success. The
resources considered for the project are indicated as follows-
Figure 2: Resources in Sap Integration Project
The resources assigned for each task as identified in figure 1 is indicated in the figure 3
below-
VUIS Consulting Project Plan Page 10
[Insert Author name here]
The above Gantt chart represents the schedule activities of the project; the tasks shown in
red indicate the critical tasks of the project.
Resources
Appropriate estimation of the resources, critically determine the project success. The
resources considered for the project are indicated as follows-
Figure 2: Resources in Sap Integration Project
The resources assigned for each task as identified in figure 1 is indicated in the figure 3
below-
VUIS Consulting Project Plan Page 10
[Insert Author name here]
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Figure 3: The task Resource Overview
The overview of the resources considered in the project are indicated as follows-
VUIS Consulting Project Plan Page 11
[Insert Author name here]
The overview of the resources considered in the project are indicated as follows-
VUIS Consulting Project Plan Page 11
[Insert Author name here]

Figure 4: The overview of the Resources Considered
Budget
The budget estimated for the project is indicated as follows-
VUIS Consulting Project Plan Page 12
[Insert Author name here]
Budget
The budget estimated for the project is indicated as follows-
VUIS Consulting Project Plan Page 12
[Insert Author name here]
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 16
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.