This assignment delves into project management principles, specifically focusing on the Essendon & Buckley Street level crossing removal project and potential software failures. It meticulously outlines project activities from initiation to closure, including identifying objectives, conducting feasibility studies, and appointing team members. The assignment details dependencies and sequences of activities, resources required, and durations for each task. A bar chart visually represents the project timeline, and the critical path is identified to ensure timely completion. Furthermore, the assignment includes a work breakdown structure (WBS), project completion milestones, a comprehensive budget, and a cost-benefit analysis. Resource allocation is clearly defined in a resource sheet, providing a complete overview of the project's planning and execution phases. Desklib offers a wealth of similar solved assignments and past papers for students seeking additional resources.
Document Page
0
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
Assignment 3: Unit project - Part B
Software Failures
Name of Student
Name of the University
Author Note
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
1
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
Table of Contents
Project Activities.............................................................................................................................2
Activity List:................................................................................................................................2
Dependencies and Sequence of Above Activities...........................................................................4
Resources Required for each Activity.........................................................................................6
Duration of each activity...........................................................................................................11
Bar Chart....................................................................................................................................13
Critical Path...............................................................................................................................15
WBS...........................................................................................................................................17
Project Completion Date (Milestones and durations)................................................................17
Budget........................................................................................................................................18
Cost Benefit Analysis................................................................................................................20
Resource Sheet:.........................................................................................................................23
References......................................................................................................................................24
Document Page
2
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
Project Activities
Activity List:
WBS Task Name Duration Start Finish
0
Essendon & Buckley Street level crossing
removal 985 days Wed 4/25/18 Tue 2/1/22
1 Initiation phase of the project 73 days Wed 4/25/18 Fri 8/3/18
1.1 Identifying objectives of the project 15 days Wed 4/25/18 Tue 5/15/18
1.2 Undertaking feasibility study 20 days Wed 5/16/18 Tue 6/12/18
1.3 Establishing project charter 16 days Fri 7/13/18 Fri 8/3/18
1.4 Appointing team members of the project 22 days Wed 6/13/18 Thu 7/12/18
1.5
Milestone 1: Completion of project initiation
phase 0 days Fri 8/3/18 Fri 8/3/18
2 Planning phase of the project 148 days Mon 8/6/18 Wed 2/27/19
2.1 Site investigations 22 days Mon 8/6/18 Tue 9/4/18
2.2 Solution announced 20 days Wed 9/5/18 Tue 10/2/18
2.3 Community information sessions 25 days Wed 10/3/18 Tue 11/6/18
2.4 Trader consultation 26 days Wed 11/7/18 Wed 12/12/18
2.5 Assessment of design options 26 days Thu 12/13/18 Thu 1/17/19
2.6 Lowering Buckley street under rail line 29 days Fri 1/18/19 Wed 2/27/19
2.7 Milestone 2: Completion of planning phase 0 days Wed 2/27/19 Wed 2/27/19
3 Procurement phase 420 days Thu 2/28/19 Wed 10/7/20
3.1 Community input on design elements 32 days Thu 2/28/19 Fri 4/12/19
Document Page
3
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
3.2 North west alliance project partner announced 39 days Mon 4/15/19 Thu 6/6/19
3.3 Construction partner announced 134 days Fri 6/7/19 Wed 10/7/20
3.4 Community consultation 47 days Fri 6/7/19 Mon 8/12/19
3.5 Refinement of design including community inputs 50 days Tue 8/13/19 Mon 10/21/19
3.6 Finalizing design 42 days Tue 10/22/19 Wed 12/18/19
3.7 Milestone 3 : Completion of procurement phase 0 days Wed 12/18/19 Wed 12/18/19
4 Construction phase 480 days Thu 12/19/19 Wed 10/20/21
4.1 On-going community consultation 32 days Thu 12/19/19 Fri 1/31/20
4.2 Construction commences 34 days Mon 2/3/20 Thu 3/19/20
4.3 Preparatory work commenced 43 days Fri 3/20/20 Tue 5/19/20
4.4 Finalized design released to the community 90 days Wed 5/20/20 Wed 12/9/20
4.5
Contract awarded for Buckley street level crossing
removal project 156 days Wed 5/20/20 Thu 5/20/21
4.6 Early works commence 102 days Wed 5/20/20 Thu 10/8/20
4.7 Major works commence 48 days Thu 12/10/20 Mon 2/15/21
4.8 Boom gates removed 112 days Tue 2/16/21 Wed 7/21/21
4.9 Finalizing landscapes 65 days Thu 7/22/21 Wed 10/20/21
4.10 Milestone 4: Completion of Construction phase 0 days Wed 10/20/21 Wed 10/20/21
5 Closure phase 74 days Thu 10/21/21 Tue 2/1/22
5.1 Post-project review 20 days Thu 10/21/21 Wed 11/17/21
5.2 Stakeholder-sign off 30 days Thu 11/18/21 Wed 12/29/21
5.3 Documentation 24 days Thu 12/30/21 Tue 2/1/22
5.4 Milestone 4: Completion of project closure phase 0 days Wed 11/17/21 Wed 11/17/21
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
4
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
Dependencies and Sequence of Above Activities
WBS Task Name Duration Start Finish Predecessors
0
Essendon & Buckley Street level
crossing removal 985 days Wed 4/25/18 Tue 2/1/22
1 Initiation phase of the project 73 days Wed 4/25/18 Fri 8/3/18
1.1 Identifying objectives of the project 15 days Wed 4/25/18 Tue 5/15/18
1.2 Undertaking feasibility study 20 days Wed 5/16/18 Tue 6/12/18 2
1.3 Establishing project charter 16 days Fri 7/13/18 Fri 8/3/18 3
1.4 Appointing team members of the project 22 days Wed 6/13/18 Thu 7/12/18 3
1.5
Milestone 1: Completion of project
initiation phase 0 days Fri 8/3/18 Fri 8/3/18 5,4
2 Planning phase of the project 148 days Mon 8/6/18 Wed 2/27/19
2.1 Site investigations 22 days Mon 8/6/18 Tue 9/4/18 6
2.2 Solution announced 20 days Wed 9/5/18 Tue 10/2/18 8,6
2.3 Community information sessions 25 days Wed 10/3/18 Tue 11/6/18 9
2.4 Trader consultation 26 days Wed 11/7/18 Wed 12/12/18 10,9
2.5 Assessment of design options 26 days Thu 12/13/18 Thu 1/17/19 11
2.6 Lowering Buckley street under rail line 29 days Fri 1/18/19 Wed 2/27/19 12,11
2.7
Milestone 2: Completion of planning
phase 0 days Wed 2/27/19 Wed 2/27/19 13
3 Procurement phase 420 days Thu 2/28/19 Wed 10/7/20
Document Page
5
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
3.1 Community input on design elements 32 days Thu 2/28/19 Fri 4/12/19 14
3.2
North west alliance project partner
announced 39 days Mon 4/15/19 Thu 6/6/19 16,14
3.3 Construction partner announced 134 days Fri 6/7/19 Wed 10/7/20 17
3.4 Community consultation 47 days Fri 6/7/19 Mon 8/12/19 17
3.5
Refinement of design including
community inputs 50 days Tue 8/13/19 Mon 10/21/19 19
3.6 Finalizing design 42 days Tue 10/22/19 Wed 12/18/19 20
3.7
Milestone 3 : Completion of procurement
phase 0 days Wed 12/18/19 Wed 12/18/19 21,20
4 Construction phase 480 days Thu 12/19/19 Wed 10/20/21
4.1 On-going community consultation 32 days Thu 12/19/19 Fri 1/31/20 22
4.2 Construction commences 34 days Mon 2/3/20 Thu 3/19/20 24,22
4.3 Preparatory work commenced 43 days Fri 3/20/20 Tue 5/19/20 25
4.4
Finalized design released to the
community 90 days Wed 5/20/20 Wed 12/9/20 26
4.5
Contract awarded for Buckley street level
crossing removal project 156 days Wed 5/20/20 Thu 5/20/21 26
4.6 Early works commence 102 days Wed 5/20/20 Thu 10/8/20 26
4.7 Major works commence 48 days Thu 12/10/20 Mon 2/15/21 27
4.8 Boom gates removed 112 days Tue 2/16/21 Wed 7/21/21 30
4.9 Finalizing landscapes 65 days Thu 7/22/21 Wed 10/20/21 31
4.10 Milestone 4: Completion of Construction 0 days Wed 10/20/21 Wed 10/20/21 32
Document Page
6
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
phase
5 Closure phase 74 days Thu 10/21/21 Tue 2/1/22
5.1 Post-project review 20 days Thu 10/21/21 Wed 11/17/21 33
5.2 Stakeholder-sign off 30 days Thu 11/18/21 Wed 12/29/21 35,33
5.3 Documentation 24 days Thu 12/30/21 Tue 2/1/22 35
5.4
Milestone 4: Completion of project closure
phase 0 days Wed 11/17/21 Wed 11/17/21 35
Resources Required for each Activity
WBS Task Name Duration Start Finish Resource Names
0
Essendon & Buckley
Street level crossing
removal
985 days Wed 4/25/18 Tue 2/1/22
1
Initiation phase of the
project 73 days Wed 4/25/18 Fri 8/3/18
1.1
Identifying objectives of
the project 15 days Wed 4/25/18 Tue 5/15/18 Project manager
1.2
Undertaking feasibility
study 20 days Wed 5/16/18 Tue 6/12/18 Project manager
1.3
Establishing project
charter 16 days Fri 7/13/18 Fri 8/3/18
Project manager, Project
planner
1.4
Appointing team
members of the project 22 days Wed 6/13/18 Thu 7/12/18
Project manager, Project
planner
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
1.5
Milestone 1: Completion
of project initiation
phase
0 days Fri 8/3/18 Fri 8/3/18
2
Planning phase of the
project 148 days Mon 8/6/18 Wed 2/27/19
2.1 Site investigations 22 days Mon 8/6/18 Tue 9/4/18
Supervisor, Construction
manager
2.2 Solution announced 20 days Wed 9/5/18 Tue 10/2/18
Construction technician,
Contractor, Equipment cost[1]
2.3
Community information
sessions 25 days Wed 10/3/18 Tue 11/6/18
Construction manager,
Contractor
2.4 Trader consultation 26 days Wed 11/7/18 Wed 12/12/18
Construction manager,
Contractor
2.5
Assessment of design
options 26 days Thu 12/13/18 Thu 1/17/19
Construction manager,
Contractor, Sub-contractor
2.6
Lowering Buckley street
under rail line 29 days Fri 1/18/19 Wed 2/27/19
Architect, Construction
manager, Construction
technician, Sub-contractor
2.7
Milestone 2: Completion
of planning phase 0 days Wed 2/27/19 Wed 2/27/19
3 Procurement phase 420 days Thu 2/28/19 Wed 10/7/20
3.1 Community input on 32 days Thu 2/28/19 Fri 4/12/19 Cost for removing level
Document Page
8
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
design elements
crossing[1], Supervisor,
Architect, Construction
technician, Equipment cost[1]
3.2
North west alliance
project partner
announced
39 days Mon 4/15/19 Thu 6/6/19
Supervisor, Architect,
Construction manager,
Contractor, Procurement
manager
3.3
Construction partner
announced 134 days Fri 6/7/19 Wed 10/7/20
Supervisor, Architect,
Construction technician,
Contractor, Procurement
manager
3.4 Community consultation 47 days Fri 6/7/19 Mon 8/12/19
Cost for removing level
crossing[1], Architect,
Construction technician,
Contractor
3.5
Refinement of design
including community
inputs
50 days Tue 8/13/19 Mon 10/21/19
Architect, Construction
technician, Contractor,
Financial manager,
Procurement manager
3.6 Finalizing design 42 days Tue 10/22/19 Wed 12/18/19
Supervisor, Architect,
Equipment cost[1],
Procurement manager
Document Page
9
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
3.7
Milestone 3 :
Completion of
procurement phase
0 days Wed
12/18/19 Wed 12/18/19
4 Construction phase 480 days Thu 12/19/19 Wed 10/20/21
4.1
On-going community
consultation 32 days Thu 12/19/19 Fri 1/31/20
Supervisor, Architect,
Contractor, Procurement
manager, Sub-contractor
4.2
Construction
commences 34 days Mon 2/3/20 Thu 3/19/20
Cost for removing level
crossing[1], Project manager,
Architect, Construction
technician, Procurement
manager
4.3
Preparatory work
commenced 43 days Fri 3/20/20 Tue 5/19/20
Cost for removing level
crossing[1], Supervisor,
Architect, Construction
technician, Contractor,
Equipment cost[1], Sub-
contractor
4.4
Finalized design
released to the
community
90 days Wed 5/20/20 Wed 12/9/20
Supervisor, Architect,
Construction manager,
Construction technician,
Procurement manager
4.5 Contract awarded for 156 days Wed 5/20/20 Thu 5/20/21 Cost for removing level
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
10
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
Buckley street level
crossing removal project
crossing[1], Project manager,
Architect, Construction
technician, Contractor, Sub-
contractor
4.6 Early works commence 102 days Wed 5/20/20 Thu 10/8/20
Cost for removing level
crossing[1], Architect,
Construction manager,
Construction technician,
Equipment cost[1]
4.7 Major works commence 48 days Thu 12/10/20 Mon 2/15/21
Cost for removing level
crossing[1], Project manager,
Supervisor, Architect,
Construction manager,
Construction technician, Sub-
contractor
4.8 Boom gates removed 112 days Tue 2/16/21 Wed 7/21/21
Cost for removing level
crossing[1], Project manager,
Architect, Construction
manager, Construction
technician, Contractor
4.9 Finalizing landscapes 65 days Thu 7/22/21 Wed 10/20/21 Architect, Construction
manager, Construction
technician, Contractor, Sub-
Document Page
11
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
contractor
4.10
Milestone 4: Completion
of Construction phase 0 days Wed
10/20/21 Wed 10/20/21
5 Closure phase 74 days Thu 10/21/21 Tue 2/1/22
5.1 Post-project review 20 days Thu 10/21/21 Wed 11/17/21
Project manager, Project
planner
5.2 Stakeholder-sign off 30 days Thu 11/18/21 Wed 12/29/21
Project manager, Project
planner
5.3 Documentation 24 days Thu 12/30/21 Tue 2/1/22
Project manager, Project
planner
5.4
Milestone 4: Completion
of project closure phase 0 days Wed
11/17/21 Wed 11/17/21
Duration of each activity
WBS Task Name Duration Start Finish
0
Essendon & Buckley Street level crossing
removal 985 days Wed 4/25/18 Tue 2/1/22
1 Initiation phase of the project 73 days Wed 4/25/18 Fri 8/3/18
1.1 Identifying objectives of the project 15 days Wed 4/25/18 Tue 5/15/18
1.2 Undertaking feasibility study 20 days Wed 5/16/18 Tue 6/12/18
1.3 Establishing project charter 16 days Fri 7/13/18 Fri 8/3/18
1.4 Appointing team members of the project 22 days Wed 6/13/18 Thu 7/12/18
1.5 Milestone 1: Completion of project initiation 0 days Fri 8/3/18 Fri 8/3/18