This report provides a critical analysis of the procurement method employed in the Southern Cross Station project, a major infrastructure development in Melbourne, Australia. The project, overseen by the Southern Cross Station Authority on behalf of the Victorian State Government, utilized a Public-Private Partnership (PPP) approach. The report examines the characteristics of PPP, including its advantages and disadvantages, and evaluates its suitability for the project, considering factors like cost, time, risk, and client expertise. The analysis reveals that the PPP method contributed to delays and cost overruns, suggesting that alliancing contracting might have been a more appropriate procurement method. The report also explores factors influencing the choice of construction procurement methods and assesses the reasons behind the selection of PPP for the Southern Cross Station project, ultimately offering an opinion on the effectiveness of the chosen approach and its impact on the project's success. The project's characteristics such as size, complexity, and the need for change management are also considered. The report concludes by assessing the overall effectiveness of the chosen procurement method, providing a comprehensive overview of the project's procurement strategy and outcomes.
Document Page
Alliancing Procurement Method 1
ALLIANCING PROCUREMENT METHOD
ASSIGNMENT 2
CRITICAL ANALYSIS REPORT
STUDENT NAME
STUDENT ID
COURSE NAME
PROFESSOR
UNIVERSITY
CITY/STATE
DATE
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Alliancing Procurement Method 2
Table of Contents
Executive Summary...................................................................................................................................3
1. Introduction.......................................................................................................................................4
1.1. Purpose of the Report................................................................................................................4
1.2. Project Description....................................................................................................................4
2. Factors Affecting Choice of Construction Procurement Method...................................................7
2.1. Cost.............................................................................................................................................8
2.2. Time............................................................................................................................................8
2.3. Clients’ expertise and requirements.........................................................................................8
2.4. Project characteristics...............................................................................................................9
2.5. Ability to make changes............................................................................................................9
2.6. Risks..........................................................................................................................................10
2.7. Industry preference.................................................................................................................10
2.8. External factors........................................................................................................................10
3. Procurement method used in Southern Cross Station Project.....................................................10
3.1. Characteristics of PPP Procurement Method........................................................................11
3.2. Advantages of PPP Procurement Method..............................................................................12
3.3. Disadvantages of PPP Procurement Method.........................................................................14
4. Important Procurement Characteristics........................................................................................15
5. Potential Reasons Why PPP was Selected for Southern Cross Station Project..........................16
6. Popularity of PPP Procurement Method.......................................................................................17
7. Opinion.............................................................................................................................................18
8. Conclusion........................................................................................................................................19
References................................................................................................................................................20
Document Page
Alliancing Procurement Method 3
Executive Summary
Procurement method is very important in construction industry. The procurement method used
can cause project success or failure. Thus it is very important for the client to select the most
suitable procurement method. The purpose of this report is to critically analyze the procurement
method used in executing the Southern Cross Station project. This was a mega infrastructure
development project owned by the Southern Cross Station Authority on behalf of the Victorian
State Government. The project was executed using public private partnership (PPP) where the
government collaborated with private parties to implement the project. Considering the
characteristics and objectives of the project, PPP was not the most suitable procurement method.
This method contributed to the late completion of the project due to numerous disputes and cost
overruns The best method that would have been used in this project is alliancing contracting.
Document Page
Alliancing Procurement Method 4
1. Introduction
1.1. Purpose of the Report
Procurement is a very crucial process in every construction project. This is the process that
determines how the project will be executed, key stakeholders and the overall efficiency of
project execution. Therefore it is very important for clients to ensure that they select the most
appropriate procurement method so as to complete their projects within stipulated time and
budget, and to the required industry standards and quality. This report aims at analyzing different
construction procurement methods so as to select the best method for Southern Cross Station
project. The project was executed using public private partnership (PPP) procurement method
and so this report will investigate if this method was appropriate or whether there is a better
procurement method for the project.
1.2. Project Description
Southern Cross Station (formerly known as Spencer Street Station) is one of the mega
projects that was designed to transform and improve transport infrastructure in Melbourne,
Victoria, Australia. The project is located in Docklands, Melbourne, on Spencer Street between
La Trobe Street and Collins Street. This station is Victoria’s civic landmark and one of the
biggest infrastructure projects in Melbourne, Australia. It is the 3rd busiest railway station in
Melbourne, having an average daily commuter traffic of 100,000 (Railway Technology, 2018).
The railway station is owned by IFM Investors and operated by AssetCo Management. IFM
Investors has signed a 30-year lease agreement with Victorian State Government to own, operate
and maintain the station until 2036. The agreement is under a PPP.
Southern Cross Station has different features, components and facilities. They include the
transport interchange redevelopment, 16 platforms, 22 rail tracks, a retail plaza, main office
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Alliancing Procurement Method 5
building, residential towers, passenger information screens displaying real time train departure
and arrival information, 30-bay coach station, 800-cars parking facilities, 5-minute pick up and
drop off area and improved public facilities. The station is characterized by high-quality
baggage-handling, ticketing and waiting services. All these facilities are equipped with state-of-
the-art passenger information display, lighting and seating systems. The station is renowned for
its unique architectural trapezoidal roof system that covers a whole city block of approximately
600,000 m2. The main objectives of this project were to provide practical transport experience by
transforming the existing bus terminus and railway station into a first-rate inter-modal transport
facility, ease movement of passengers, improve staffs’ working environment and make Southern
Cross Station a major transport and retain hub. The station serves interstate, regional and
metropolitan bus and rail commuters. The target of the project was to manage 15 million
passengers annually and increase this number to 45 million by 2020.
Southern Cross Station project started in 2000 when the then Southern Cross Station
Authority, a representative of the Victorian State Government, was mandated to oversee the
procurement, financing, construction and operation of the project. In 2002, the Authority signed
a Services and Development Agreement with Civic Nexus Pty Ltd, a private consortium, to
design, construct and operate the station for a period of 30 years. Construction works started in
2002 and were scheduled to be completed in 2005. Nevertheless, construction works did not
commence as expected due to contractual disputes, cost overruns and delays until 2006
(McCann, et al., 2015). Other partners involved in the construction of Southern Cross Station
were: Grimshaw Jackson Joint Venture (architects), Leighton Contractors (builders), Delaware
North Australia, Honeywell Limited, ABN AMRO and Daryl Jackson Architecture. The entire
Document Page
Alliancing Procurement Method 6
project was executed by Civic Nexus consortium, which contracted the other partners. The
primary owner of the project is Public Transport Victoria.
As stated before, this project was executed under a PPP. It was initially estimated to cost
A$350 million but it is estimated to have cost A$700 million. Construction works commenced in
2002 and ended in 2013. Every year, Civic Nexus is paid A$30 million for operating and
maintaining the facility. This will go on until 2036 when the 30-year lease agreement expires.
Southern Cross Station Redevelopment project was not completed within stipulated time and
budget due to the wrong choice of procurement method.
Below are some photos of the Southern Cross Station
Document Page
Alliancing Procurement Method 7
2. Factors Affecting Choice of Construction Procurement Method
There are several factors that should be considered when selecting a construction
procurement method. Some of these include: project completion speed, project cost certainty,
authority and ability of the client to make changes, the level of quality needed, the cost of
implementing the procurement method, risk management techniques, and clarity of defining the
responsibility of each stakeholder (Zuo, 2008). All these factors affect the choice of construction
procurement method for a particular project. The choice of procurement methods helps in
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Alliancing Procurement Method 8
avoiding numerous problems and plays a big role in attaining the specific project goals and
objectives (Clamp, et al., 2009). Some of these factors are discussed below:
2.1. Cost
Cost is one of the biggest factors that determine the choice of construction procurement
method. The cost is usually determined during the design stage of the project, with some
uncertainties. Some procurement methods are more expensive than others hence the client should
select a method that he/she can afford. It must be noted that the client will have to pay some of
his/her team depending on the type of procurement method chosen. Hence the client should
choose a procurement method that he/she is ready and able to pay its associated expenses. The
initial cost of Southern Cross Station project was estimated to be A$350 million but the project’s
final value was about A$700 million.
2.2. Time
Time is another factor that affect the choice of construction procurement method. Most
projects have timelines hence the procurement method selected should enable the tem to
complete it within stipulated time. Some methods allow design and construction phases to
overlap while others require the project to be designed completely before the start of
construction. If the project has a short deadline then procurement methods that allow overlapping
of design and construction phases should be considered. However, these methods also have their
challenges such as cost uncertainty and unclear project scope, among others.
2.3. Clients’ expertise and requirements
The relevant knowledge, experience and skills in construction projects also play a key role in
the selection of construction procurement method. For this reason, it is important to know the
knowledge, abilities, experience and requirements of the client before selecting the most
Document Page
Alliancing Procurement Method 9
appropriate procurement method. Clients who do not have comprehensive knowledge, skills and
experience in construction projects should select a procurement method that will enable them
play their role indirectly – by involving their knowledgeable and experienced representatives
such as consultants, project managers, engineers, etc. Therefore there are different procurement
methods that are suitable for clients with different levels of knowledge and experience in the
construction industry. The most important thing is for the client to select a procurement method
that will ensure that his/her requirements are met and opinions considered in every decision that
is made by the project team.
2.4. Project characteristics
Characteristics of the project also affect the choice of procurement method used for a
particular project. These characteristics include: project size, location, complexity, uniqueness,
risks, use, etc. Each of these characteristics has unique impacts on the project hence the
procurement method selected should address them.
2.5. Ability to make changes
Different construction procurement methods give the client varied levels of ability to make
changes to the project design or scope. Some methods allow the client to make changes at any
time while others have very limited provisions for the same. It is worth noting that making
changes to the project scope during construction stage has huge implications on project cost and
time. Therefore it is usually recommended that the project scope and design are completed
before the start of construction phase. Most importantly is that each procurement method gives
the client a different level of ability to make changes to the project scope.
Document Page
Alliancing Procurement Method 10
2.6. Risks
Each construction project has unique risks. If these risks are not properly identified, analyzed
and mitigated or prevented, they cause a lot of problems. In this regard, the client should ensure
that the construction procurement method selected allocates or transfers risks appropriately t
various stakeholders. The persons allocated the risks should fully understand the risks and take
full responsibility.
2.7. Industry preference
This is also another factor that should be considered when selecting a construction
procurement method. The client should consider the procurement method that most stakeholders
are conversant with in the area where the project is being executed. This will make it easier for
all stakeholders to understand each other and work as a team. Choosing a familiar procurement
method also prevents the likelihood of conflicts and legal issues among stakeholders involved in
the project.
2.8. External factors
There are also other external factors that influence the choice of a construction procurement
method. Some of these factors include: legal factors, political factors, climatic factors,
technological factors, social or community factors, etc. These factors create uncertainty if they
arise when the project is ongoing.
3. Procurement method used in Southern Cross Station Project
The procurement method used in Southern Cross Station project was PPP. As stated before,
Victorian State Government signed a PPP with Civic Nexus to design, finance, construct, operate
and maintain the project. PPP is a procurement method where governments collaborate with
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Alliancing Procurement Method 11
private companies so as to procure mega projects of high value, and signs an agreement to share
risks and opportunities of the project (Plantinga & Doree, 2016). This procurement method is
mainly used for public infrastructure projects such as roads, bridge, railways, etc. In this method,
a private party makes an agreement to finance the project.
3.1. Characteristics of PPP Procurement Method
PPP is an innovative procurement method of delivering mega infrastructure projects (Tang,
et al., 2010). This method involves collaboration between private and public sector so as to
design, finance, execute, manage and maintain a project (Fernandez, et al., 2016). In this method,
the project is usually financed largely by the private entity and partially by the government
(Robert, et al., 2014). The method is usually used for infrastructure development projects (Al-
Saadi & Abdou, 2016), (Ke, 2014). In PPP, the public sector and private sector involved have
specific responsibilities (Polyakova & Vasilyewa, 2016). The method transfers risks to parties
(developers, financiers, construction contractors, suppliers, service providers and operators) that
best understands them and which are able to manage them effectively. This method is gaining
popularity in many parts of the world including Australia (Wilson, et al., 2010). The main
characteristics of PPP are as follows:
Single private entity: in PPP procurement method, the government awards the whole project
to a single private entity or contractor. This allows the private entity to develop smarter and
better solutions for the project.
Financing: in most cases, the private sector consortium finances the entire project under a
PPP project. Once the project is complete, the government starts paying the private sector
consortium over an agreed period of time – usually 25-30 years. During this period, the private
sector consortium owns the project and rents it to the government.
Document Page
Alliancing Procurement Method 12
Preparation time: it usually takes longer to prepare and submit bids using PPP approach. This
is because both the public and private sectors have to perform due diligence and comprehensive
analyses of the project before making the final decision.
Risk: the levels of risks in PPP are relatively high due to the size and complexity of projects
executed under this procurement method. The risks are shared between the private sector and
public sector even though former bears the highest risk (Rodriguez, 2017). The consortium
therefore factors these risks into the bid price of the project.
Maintenance: since the private sector consortium is responsible for the maintenance of the
project once it is completed, the maintenance cost is factored in the project’s overall cost.
Expertise: PPP allows governments to capitalize on the best expertise in the private sector.
Under this procurement method, the government engage private entities with the best knowledge,
skills and expertise.
Relationships: PPPs fosters building of long-term relationship between the private and public
sectors.
3.2. Advantages of PPP Procurement Method
PPP procurement method has numerous benefits. Some of these are as follows:
Innovation: PPP procurement method brings great innovation from the private sector to
deliver public projects (World Bank Group, 2016). The private consortium involved in the
project always selects the most qualified professionals to undertake specific tasks of the project.
These professionals usually provide innovative solutions that are cost effective, environmentally
friendly and more efficient.