ABC Construction: Analyzing Project Delay in University Residence Hall
VerifiedAdded on  2022/12/20
|2
|478
|56
Report
AI Summary
This report presents a memorandum from a scheduling consultant regarding a 12-day delay in a university residence hall project by ABC Construction. The delay is attributed to a drilling rig breakdown by subcontractor Mchole Drilling Co., resulting in a potential penalty of $240,000. The memo evaluates three options: repairing the rig, hiring another subcontractor, or accepting the delay and finding a parallel subcontractor. Option two, hiring an additional subcontractor for $15,000, is recommended due to its cost-effectiveness compared to the other options. The memo highlights the importance of mitigating project delays and provides a clear recommendation for the vice president's consideration.
1 out of 2



