BP Solar Car Charging Points Project: A Study in Project Management
VerifiedAdded on 2023/04/05
|19
|1999
|203
Project
AI Summary
This project delves into the strategic initiative of British Petroleum (BP) to establish solar car charging points across five locations in the UK, driven by the increasing global emphasis on renewable energy. The project charter outlines the rationale, purpose, and SMART objectives, emphasizing the promotion of solar-powered car adoption. Key stakeholders include project, construction, mechanical, and electrical engineers. The scope encompasses land acquisition, construction, installation, grid connection, and rigorous testing. A detailed timeline and budget estimation are provided, along with a work breakdown structure (WBS) and critical path analysis (CPA). Resource allocation and activity duration are estimated, culminating in a Gantt chart for project visualization. The project's success hinges on assumptions such as sufficient solar-powered car usage and solar power generation, while constraints include solar energy capture efficiency and investment costs. This comprehensive project plan aims to position BP in the burgeoning renewable energy market.

Running Head: PROJECT AND RISK MANAGEMENT
Project and Risk Management
Name of the Student
Name of the University
Project and Risk Management
Name of the Student
Name of the University
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1PROJECT AND RISK MANAGEMENT
Table of Contents
Section 1: Introduction and Project Charter....................................................................................2
1. Introduction..............................................................................................................................2
2. Project Charter and Scope Statement......................................................................................2
3. Project Work Breakdown Structure.........................................................................................8
4. Schedule, Network Diagram, Critical Path............................................................................11
References......................................................................................................................................17
Table of Contents
Section 1: Introduction and Project Charter....................................................................................2
1. Introduction..............................................................................................................................2
2. Project Charter and Scope Statement......................................................................................2
3. Project Work Breakdown Structure.........................................................................................8
4. Schedule, Network Diagram, Critical Path............................................................................11
References......................................................................................................................................17

2PROJECT AND RISK MANAGEMENT
Section 1: Introduction and Project Charter
1. Introduction
British Petroleum (BP) is a multinational company that deals with the business of
petroleum supply to various retailers and clients and it is also one of the “supergiants” in the
world in this business. However, with recent recommendations from various health organizations
around the world to reduce the use of fossil fuels, BP is now focusing on renewable energy like
solar energy and electricity (Zhao and Burke 2014). The company has now commissioned a new
project in which solar car charging points will be set up at five different locations in UK. As per
the initial decision taken, the five locations will have to in popular locations where most people
are expected to use solar powered cars. Being one of the supergiants in the world in oil industry,
the company does not face much competitive challenge but keeping up with the increasing
demands of oil and maintain and grow the business is a challenge itself (Al-Mashhadany and
Attia 2014). On the other hand, ever since the company has started venturing into other markets
like eco-friendly and renewable energy sources, a great opportunity has opened for the company
to establish its authority over the new market that is currently on the rise in terms of usefulness
and popularity.
2. Project Charter and Scope Statement
The rationale for triggering this project is that with worldwide calls for increasing use of
renewable energy and expected reduction in use of oil and other fossil fuels, the company must
venture into the growing market in order to maintain sustainability of the business (Kim et al.
2014).
Section 1: Introduction and Project Charter
1. Introduction
British Petroleum (BP) is a multinational company that deals with the business of
petroleum supply to various retailers and clients and it is also one of the “supergiants” in the
world in this business. However, with recent recommendations from various health organizations
around the world to reduce the use of fossil fuels, BP is now focusing on renewable energy like
solar energy and electricity (Zhao and Burke 2014). The company has now commissioned a new
project in which solar car charging points will be set up at five different locations in UK. As per
the initial decision taken, the five locations will have to in popular locations where most people
are expected to use solar powered cars. Being one of the supergiants in the world in oil industry,
the company does not face much competitive challenge but keeping up with the increasing
demands of oil and maintain and grow the business is a challenge itself (Al-Mashhadany and
Attia 2014). On the other hand, ever since the company has started venturing into other markets
like eco-friendly and renewable energy sources, a great opportunity has opened for the company
to establish its authority over the new market that is currently on the rise in terms of usefulness
and popularity.
2. Project Charter and Scope Statement
The rationale for triggering this project is that with worldwide calls for increasing use of
renewable energy and expected reduction in use of oil and other fossil fuels, the company must
venture into the growing market in order to maintain sustainability of the business (Kim et al.
2014).
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3PROJECT AND RISK MANAGEMENT
The purpose of the project is to provide charging points for solar powered cars that will
encourage people to purchase more solar powered cars.
Three SMART objectives of the project are as follows.
Specific – The project will deliver five solar power charging points for vehicles at five
different parts of London.
Relevant – The project will promote the purchase of solar powered cars among the
customers.
Time Based – The project aims to deliver the charging stations within 6-7 months time
period.
The key stakeholders in this project include the project manager, construction manager,
mechanical engineer and electrical engineer. The scope of the project that is also within the
boundary of the project includes the following (Heagney 2016).
Renting land from Government for installation works
Construction of charging stations
Installation of charging machines
Connection with the main transmission line
Testing of the machines
The project timeline including the budget estimation is shown in the following table.
Task Name Duration Start Finish Cost
Installation of Solar Car 181 days Mon 5/6/19 Mon 1/13/20 $4,066,400.00
The purpose of the project is to provide charging points for solar powered cars that will
encourage people to purchase more solar powered cars.
Three SMART objectives of the project are as follows.
Specific – The project will deliver five solar power charging points for vehicles at five
different parts of London.
Relevant – The project will promote the purchase of solar powered cars among the
customers.
Time Based – The project aims to deliver the charging stations within 6-7 months time
period.
The key stakeholders in this project include the project manager, construction manager,
mechanical engineer and electrical engineer. The scope of the project that is also within the
boundary of the project includes the following (Heagney 2016).
Renting land from Government for installation works
Construction of charging stations
Installation of charging machines
Connection with the main transmission line
Testing of the machines
The project timeline including the budget estimation is shown in the following table.
Task Name Duration Start Finish Cost
Installation of Solar Car 181 days Mon 5/6/19 Mon 1/13/20 $4,066,400.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4PROJECT AND RISK MANAGEMENT
Charging Points
Project Initial Planning
and Discussion Phase
14 days Mon 5/6/19 Thu 5/23/19 $56,000.00
Marketing Department
Meeting
2 days Mon 5/6/19 Tue 5/7/19 $8,000.00
Discussion Regarding
New Market Venture
2 days Wed 5/8/19 Thu 5/9/19 $8,000.00
Consideration of Solar
Energy Market
2 days Fri 5/10/19 Mon 5/13/19 $8,000.00
Make Final Decision 1 day Tue 5/14/19 Tue 5/14/19 $4,000.00
Prepare Project
Proposal
5 days Wed 5/15/19 Tue 5/21/19 $20,000.00
Submit Proposal to
Higher Management
2 days Wed 5/22/19 Thu 5/23/19 $8,000.00
Receive Approval to
Proceed
0 days Thu 5/23/19 Thu 5/23/19 $0.00
Project Preparation
Phase
28 days Fri 5/24/19 Tue 7/2/19 $164,400.00
Form Project Team 3 days Fri 5/24/19 Tue 5/28/19 $12,000.00
Charging Points
Project Initial Planning
and Discussion Phase
14 days Mon 5/6/19 Thu 5/23/19 $56,000.00
Marketing Department
Meeting
2 days Mon 5/6/19 Tue 5/7/19 $8,000.00
Discussion Regarding
New Market Venture
2 days Wed 5/8/19 Thu 5/9/19 $8,000.00
Consideration of Solar
Energy Market
2 days Fri 5/10/19 Mon 5/13/19 $8,000.00
Make Final Decision 1 day Tue 5/14/19 Tue 5/14/19 $4,000.00
Prepare Project
Proposal
5 days Wed 5/15/19 Tue 5/21/19 $20,000.00
Submit Proposal to
Higher Management
2 days Wed 5/22/19 Thu 5/23/19 $8,000.00
Receive Approval to
Proceed
0 days Thu 5/23/19 Thu 5/23/19 $0.00
Project Preparation
Phase
28 days Fri 5/24/19 Tue 7/2/19 $164,400.00
Form Project Team 3 days Fri 5/24/19 Tue 5/28/19 $12,000.00

5PROJECT AND RISK MANAGEMENT
Survey Various Area of
the City
10 days Wed 5/29/19 Tue 6/11/19 $40,000.00
Identify Specific and
Convenient Points for Solar
Power Charging
4 days Wed 6/12/19 Mon 6/17/19 $16,000.00
Analyze Project
Feasibility
5 days Tue 6/18/19 Mon 6/24/19 $34,000.00
Determine Resources
Required for the Project
4 days Tue 6/25/19 Fri 6/28/19 $54,400.00
Submit Analysis Report 2 days Mon 7/1/19 Tue 7/2/19 $8,000.00
Receive Approval to
Proceed with Project
Planning
0 days Tue 7/2/19 Tue 7/2/19 $0.00
Detailed Planning for
the Project
37 days Wed 7/3/19 Thu 8/22/19 $192,800.00
Preparation of Project
Charter
5 days Wed 7/3/19 Tue 7/9/19 $20,000.00
Preparation of Project 2 days Wed 7/10/19 Thu 7/11/19 $8,000.00
Survey Various Area of
the City
10 days Wed 5/29/19 Tue 6/11/19 $40,000.00
Identify Specific and
Convenient Points for Solar
Power Charging
4 days Wed 6/12/19 Mon 6/17/19 $16,000.00
Analyze Project
Feasibility
5 days Tue 6/18/19 Mon 6/24/19 $34,000.00
Determine Resources
Required for the Project
4 days Tue 6/25/19 Fri 6/28/19 $54,400.00
Submit Analysis Report 2 days Mon 7/1/19 Tue 7/2/19 $8,000.00
Receive Approval to
Proceed with Project
Planning
0 days Tue 7/2/19 Tue 7/2/19 $0.00
Detailed Planning for
the Project
37 days Wed 7/3/19 Thu 8/22/19 $192,800.00
Preparation of Project
Charter
5 days Wed 7/3/19 Tue 7/9/19 $20,000.00
Preparation of Project 2 days Wed 7/10/19 Thu 7/11/19 $8,000.00
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6PROJECT AND RISK MANAGEMENT
Schedule
Estimation of Final
Budget
5 days Fri 7/12/19 Thu 7/18/19 $20,000.00
Risk Analysis 5 days Fri 7/19/19 Thu 7/25/19 $48,000.00
Development of Risk
Mitigation Plan
3 days Fri 7/26/19 Tue 7/30/19 $28,800.00
Contact Government for
License
2 days Wed 7/31/19 Thu 8/1/19 $8,000.00
Receive Approval and
Land Rent from
Government
15 days Fri 8/2/19 Thu 8/22/19 $60,000.00
Completion of Planning 0 days Thu 8/22/19 Thu 8/22/19 $0.00
Charging Point
Installation Works
85 days Fri 8/23/19 Thu 12/19/19 $3,048,000.00
Purchasing Materials 10 days Fri 8/23/19 Thu 9/5/19 $2,040,000.00
Building of Charging
Station
30 days Fri 9/6/19 Thu 10/17/19 $384,000.00
Schedule
Estimation of Final
Budget
5 days Fri 7/12/19 Thu 7/18/19 $20,000.00
Risk Analysis 5 days Fri 7/19/19 Thu 7/25/19 $48,000.00
Development of Risk
Mitigation Plan
3 days Fri 7/26/19 Tue 7/30/19 $28,800.00
Contact Government for
License
2 days Wed 7/31/19 Thu 8/1/19 $8,000.00
Receive Approval and
Land Rent from
Government
15 days Fri 8/2/19 Thu 8/22/19 $60,000.00
Completion of Planning 0 days Thu 8/22/19 Thu 8/22/19 $0.00
Charging Point
Installation Works
85 days Fri 8/23/19 Thu 12/19/19 $3,048,000.00
Purchasing Materials 10 days Fri 8/23/19 Thu 9/5/19 $2,040,000.00
Building of Charging
Station
30 days Fri 9/6/19 Thu 10/17/19 $384,000.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7PROJECT AND RISK MANAGEMENT
Installation of Electrical
Machines and Equipments
20 days Fri 10/18/19 Thu 11/14/19 $336,000.00
Connection with Main
Line
10 days Fri 11/15/19 Thu 11/28/19 $136,000.00
Installation of Insulators 5 days Fri 11/29/19 Thu 12/5/19 $84,000.00
Detailed Testing 10 days Fri 12/6/19 Thu 12/19/19 $68,000.00
Completion of
Installation
0 days Thu 12/19/19 Thu 12/19/19 $0.00
Commissioning, Sign
Off and Closing
17 days Fri 12/20/19 Mon 1/13/20 $605,200.00
Review the Charging
Stations
10 days Fri 12/20/19 Thu 1/2/20 $540,000.00
Commissioning of the
Charging Stations
5 days Fri 1/3/20 Thu 1/9/20 $38,000.00
Stakeholder Sign Off 2 days Fri 1/10/20 Mon 1/13/20 $27,200.00
Closing 0 days Mon 1/13/20 Mon 1/13/20 $0.00
The project assumptions include the following.
There is sufficient number of solar powered cars in the city.
There is sufficient amount of solar power generated for charging the cars.
Installation of Electrical
Machines and Equipments
20 days Fri 10/18/19 Thu 11/14/19 $336,000.00
Connection with Main
Line
10 days Fri 11/15/19 Thu 11/28/19 $136,000.00
Installation of Insulators 5 days Fri 11/29/19 Thu 12/5/19 $84,000.00
Detailed Testing 10 days Fri 12/6/19 Thu 12/19/19 $68,000.00
Completion of
Installation
0 days Thu 12/19/19 Thu 12/19/19 $0.00
Commissioning, Sign
Off and Closing
17 days Fri 12/20/19 Mon 1/13/20 $605,200.00
Review the Charging
Stations
10 days Fri 12/20/19 Thu 1/2/20 $540,000.00
Commissioning of the
Charging Stations
5 days Fri 1/3/20 Thu 1/9/20 $38,000.00
Stakeholder Sign Off 2 days Fri 1/10/20 Mon 1/13/20 $27,200.00
Closing 0 days Mon 1/13/20 Mon 1/13/20 $0.00
The project assumptions include the following.
There is sufficient number of solar powered cars in the city.
There is sufficient amount of solar power generated for charging the cars.

8PROJECT AND RISK MANAGEMENT
The charging points will encourage the customers to purchase more solar powered
cars.
The constraints of the project are as follows.
Solar power generation is a constraint as there is no high efficiency solar energy
capturing device yet developed.
Installation of five charging stations will require huge amount of investment.
3. Project Work Breakdown Structure
The work breakdown structure of the project is shown in the following table (Kerzner and
Kerzner 2017).
WBS Task Name
0 Installation of Solar Car Charging Points
1 Project Initial Planning and Discussion Phase
1.1 Marketing Department Meeting
1.2 Discussion Regarding New Market Venture
1.3 Consideration of Solar Energy Market
1.4 Make Final Decision
1.5 Prepare Project Proposal
1.6 Submit Proposal to Higher Management
The charging points will encourage the customers to purchase more solar powered
cars.
The constraints of the project are as follows.
Solar power generation is a constraint as there is no high efficiency solar energy
capturing device yet developed.
Installation of five charging stations will require huge amount of investment.
3. Project Work Breakdown Structure
The work breakdown structure of the project is shown in the following table (Kerzner and
Kerzner 2017).
WBS Task Name
0 Installation of Solar Car Charging Points
1 Project Initial Planning and Discussion Phase
1.1 Marketing Department Meeting
1.2 Discussion Regarding New Market Venture
1.3 Consideration of Solar Energy Market
1.4 Make Final Decision
1.5 Prepare Project Proposal
1.6 Submit Proposal to Higher Management
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

9PROJECT AND RISK MANAGEMENT
1.7 Receive Approval to Proceed
2 Project Preparation Phase
2.1 Form Project Team
2.2 Survey Various Area of the City
2.3 Identify Specific and Convenient Points for Solar Power Charging
2.4 Analyze Project Feasibility
2.5 Determine Resources Required for the Project
2.6 Submit Analysis Report
2.7 Receive Approval to Proceed with Project Planning
3 Detailed Planning for the Project
3.1 Preparation of Project Charter
3.2 Preparation of Project Schedule
3.3 Estimation of Final Budget
3.4 Risk Analysis
3.5 Development of Risk Mitigation Plan
3.6 Contact Government for License
1.7 Receive Approval to Proceed
2 Project Preparation Phase
2.1 Form Project Team
2.2 Survey Various Area of the City
2.3 Identify Specific and Convenient Points for Solar Power Charging
2.4 Analyze Project Feasibility
2.5 Determine Resources Required for the Project
2.6 Submit Analysis Report
2.7 Receive Approval to Proceed with Project Planning
3 Detailed Planning for the Project
3.1 Preparation of Project Charter
3.2 Preparation of Project Schedule
3.3 Estimation of Final Budget
3.4 Risk Analysis
3.5 Development of Risk Mitigation Plan
3.6 Contact Government for License
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

10PROJECT AND RISK MANAGEMENT
3.7 Receive Approval and Land Rent from Government
3.8 Completion of Planning
4 Charging Point Installation Works
4.1 Purchasing Materials
4.2 Building of Charging Station
4.3 Installation of Electrical Machines and Equipments
4.4 Connection with Main Line
4.5 Installation of Insulators
4.6 Detailed Testing
4.7 Completion of Installation
5 Commissioning, Sign Off and Closing
5.1 Review the Charging Stations
5.2 Commissioning of the Charging Stations
5.3 Stakeholder Sign Off
5.4 Closing
3.7 Receive Approval and Land Rent from Government
3.8 Completion of Planning
4 Charging Point Installation Works
4.1 Purchasing Materials
4.2 Building of Charging Station
4.3 Installation of Electrical Machines and Equipments
4.4 Connection with Main Line
4.5 Installation of Insulators
4.6 Detailed Testing
4.7 Completion of Installation
5 Commissioning, Sign Off and Closing
5.1 Review the Charging Stations
5.2 Commissioning of the Charging Stations
5.3 Stakeholder Sign Off
5.4 Closing

11PROJECT AND RISK MANAGEMENT
4. Schedule, Network Diagram, Critical Path
The main activities that define the execution work package for the project is shown in the
following table.
WBS Task Name
0 Installation of Solar Car Charging Points
1 Charging Point Installation Works
1.1 Purchasing Materials
1.2 Building of Charging Station
1.3 Installation of Electrical Machines and Equipments
1.4 Connection with Main Line
1.5 Installation of Insulators
1.6 Detailed Testing
1.7 Completion of Installation
The project is sequenced using CPA methodology as shown in the following diagram.
4. Schedule, Network Diagram, Critical Path
The main activities that define the execution work package for the project is shown in the
following table.
WBS Task Name
0 Installation of Solar Car Charging Points
1 Charging Point Installation Works
1.1 Purchasing Materials
1.2 Building of Charging Station
1.3 Installation of Electrical Machines and Equipments
1.4 Connection with Main Line
1.5 Installation of Insulators
1.6 Detailed Testing
1.7 Completion of Installation
The project is sequenced using CPA methodology as shown in the following diagram.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 19
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.