Singapore University SIB Project Implementation Report - BUS353e

Verified

Added on  2022/09/14

|14
|709
|19
Report
AI Summary
This report analyzes the implementation of a Smart Building (SIB) project, undertaken by DWS, a Singaporean SME. The project, initiated in September 2019 with a target completion by December 26, 2019, aimed to meet specific objectives and priorities, including compliance with IMDA requirements and a CPI of at least 1. The project faced challenges, including schedule changes due to resource over-allocation and software bugs, which pushed the completion date to January 3, 2020. Cost overruns were also encountered, exceeding the initial budget due to factors like increased equipment costs, rework, and errors in cable estimation. The report highlights contributing events, such as improper schedule estimation and resource leveling, which led to delays and cost increases. Despite these challenges, the project provided valuable learning opportunities in project management, including planning, scheduling, and understanding CPI. The report concludes with recommendations for future projects, emphasizing the importance of accurate project planning, cost estimation, and resource management.
Document Page
SIB Project
Implementation
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Project Objectives
DWS is a fast-growing
SME in Singapore
DWS has planned to
work on the smart
building project
DWS has secured a
project to implement a
smart building system
The project needs to
start of September 2,
2019
The project is required
to be completed early
in January 2020
However, the
preferable completion
date of the project is
December 26, 2019
Document Page
Project Priorities
The priorities of the project are indicated as
follows-
o The SIB project needs to comply with the
IMDA’s requirement
o The project should have a CPI of at least 1
o Therefore, cost and the performance of the
project are two top most project priorities
Document Page
Meeting Project Objectives
and Priorities
After the execution of the project, a few of the
priorities and the objectives of the project are met.
However, the project could not be implemented
with a CPI of 1 as the CPI turned out to be .97
The project could not be completed within
December 26 as it is completed in January 3, 2019
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Changes in the Schedule
A lot of changes in the schedule is observed during
project progress
At first due to over allocation of the resources, the end
date of the project moved from December 6 to
December 30.
Apart from that, identification of a software bug
resulted in addition of three more days in the project’s
schedule pushing the completion date to January 3,
2020.
Document Page
Contributing Events
A number of contributing events added to the
delay in the completion of the project
The estimation of schedule along with over
allocation of the resources contributed to
improper estimation
Solving the resource over allocation within
slack time was not possible
Document Page
Contributing Events (Cont..)
The contributing events for the delays in project
progress are indicated as follows-
The levelling of the resource to the available time
resulted in increase in the time required for project
completion
Apart from that, the late identification of the
software bugs pushed the end date of the project to
January 3, 2020
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Cost Overruns
There is a cost overrun in consideration to the
original estimated budget of the project
o The original estimated cost of the project was
$297,000.00
o However, the completion cost of the project
turned out to be$305,600.00
Document Page
Contributors of Cost
Overruns
There are a number of contributors of cost overrun in
a project, which are indicated as follows-
o Appreciation of the US dollars increased equipment
cost by 6%
o Reworks in the data room rendered an additional
cost of $3000
Document Page
Contributors of Cost
Overruns (cont..)
o There was an error in the estimation of the cable required
in the project and the length of the cable required.
o This incurred an additional cost of $ 2,000
The main contributors of the cost overrun are summarized.
However, although the 1st contributor could not be
addressed, it was possible to address and manage all the
other contributors of cost increase.
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Lesson Learnt
This course and the assignment have provided me a
good learning opportunity
I have learnt about the various processes of
managing a project
I could gather skills necessary to plan and schedule
a project in MS project.
Document Page
Lesson Learnt (cont..)
This course work have helped me to understand the
concept of CPI and its need in project
management
I have gathered knowledge about various conflict
resolution techniques that are necessary for solving
the issues within a project team
I have learn to work efficiently with MS Project
Document Page
Suggestion for future Projects
There are a number of problems faced in execution
of the SIB project starting from poor project planning
to improper cost estimation
For future projects, it is recommended that the
estimation of the project and development of the
project plan should consider all the constraints in the
project
The budget estimation for the project must be more
accurate
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser