COIT11226 ASSESSMENT 1
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Contents
Introduction......................................................................................................................................3
Task 1. System Development Methodology....................................................................................4
Modified Waterfall Model...........................................................................................................4
Extreme Programming.................................................................................................................4
Task 2. Project Gantt Chart.............................................................................................................6
Task 3. Economic Cost Feasibility/ Project Budgeting.................................................................17
2.b:.............................................................................................................................................17
2.c:.............................................................................................................................................18
3.a:.............................................................................................................................................18
3.b:.............................................................................................................................................19
3.c:.............................................................................................................................................19
Conclusion.....................................................................................................................................20
References......................................................................................................................................21
Introduction......................................................................................................................................3
Task 1. System Development Methodology....................................................................................4
Modified Waterfall Model...........................................................................................................4
Extreme Programming.................................................................................................................4
Task 2. Project Gantt Chart.............................................................................................................6
Task 3. Economic Cost Feasibility/ Project Budgeting.................................................................17
2.b:.............................................................................................................................................17
2.c:.............................................................................................................................................18
3.a:.............................................................................................................................................18
3.b:.............................................................................................................................................19
3.c:.............................................................................................................................................19
Conclusion.....................................................................................................................................20
References......................................................................................................................................21

Introduction
Here, in this report, project management has been defined using a case study to develop a new
“Online SolarPower System” for the Bob Sparks including different phases of the project as well
as resources involved in the project. It also explains complete detail of the project and how the
workflow for the complete project starting from planning to the submission of the final project
after completion.
The main aim of the report to enhance the knowledge and skills of an individual for the effective
management of any project and their functions along with complete analysis of different reports
and risks related with the project which can be minimized before starting of the real work on the
project.
Here, in this report, project management has been defined using a case study to develop a new
“Online SolarPower System” for the Bob Sparks including different phases of the project as well
as resources involved in the project. It also explains complete detail of the project and how the
workflow for the complete project starting from planning to the submission of the final project
after completion.
The main aim of the report to enhance the knowledge and skills of an individual for the effective
management of any project and their functions along with complete analysis of different reports
and risks related with the project which can be minimized before starting of the real work on the
project.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Task 1. System Development Methodology
Modified Waterfall Model
It is a modified version of the Waterfall model. In this version, different phases can be
overlapped when required and some phases are divided into small sub-phases containing sub-
elements of any phase for the task and also have better flexibility in comparison with pure
waterfall model (Rayo 2015).
Figure 1: Modified Waterfall Model
(Source: Thorogood 2013)
Extreme Programming
It is a type of development model which consist of step by step developments of the basis of
functions and the improvement in different phases of the task. It helps to emphasis the complete
and final report produced for the task (Powell-Morse 2017).
Modified Waterfall Model
It is a modified version of the Waterfall model. In this version, different phases can be
overlapped when required and some phases are divided into small sub-phases containing sub-
elements of any phase for the task and also have better flexibility in comparison with pure
waterfall model (Rayo 2015).
Figure 1: Modified Waterfall Model
(Source: Thorogood 2013)
Extreme Programming
It is a type of development model which consist of step by step developments of the basis of
functions and the improvement in different phases of the task. It helps to emphasis the complete
and final report produced for the task (Powell-Morse 2017).
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Figure 2: Extreme Programming
(Source: Gordon 2017)
Table 1: Comparison table between Modified Waterfall Model and Extreme Programming
Modified Waterfall Model Extreme Programming
A modified version of pure Waterfall model Development model for improvement
Phases can overlap depending upon
requirement
Emphasize complete report developed for the
project
High flexibility Assurance for quality done on the basis of test
Reduced documentation Best suited for small projects
Difficult to create milestones Complex method for large projects
High chances for miscommunication due to
the parallel performance of different activities
High costing for programming
Mistakes in assumptions Difficult and complex to create a test case
(Ji and Sedano, 2011)
(Source: Gordon 2017)
Table 1: Comparison table between Modified Waterfall Model and Extreme Programming
Modified Waterfall Model Extreme Programming
A modified version of pure Waterfall model Development model for improvement
Phases can overlap depending upon
requirement
Emphasize complete report developed for the
project
High flexibility Assurance for quality done on the basis of test
Reduced documentation Best suited for small projects
Difficult to create milestones Complex method for large projects
High chances for miscommunication due to
the parallel performance of different activities
High costing for programming
Mistakes in assumptions Difficult and complex to create a test case
(Ji and Sedano, 2011)

Task 2. Project Gantt Chart
The Gantt Chart for the new business named “Online SolarPower System” for the Bob-Sparks
has been shown below which consist of different phases starting with the planning of the new
project and ends with the submission of the final project after successful development,
implementation, documentation, and testing of the new web-based online business system. All
the members of the project such as Project manager, CEO, Accounts Manager, Analyst,
Programmer, Testing agent, and others have been defined along with their role in specific phases
of the project. Different reports and tables have been generated for a better understanding of
different phases of the project.
Planning: It consists of complete research and evaluation of all the solar power plants and
business which are running currently in the market in order to plan a new and effective online
business system for the Bob-Sparks to stand unique and different from other competitors
available in the market.
Meeting & discussion: It consists of meeting with other members of the project and business in
order to discuss all the details and planning of the new project to share the new ideas and
techniques which will be used in the new online system for the business of Solar Power. It also
includes feedback collection from other team members, their improvement in planning and
approval from other team members.
Design & development: It consists of complete design and development stage of the new online
business platform for the Solar Power to be used by Bob-Sparks. It will help both customers as
well as organization to manage all the orders, quotes, requests, approval and payment for the
customer.
Testing of the new online business system: It consists of testing of the new online business
platform designed and implemented to be used for Solar Power by the Bob-Sparks. It also
includes the recording of different results and feedback for the working and performance of the
newly designed system which is done by the testing agent.
Improvement and final implementation: It consists of improvement which needs to be done
on the implementation and design of new online business system to enhance the functions and
The Gantt Chart for the new business named “Online SolarPower System” for the Bob-Sparks
has been shown below which consist of different phases starting with the planning of the new
project and ends with the submission of the final project after successful development,
implementation, documentation, and testing of the new web-based online business system. All
the members of the project such as Project manager, CEO, Accounts Manager, Analyst,
Programmer, Testing agent, and others have been defined along with their role in specific phases
of the project. Different reports and tables have been generated for a better understanding of
different phases of the project.
Planning: It consists of complete research and evaluation of all the solar power plants and
business which are running currently in the market in order to plan a new and effective online
business system for the Bob-Sparks to stand unique and different from other competitors
available in the market.
Meeting & discussion: It consists of meeting with other members of the project and business in
order to discuss all the details and planning of the new project to share the new ideas and
techniques which will be used in the new online system for the business of Solar Power. It also
includes feedback collection from other team members, their improvement in planning and
approval from other team members.
Design & development: It consists of complete design and development stage of the new online
business platform for the Solar Power to be used by Bob-Sparks. It will help both customers as
well as organization to manage all the orders, quotes, requests, approval and payment for the
customer.
Testing of the new online business system: It consists of testing of the new online business
platform designed and implemented to be used for Solar Power by the Bob-Sparks. It also
includes the recording of different results and feedback for the working and performance of the
newly designed system which is done by the testing agent.
Improvement and final implementation: It consists of improvement which needs to be done
on the implementation and design of new online business system to enhance the functions and
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

performance of the complete system to become more effective both for the organization as well
as the customers.
Report and documentation: It consists of generation or reports of a new online business system
which has been designed and implemented for the “Online SolarPower System” and result have
been documented for the approval from the team members as well as the legal purposes.
Submission: It is the final and last stage of the project in which final submission of the newly
developed project for the online business system has been done to be used by the organization as
well as the customers.
Table 2: Phases of project
Task
Mode Task Name Durati
on Start Finish Predecess
ors Resource Names Cost
Auto
Schedule
d
Online
SolarPower
System
35
days
Mon
3/11/1
9
Fri
4/26/1
9
$23,040.
00
Auto
Schedule
d
Planning 5 days
Mon
3/11/1
9
Fri
3/15/1
9
$2,480.00
Auto
Schedule
d
Research
on Solar
Power
business
1 day
Mon
3/11/1
9
Mon
3/11/1
9
Analyst,Project Manager $640.00
Auto
Schedule
d
Collecting
new ideas 1 day
Tue
3/12/1
9
Tue
3/12/1
9
2 Analyst,Project Manager $640.00
Auto
Schedule
d
Document
ation of ideas
and planing
2 days
Wed
3/13/1
9
Thu
3/14/1
9
3 Project Manager $800.00
as the customers.
Report and documentation: It consists of generation or reports of a new online business system
which has been designed and implemented for the “Online SolarPower System” and result have
been documented for the approval from the team members as well as the legal purposes.
Submission: It is the final and last stage of the project in which final submission of the newly
developed project for the online business system has been done to be used by the organization as
well as the customers.
Table 2: Phases of project
Task
Mode Task Name Durati
on Start Finish Predecess
ors Resource Names Cost
Auto
Schedule
d
Online
SolarPower
System
35
days
Mon
3/11/1
9
Fri
4/26/1
9
$23,040.
00
Auto
Schedule
d
Planning 5 days
Mon
3/11/1
9
Fri
3/15/1
9
$2,480.00
Auto
Schedule
d
Research
on Solar
Power
business
1 day
Mon
3/11/1
9
Mon
3/11/1
9
Analyst,Project Manager $640.00
Auto
Schedule
d
Collecting
new ideas 1 day
Tue
3/12/1
9
Tue
3/12/1
9
2 Analyst,Project Manager $640.00
Auto
Schedule
d
Document
ation of ideas
and planing
2 days
Wed
3/13/1
9
Thu
3/14/1
9
3 Project Manager $800.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Auto
Schedule
d
Finalizatio
n of planing 1 day
Fri
3/15/1
9
Fri
3/15/1
9
4 Project Manager $400.00
Auto
Schedule
d
Milestone:
Completion of
planning
0 days
Fri
3/15/1
9
Fri
3/15/1
9
5 $0.00
Auto
Schedule
d
Meeting &
discussion 7 days
Mon
3/18/1
9
Tue
3/26/1
9
$8,800.00
Auto
Schedule
d
Meeting
with business
members
1 day
Mon
3/18/1
9
Mon
3/18/1
9
6
Accounts
manager,Administratior,CEO,Fin
ance manager,Installation
manager,Project Manager
$1,960.00
Auto
Schedule
d
Discussion
of plan 2 days
Tue
3/19/1
9
Wed
3/20/1
9
8
Accounts manager,CEO,Finance
manager,Installation
manager,Project Manager
$3,440.00
Auto
Schedule
d
Feedback
collection 1 day
Thu
3/21/1
9
Thu
3/21/1
9
9 Project Manager $400.00
Auto
Schedule
d
Improvem
ent 2 days
Fri
3/22/1
9
Mon
3/25/1
9
10 Analyst,Project Manager $1,280.00
Auto
Schedule
d
Approval
of plan 1 day
Tue
3/26/1
9
Tue
3/26/1
9
11
Accounts manager,CEO,Finance
manager,Installation
manager,Project Manager
$1,720.00
Auto
Schedule
d
Milestone:
Completion of
meeting &
discussion
0 days
Tue
3/26/1
9
Tue
3/26/1
9
12 $0.00
Auto
Schedule
Design &
development
9 days Wed
3/27/1
Mon
4/8/19
$4,560.00
Schedule
d
Finalizatio
n of planing 1 day
Fri
3/15/1
9
Fri
3/15/1
9
4 Project Manager $400.00
Auto
Schedule
d
Milestone:
Completion of
planning
0 days
Fri
3/15/1
9
Fri
3/15/1
9
5 $0.00
Auto
Schedule
d
Meeting &
discussion 7 days
Mon
3/18/1
9
Tue
3/26/1
9
$8,800.00
Auto
Schedule
d
Meeting
with business
members
1 day
Mon
3/18/1
9
Mon
3/18/1
9
6
Accounts
manager,Administratior,CEO,Fin
ance manager,Installation
manager,Project Manager
$1,960.00
Auto
Schedule
d
Discussion
of plan 2 days
Tue
3/19/1
9
Wed
3/20/1
9
8
Accounts manager,CEO,Finance
manager,Installation
manager,Project Manager
$3,440.00
Auto
Schedule
d
Feedback
collection 1 day
Thu
3/21/1
9
Thu
3/21/1
9
9 Project Manager $400.00
Auto
Schedule
d
Improvem
ent 2 days
Fri
3/22/1
9
Mon
3/25/1
9
10 Analyst,Project Manager $1,280.00
Auto
Schedule
d
Approval
of plan 1 day
Tue
3/26/1
9
Tue
3/26/1
9
11
Accounts manager,CEO,Finance
manager,Installation
manager,Project Manager
$1,720.00
Auto
Schedule
d
Milestone:
Completion of
meeting &
discussion
0 days
Tue
3/26/1
9
Tue
3/26/1
9
12 $0.00
Auto
Schedule
Design &
development
9 days Wed
3/27/1
Mon
4/8/19
$4,560.00

d 9
Auto
Schedule
d
Designing
of new online
business
system
4 days
Wed
3/27/1
9
Mon
4/1/19 13
Installation
staffs,Programmer,Project
Manager
$3,360.00
Auto
Schedule
d
Developm
ent of new
system
3 days Tue
4/2/19
Thu
4/4/19 15 Programmer $720.00
Auto
Schedule
d
Implement
ation of new
system
2 days Fri
4/5/19
Mon
4/8/19 16 Programmer $480.00
Auto
Schedule
d
Milestone: 0 days Mon
4/8/19
Mon
4/8/19 17 $0.00
Auto
Schedule
d
Testing of
new online
business
system
4 days Tue
4/9/19
Fri
4/12/1
9
$2,000.00
Auto
Schedule
d
Testing 2 days Tue
4/9/19
Wed
4/10/1
9
18 Programmer,Quality agent $1,120.00
Auto
Schedule
d
Recording
results 1 day
Thu
4/11/1
9
Thu
4/11/1
9
20 Analyst,Quality agent $560.00
Auto
Schedule
d
Feedback
recorded 1 day
Fri
4/12/1
9
Fri
4/12/1
9
21 Quality agent $320.00
Auto
Schedule
d
Milestone: 0 days
Fri
4/12/1
9
Fri
4/12/1
9
22 $0.00
Auto
Schedule
d
Designing
of new online
business
system
4 days
Wed
3/27/1
9
Mon
4/1/19 13
Installation
staffs,Programmer,Project
Manager
$3,360.00
Auto
Schedule
d
Developm
ent of new
system
3 days Tue
4/2/19
Thu
4/4/19 15 Programmer $720.00
Auto
Schedule
d
Implement
ation of new
system
2 days Fri
4/5/19
Mon
4/8/19 16 Programmer $480.00
Auto
Schedule
d
Milestone: 0 days Mon
4/8/19
Mon
4/8/19 17 $0.00
Auto
Schedule
d
Testing of
new online
business
system
4 days Tue
4/9/19
Fri
4/12/1
9
$2,000.00
Auto
Schedule
d
Testing 2 days Tue
4/9/19
Wed
4/10/1
9
18 Programmer,Quality agent $1,120.00
Auto
Schedule
d
Recording
results 1 day
Thu
4/11/1
9
Thu
4/11/1
9
20 Analyst,Quality agent $560.00
Auto
Schedule
d
Feedback
recorded 1 day
Fri
4/12/1
9
Fri
4/12/1
9
21 Quality agent $320.00
Auto
Schedule
d
Milestone: 0 days
Fri
4/12/1
9
Fri
4/12/1
9
22 $0.00
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Auto
Schedule
d
Improveme
nt and final
implementati
on
4 days
Mon
4/15/1
9
Thu
4/18/1
9
$960.00
Auto
Schedule
d
Correction
of feedback 2 days
Mon
4/15/1
9
Tue
4/16/1
9
22 Programmer $480.00
Auto
Schedule
d
Final
implementati
on
2 days
Wed
4/17/1
9
Thu
4/18/1
9
25 Programmer $480.00
Auto
Schedule
d
Milestone: 0 days
Thu
4/18/1
9
Thu
4/18/1
9
26 $0.00
Auto
Schedule
d
Report and
documentatio
n
5 days
Fri
4/19/1
9
Thu
4/25/1
9
$3,080.00
Auto
Schedule
d
Generation
of report 2 days
Fri
4/19/1
9
Mon
4/22/1
9
27 Analyst $480.00
Auto
Schedule
d
Document
ation of
reports
2 days
Tue
4/23/1
9
Wed
4/24/1
9
29 Administratior,Analyst $960.00
Auto
Schedule
d
Approval
of documents 1 day
Thu
4/25/1
9
Thu
4/25/1
9
30 Administratior,Analyst,CEO,Fina
nce manager,Project Manager $1,640.00
Auto
Schedule
d
Milestone: 0 days
Thu
4/25/1
9
Thu
4/25/1
9
31 $0.00
Auto
Schedule
d
Submission 1 day
Fri
4/26/1
9
Fri
4/26/1
9
$1,160.00
Schedule
d
Improveme
nt and final
implementati
on
4 days
Mon
4/15/1
9
Thu
4/18/1
9
$960.00
Auto
Schedule
d
Correction
of feedback 2 days
Mon
4/15/1
9
Tue
4/16/1
9
22 Programmer $480.00
Auto
Schedule
d
Final
implementati
on
2 days
Wed
4/17/1
9
Thu
4/18/1
9
25 Programmer $480.00
Auto
Schedule
d
Milestone: 0 days
Thu
4/18/1
9
Thu
4/18/1
9
26 $0.00
Auto
Schedule
d
Report and
documentatio
n
5 days
Fri
4/19/1
9
Thu
4/25/1
9
$3,080.00
Auto
Schedule
d
Generation
of report 2 days
Fri
4/19/1
9
Mon
4/22/1
9
27 Analyst $480.00
Auto
Schedule
d
Document
ation of
reports
2 days
Tue
4/23/1
9
Wed
4/24/1
9
29 Administratior,Analyst $960.00
Auto
Schedule
d
Approval
of documents 1 day
Thu
4/25/1
9
Thu
4/25/1
9
30 Administratior,Analyst,CEO,Fina
nce manager,Project Manager $1,640.00
Auto
Schedule
d
Milestone: 0 days
Thu
4/25/1
9
Thu
4/25/1
9
31 $0.00
Auto
Schedule
d
Submission 1 day
Fri
4/26/1
9
Fri
4/26/1
9
$1,160.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Auto
Schedule
d
Submissio
n of project 1 day
Fri
4/26/1
9
Fri
4/26/1
9
32 CEO,Finance manager,Project
Manager $1,160.00
Auto
Schedule
d
Milestone: 0 days
Fri
4/26/1
9
Fri
4/26/1
9
34 $0.00
Schedule
d
Submissio
n of project 1 day
Fri
4/26/1
9
Fri
4/26/1
9
32 CEO,Finance manager,Project
Manager $1,160.00
Auto
Schedule
d
Milestone: 0 days
Fri
4/26/1
9
Fri
4/26/1
9
34 $0.00

ID Task
Mode
Task Name Duration Start Finish PredecessorsResource
Names
Cost
0 Online
SolarPower
System
35
days
Mon
3/11/19
Fri
4/26/19
$23,040.00
1 Planning 5 days Mon
3/11/19
Fri
3/15/19
$2,480.00
2 Research on
Solar Power
business
1 day Mon
3/11/19
Mon
3/11/19
Analyst,Project
Manager
$640.00
3 Collecting
new ideas
1 day Tue
3/12/19
Tue
3/12/19
2 Analyst,Project
Manager
$640.00
4 Documentation
of ideas and
planing
2 days Wed
3/13/19
Thu
3/14/19
3 Project
Manager
$800.00
5 Finalization
of planing
1 day Fri
3/15/19
Fri
3/15/19
4 Project
Manager
$400.00
6 Milestone:
Completion
of planning
0 days Fri
3/15/19
Fri
3/15/19
5 $0.00
7 Meeting &
discussion
7 days Mon
3/18/19
Tue
3/26/19
$8,800.00
8 Meeting with
business
members
1 day Mon
3/18/19
Mon
3/18/19
6 Accounts
manager,Administratior,CEO,Finance
manager,Installation
manager,Project
$1,960.00
9 Discussion of
plan
2 days Tue
3/19/19
Wed
3/20/19
8 Accounts
manager,CEO,Finance
manager,Installation
$3,440.00
10 Feedback
collection
1 day Thu
3/21/19
Thu
3/21/19
9 Project
Manager
$400.00
11 Improvement 2 days Fri 3/22/19Mon 3/25/1910 Analyst,Project Manager$1,280.00
12 Approval of plan1 day Tue 3/26/19Tue 3/26/1911 Accounts manager,CEO,Finance manager,Installation manager,Project Manager$1,720.00
13 Milestone:
Completion
of meeting &
discussion
0 days Tue
3/26/19
Tue
3/26/19
12 $0.00
14 Design &
development
9 days Wed
3/27/19
Mon
4/8/19
$4,560.00
15 Designing of
new online
business
system
4 days Wed
3/27/19
Mon
4/1/19
13 Installation
staffs,Programmer,Project
Manager
$3,360.00
16 Development
of new
system
3 days Tue
4/2/19
Thu
4/4/19
15 Programmer $720.00
17 Implementation
of new
system
2 days Fri
4/5/19
Mon
4/8/19
16 Programmer $480.00
18 Milestone: 0 days Mon 4/8/19Mon 4/8/1917 $0.00
19 Testing of new
online business
system
4 days Tue
4/9/19
Fri
4/12/19
$2,000.00
20 Testing 2 days Tue
4/9/19
Wed
4/10/19
18 Programmer,Quality
agent
$1,120.00
21 Recording
results
1 day Thu
4/11/19
Thu
4/11/19
20 Analyst,Quality
agent
$560.00
22 Feedback
recorded
1 day Fri
4/12/19
Fri
4/12/19
21 Quality
agent
$320.00
23 Milestone: 0 days Fri
4/12/19
Fri
4/12/19
22 $0.00
24 Improvement
and final
implementation
4 days Mon
4/15/19
Thu
4/18/19
$960.00
25 Correction of
feedback
2 days Mon
4/15/19
Tue
4/16/19
22 Programmer $480.00
26 Final
implementation
2 days Wed
4/17/19
Thu
4/18/19
25 Programmer $480.00
27 Milestone: 0 days Thu
4/18/19
Thu
4/18/19
26 $0.00
28 Report and
documentation
5 days Fri
4/19/19
Thu
4/25/19
$3,080.00
29 Generation of
report
2 days Fri
4/19/19
Mon
4/22/19
27 Analyst $480.00
30 Documentation
of reports
2 days Tue
4/23/19
Wed
4/24/19
29 Administratior,Analyst$960.00
31 Approval of
documents
1 day Thu
4/25/19
Thu
4/25/19
30 Administratior,Analyst,CEO,Finance
manager,Project
Manager
$1,640.00
Analyst,Project Manager
Analyst,Project Manager
Project Manager
Project Manager
3/ 15
Accounts manager,Administratior,CEO,Finance manager,Installation manage
Accounts manager,CEO,Finance manager,Installation manager,Project Ma
Project Manager
Analyst,Project Manager
Accounts manager,CEO,Finance manager,Installation manager,Pro
3/ 26
Installation staffs,Programmer,Project Manager
Programmer
Programmer
4/ 8
Programmer,Quality agent
Analyst,Quality agent
Quality agent
4/ 12
Programmer
Programmer
4/ 18
Analyst
Administratior,Analyst
Administratior,Analyst,CEO,F
10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30
March 2019 April 2019
Mode
Task Name Duration Start Finish PredecessorsResource
Names
Cost
0 Online
SolarPower
System
35
days
Mon
3/11/19
Fri
4/26/19
$23,040.00
1 Planning 5 days Mon
3/11/19
Fri
3/15/19
$2,480.00
2 Research on
Solar Power
business
1 day Mon
3/11/19
Mon
3/11/19
Analyst,Project
Manager
$640.00
3 Collecting
new ideas
1 day Tue
3/12/19
Tue
3/12/19
2 Analyst,Project
Manager
$640.00
4 Documentation
of ideas and
planing
2 days Wed
3/13/19
Thu
3/14/19
3 Project
Manager
$800.00
5 Finalization
of planing
1 day Fri
3/15/19
Fri
3/15/19
4 Project
Manager
$400.00
6 Milestone:
Completion
of planning
0 days Fri
3/15/19
Fri
3/15/19
5 $0.00
7 Meeting &
discussion
7 days Mon
3/18/19
Tue
3/26/19
$8,800.00
8 Meeting with
business
members
1 day Mon
3/18/19
Mon
3/18/19
6 Accounts
manager,Administratior,CEO,Finance
manager,Installation
manager,Project
$1,960.00
9 Discussion of
plan
2 days Tue
3/19/19
Wed
3/20/19
8 Accounts
manager,CEO,Finance
manager,Installation
$3,440.00
10 Feedback
collection
1 day Thu
3/21/19
Thu
3/21/19
9 Project
Manager
$400.00
11 Improvement 2 days Fri 3/22/19Mon 3/25/1910 Analyst,Project Manager$1,280.00
12 Approval of plan1 day Tue 3/26/19Tue 3/26/1911 Accounts manager,CEO,Finance manager,Installation manager,Project Manager$1,720.00
13 Milestone:
Completion
of meeting &
discussion
0 days Tue
3/26/19
Tue
3/26/19
12 $0.00
14 Design &
development
9 days Wed
3/27/19
Mon
4/8/19
$4,560.00
15 Designing of
new online
business
system
4 days Wed
3/27/19
Mon
4/1/19
13 Installation
staffs,Programmer,Project
Manager
$3,360.00
16 Development
of new
system
3 days Tue
4/2/19
Thu
4/4/19
15 Programmer $720.00
17 Implementation
of new
system
2 days Fri
4/5/19
Mon
4/8/19
16 Programmer $480.00
18 Milestone: 0 days Mon 4/8/19Mon 4/8/1917 $0.00
19 Testing of new
online business
system
4 days Tue
4/9/19
Fri
4/12/19
$2,000.00
20 Testing 2 days Tue
4/9/19
Wed
4/10/19
18 Programmer,Quality
agent
$1,120.00
21 Recording
results
1 day Thu
4/11/19
Thu
4/11/19
20 Analyst,Quality
agent
$560.00
22 Feedback
recorded
1 day Fri
4/12/19
Fri
4/12/19
21 Quality
agent
$320.00
23 Milestone: 0 days Fri
4/12/19
Fri
4/12/19
22 $0.00
24 Improvement
and final
implementation
4 days Mon
4/15/19
Thu
4/18/19
$960.00
25 Correction of
feedback
2 days Mon
4/15/19
Tue
4/16/19
22 Programmer $480.00
26 Final
implementation
2 days Wed
4/17/19
Thu
4/18/19
25 Programmer $480.00
27 Milestone: 0 days Thu
4/18/19
Thu
4/18/19
26 $0.00
28 Report and
documentation
5 days Fri
4/19/19
Thu
4/25/19
$3,080.00
29 Generation of
report
2 days Fri
4/19/19
Mon
4/22/19
27 Analyst $480.00
30 Documentation
of reports
2 days Tue
4/23/19
Wed
4/24/19
29 Administratior,Analyst$960.00
31 Approval of
documents
1 day Thu
4/25/19
Thu
4/25/19
30 Administratior,Analyst,CEO,Finance
manager,Project
Manager
$1,640.00
Analyst,Project Manager
Analyst,Project Manager
Project Manager
Project Manager
3/ 15
Accounts manager,Administratior,CEO,Finance manager,Installation manage
Accounts manager,CEO,Finance manager,Installation manager,Project Ma
Project Manager
Analyst,Project Manager
Accounts manager,CEO,Finance manager,Installation manager,Pro
3/ 26
Installation staffs,Programmer,Project Manager
Programmer
Programmer
4/ 8
Programmer,Quality agent
Analyst,Quality agent
Quality agent
4/ 12
Programmer
Programmer
4/ 18
Analyst
Administratior,Analyst
Administratior,Analyst,CEO,F
10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30
March 2019 April 2019
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 21
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.