This document presents a detailed project plan for organizing the SickKids Gala on October 21, 2017. It includes an executive summary outlining the budget ($110,000) and projected profit ($95,000), a timeline with key deadlines, and a breakdown of event logistics. The plan covers various aspects, including venue selection (The Eglington Grand), guest list (subscribers, donors, performers, speakers), catering, silent auction, marketing strategies (website, social media, email invitations), volunteer coordination, and risk assessment. A work breakdown structure, responsibility matrix, and communication plan are also provided, ensuring clear task delegation and communication among stakeholders (SickKids Foundation, project team, subject experts, and project manager Nancy). The document aims to secure approval for the budget and deadlines to ensure the successful execution of the fundraising gala for the SickKids Foundation.
Document Page
[School]
[Course title]
Sickkids gala
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Executive Summary
Michael Apkon,
Attached is a detailed outline of all components required to organize the
SickKids Gala on October 21, 2017. Our estimated budget is $110 000.The
estimated profit of the event is $95 000. The Gala will take place in The
Eglington Grand due to the locational convenience, open space for
decorative opportunities and great backdrop for photos. The following is a
list of summarized deadlines
February 21, 2017: A confirmed committee, rooms for out of town
guests, MC confirmation, developing a theme and contacting speakers,
photographer and a videographer, sponsorship opportunities outreach,
and a finalized volunteer list.
April 21, 2017: $5000 deposit for venue, save-the-date
communication, sending sponsor invitations, setting print times for
program pamphlet, meet with catering company for food menu,
confirming the menu, audio-visual equipment format with the venue
manager, floral arrangement confirmation, event marketing (posters,
social media outreach, etc.).
September 21, 2017: Catering deposit, RSVP list confirmation.
October 7, 2017: Hotel room count confirmation, print program
pamphlet, final RSVP list- all tickets are to be sold.
October 14, 2017: Check audio- visual aspects of the venue, write
SickKids Gala day schedule in preparation for the event (delegation of
tasks and scheduled event).
October 21, 2017: Following the previously written SickKids Gala
schedule to ensure proper set up and execution of the event.
Looking for your confirmation and approval on the estimated budget and
deadlines so we can go forward with this project and ensure its success.
Thank you,
SickKids Gala organizing team
Overview
Execution
Date: Saturday, October 21 (8 months) 5:00PM-12:00AM
Venue: The Eglington Grand
Event Layout
o Cocktails and appetizers before dinner
o Silent auction throughout the night
o Seating and special speakers after cocktail hour
o Followed by dinner and a live performance
Guests
Document Page
o Subscribers
o Donors
MC/host
Performers
o Special guest speakers (2)
o Artists: DJ, and Owl City
Food/Catering
o Catering company waiters
o Wine
o Gourmet foods
Silent Auction (all funds donated)
o 21 items at high value
Photographer
o Videographer (1)
o Photo taker (1)
Decorations
o Floral Arrangements
o Table Cards
Volunteers
o Set up/tear down
Marketing
o SickKids Website
o Support Groups
o Social Media Promotions from headliners
o Email invitations to subscribers/ donors
Invitations
o 10 Free Invitations
Music
o Owl City Performance
o DJ
Hotel Discounts for out of town guests
o Hotel Recommendations
Menu
o Vegetarian
o Non-vegetarian
o 3 courses
Introduction
Value Proposition
The purpose of this project is to collect fund from both tickets and
auction activities to support SickKids Foundation. SickKids is the second-
Document Page
largest pediatric research hospital in the world, and philanthropy is a critical
source of funding for SickKids Hospital. Their foundation hold many events
for fundraising every year and our project team want to be one of it.
Requirements
Stakeholders
Customer
o SickKids: receiving the money, to ensure that the name is
associated with a positive experience
Project Users
o Patrons/supporters: To provide the resources necessary to help
SickKids organization save lives
o Patients: benefactors of SickKids
Project Sponsor
o CEO of SickKids: To approve project plans, time, scope and
budget
Project Team
o Organizing team supporting Nancy: Amalia, Lenore Lang, Boyang
Subject Experts
o Special Speakers: providing information and spreading
awareness about the cause
o Catering Employees: Using their serving knowledge to provide
good service
o Security: To ensure safety of guests and performers
Project Manager
o Nancy: Ensure successful completion of project
Stakeholders involved in the project are:
SickKids Foundation, as the customer who will receiving the fund collected
from our gala, to ensure that what our team doing is on the track and its
name is associated with a positive experience.
Project users are consisting of patrons and patients. Patrons will act as
supporters to provide the resources necessary to help SickKids to save lives
and maintain daily activities. Patients are the beneficiaries of SickKids
Foundation who are going to get benefit from the fund.
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
CEO of the SickKids Foundation will be the project sponsor to give
approve on our project plans about time, scope and budget etc.
Project team include Amalia, Lenore, Lang and Boyang, they are
responsible to put plan into practice and support Nancy.
Subject experts will be the people we are hiring or inviting for the gala
like special speakers, catering employees, and security. Special speakers will
give speeches in the gala to encourage patrons to contribute more for the
foundation. Catering employees are responsible to satisfied all the needs
related to catering by using their serving knowledge to provide good
services. Security is responsible to doing staff check and ensure the safety of
guests and performers during gala.
Our project manager Nancy will be the executive of the team to ensure
successful completion of the project.
Work Breakdown Structure
Project Plan
8 Months in
Advance
-Form a committee
-Set the date: October 21, 2017
-Look for rooms for out of town guests
-Hire an MC
-Develop a theme and invite speakers (parents or people
from the hospital?)
-Send out invitations to famous singers who could perform
-Hire a photographer/video
-Sponsorships (start thinking of who we would like to write
letters to
-Look for volunteers
6 Months in
Advance
-Confirm the venue (and put down $5000 deposit)
-Save-the-date communication
Document Page
-Send out the invitations for sponsors
-Set print times for the program pamphlet
-Meet with the catering company to try different foods
-Meet with the venue manager and confirm the format,
menu, audio-visual equipment
-Look at flower arrangements
-Start advertisements
1 Month in
Advance
-Finalize the menu and floral arrangements
-50% deposit to venue (catering)
-Start keeping lists of people who have RSVP’d so far
2 Weeks in
Advance
-Give the hotel the estimated count of who will need a room
-Print the program pamphlet (wait until last minute to print
guest cards, there might be last minute RSVP)
1 Week in
Advance
-Check audio-visual aspects of the venue
Program Schedule
12:00PM-4:30PM Set up
5:00PM-6:30PM Cocktail and appetizer hour. Guest start arriving, coat check.
Free champagne, 2 signature cocktails (Caesars and Margaritas)
6:30PM Dinner service starts
6:30-8:30PM Dinner and desserts being served
7:30PM 1st Speech while guests are having dinner
8:00PM 2nd Speech
8:30PM 3rd Speech
9:00PM Famous Artist’s Performance
11:30PM - 2:00AM Close out – cleaning up
Project Plan
The table below shows the project activities, who is doing it, how
long it will take, how much it will cost, and dependencies on other
tasks:
S.
No
Activity Responsible Durati
on
Bud
get
Depende
ncy
1 Define Venue 1
week
TBD 16
2 Design Event
Layout
Project Manager,
Project Team
2
month
s
TBD 17
Document Page
3 Identify Guests Project Manager
Project Team
2
weeks
TBD 17
4 Identify and Train
Host
Project Manager
Project Team
1
month
TBD 17
5 Identify
Performers
Project Manager
Project Team
1
month
TBD 17
6 Arrange Food and
Catering Service
Project Manager
Project Team
2
month
TBD 2
7 Silent Auction
Preparation
Project Manager
Project Team
2
month
TBD 2
8 Arrange
Photographer
Project Manager
Project Team
1
week
TBD 2
9 Implement
Decorations
Subject Experts 1
month
TBD 2
10 Arrange
Volunteers
Project Team 1
week
TBD 1
11 Conduct
Marketing
Project Team 4
month
s
TBD 5
12 Send Invitations Project Team 1
month
TBD 11
13 Arrange Music Subject Experts 1
week
TBD 5
14 Arrange Hotel
Discounts
Subject Experts 2
week
TBD 10
15 Arrange Menus Subject Experts 2
week
TBD 14
16 Identify Event
Scope
Project Manager,
Project Sponsor
1
week
TBD 0
17 Identify Event
Requirements
Project Manager 1
week
TBD 16
Responsibility Matrix
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Project
Sponsor
Project
Manager
Project
Team
Subject
Experts
Define Venue I R
Design Event Layout I R
Identify Guests I A R
Identify and Train
Host
I R
Identify Performers I A R I
Arrange Food and
Catering Service
I A R I
Silent Auction
Preparation
I A R I
Arrange
Photographer
I A R I
Implement
Decorations
I A R
Arrange Volunteers I A R
Conduct Marketing I A R
Send Invitations I A R
Arrange Music I A R
Arrange Hotel
Discounts
I A R
Arrange Menus I A R
Document Page
Identify Event Scope A R
Identify Event
Requirements
A R
R – Responsible
A – Accountable
C – Consulted
I – Informed
Q – Quality Review
Communication Plan
The table below shows the communication plan for the project:
Audience/
Stakeholder
Message Medium Freque
ncy
Responsi
ble
Customers Event
information
Email messa
ge
Monthl
y
Project
Manager
Project Users Resources
required,
update
Face to face
meeting
Weekly Project
Manager
Project
Sponsor
Overall project
progress
update
Email
message
Weekly Project
Manager
Project Team Daily project
progress
update
Face to face
meeting
Daily Project
Manager
Subject Experts Event
information
Email
message
Monthl
y
Project
Manager
Project
Manager
Project
Progress
Face to face
meeting
Daily Project
Manager
Document Page
Project Risk Assessment
Close the Project