University Project Management Report: St. Helena Marina Development

Verified

Added on  2021/05/27

|20
|3427
|115
Report
AI Summary
This report provides a comprehensive analysis of the St. Helena Marina development project. It begins with an introduction outlining the project's purpose of attracting tourists and promoting tourism. The report then delves into stakeholder analysis, identifying key stakeholders and their roles, responsibilities, interests, and potential impacts. It addresses communication and political issues, including stakeholder management, communication strategies, and political considerations. A business case is presented, including an executive summary, background information, financial aspects, objectives, benefits, and stakeholder issues. The project's key milestones, high-level schedule, and budget are detailed, along with a risk assessment, assumptions, and communication plan. The report concludes with recommendations and supporting documentation, including a Gantt chart and bibliography.
Document Page
Running head: PROJECT MANAGEMENT: - ST. HELENA MARINA DEVELOPMENT
Project Management
St. Helena Marina Development Project
Name of the Student
Name of the University
Author note
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
1
PROJECT MANAGEMENT: - ST. HELENA MARINA DEVELOPMENT
Table of Contents
Introduction......................................................................................................................................3
Task 1: Stakeholders........................................................................................................................3
Task 2: Stakeholder, Communications, & Political Issues..............................................................6
Task 3: Outline of Business Case....................................................................................................7
Executive Summary.....................................................................................................................7
Background..................................................................................................................................7
Finance: Source of funds.............................................................................................................8
Objectives and scope...................................................................................................................8
Benefits........................................................................................................................................8
Summary of stakeholder issues...................................................................................................8
Stakeholder management plan.....................................................................................................9
Key milestones.............................................................................................................................9
High-Level Schedule...................................................................................................................9
Project Budget...........................................................................................................................12
Risks..........................................................................................................................................14
Assumptions..............................................................................................................................15
Project communications.............................................................................................................15
Recommendation.......................................................................................................................15
Task 4.............................................................................................................................................15
Bibliography..................................................................................................................................16
Appendix........................................................................................................................................18
Figure 1: Gantt chart......................................................................................................................18
Document Page
2
PROJECT MANAGEMENT: - ST. HELENA MARINA DEVELOPMENT
Introduction
New developments and changes allow the community to be upgraded and adopt new
behaviors those can result in the enhancement of the life living of the individuals within the
society. Development of the marina near Jamestown wharf has been considered one of the best
approach for attracting the tourists and promotes tourism in the Saint Helena Island. The purpose
of this report is to highlight the aspects related to the stakeholders and communication
management within the project considering the successful and efficient delivery of the project. A
business case is also proposed considering the various deliverables of the project.
Task 1: Stakeholders
Interviewing the stakeholders via questionnaire can be regarded as the best approach for
this project delivery and set of questions were distributed for identifying the problems those are
expected to be faced by them after connecting with the project. Following are the results of the
interview:
Name Stakeholder Roles Responsibilities Interest Impact
Louie
Phillips
Head of the
Project
Manage all the
stakeholders
and make
better
decision-
making
Consider every
stakeholder
while decision-
making
High Very High
Aimee Project Manager Manage the Every Very High Very High
Document Page
3
PROJECT MANAGEMENT: - ST. HELENA MARINA DEVELOPMENT
Curtis roles and
responsibilities
of the
stakeholders
associated
within the
project
stakeholder is
assigned with
the duties and
jobs as per their
capability of
project delivery
Morgan
Norris
Architect
Develop the
design of the
entire
transformation
as per the need
Consider all the
natural aspects
and develop a
sophisticated
and long
running model
for the
establishment
Medium High
Erin
Newton
Resource
Manager
Manage the
resources
necessary for
the delivery of
the project
All the
resources
necessary for
the project
delivery is
available
throughout the
project
Medium High
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
4
PROJECT MANAGEMENT: - ST. HELENA MARINA DEVELOPMENT
lifecycle
Emily
Houghton
Business Analyst
Analyze the
tourism
market in the
local and
global
environment
Effectively
propose the
results for the
implementation
of the changes
High High
Charlie
Nixon
Market Analyst
Analyze the
internal and
external
markets for
identifying the
problems and
solution
Propose a best
course of action
for enhancing
the market
condition
Medium Medium
Georgina
Doherty
Promotional
Manager
Promote the
new growth
and
development
at St. Helena
Marina
Promote the
objective and
outcomes in
efficient and
effective
manner
High Medium
Louie
Arnold
Civil Engineers Deliver the
civil
engineering
Keep the civil
construction
risks far away
Very High High
Document Page
5
PROJECT MANAGEMENT: - ST. HELENA MARINA DEVELOPMENT
and
construction
works
from the
project
-
Local community
Avail the
services being
presented
Provide
necessary
suggestions and
feedback
Low High
-
UK Government
Provide loans
and legal
agreement to
proceed with
the project
Provide enough
funds and all
the necessary
legal allowance
High High
Task 2: Stakeholder, Communications, & Political Issues
Issues raised in the development of this project can be listed as:
Stakeholder issues: assigning stakeholders with proper skills and knowledge related to
the same sector can be an issue while executing the project as in manner to adhere maximum
efficiency from the jobs of the stakeholders, it is necessary to assign the roles and responsibilities
as per their capabilities.
Communication issues: proper communication needs to be established considering the
discussion on the ongoing project, related issues, and solution for the successful delivery of the
project. it is an obvious factor to look the project from different perspectives so an effective
Document Page
6
PROJECT MANAGEMENT: - ST. HELENA MARINA DEVELOPMENT
communication management plan is necessary for the development and growth of a successful
project.
Political issues: This is a very big project and hence, needs various construction and
modifications for which outsourcing becomes the crucial factor for the successful deployment of
the project. The project needs to be politically clear in manner to assure not any further obstacle
in the growth and development of the project.
Environmental issues: The entire project will need to be completed on an island and
hence, the logistics is a genuine problem that should be eliminated before the project execution
starts and manage the exchange of the resources throughout the project lifecycle.
Task 3: Outline of Business Case
Executive Summary
The purpose of this task is to summarize the current situation of the island and propose a
planned and effective business case that can reflect the aspects of the proposed project. the
delivery of the project should be an effective and efficient follow of the activities that can be
helpful in b ringing out maximum profit for the UK government.
Background
The proposed project will be establishing a marina that will have all types of the fantasy
that is always loveable by the tourist while thinking of visiting an island. It will provide a
sophisticated model for the logistics and transport in manner to be connected with the outside
world. Berthing facilities will be enhanced through increasing the berth capacities. There will be
establishment of the bars, restaurants, parking, residential apartments, online taxi services and
many more.
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7
PROJECT MANAGEMENT: - ST. HELENA MARINA DEVELOPMENT
Finance: Source of funds
Government will be funding the entire growth and production of the project. Further
attempts can be made to get more funds through promoting the private companies through
offering advertisement in the exchange of the financial help.
Objectives and scope
In-scope objectives of the project are:
To provide better tourism experience to the tourists
To deliver the project in successful and efficient manner
To establish a transport network for increasing the traffic of the tourists
To attract the tourists through providing attractive facilities
Out-scope objectives are:
Promotion related objectives are out of scope
Conflict management is also out of the scope
Benefits
Increase the tourists engagement with the island
Enhance the overall revenue of the UK treasury
Enhance the livelihood of the local community of the island
Provide better and enhanced facilities and services to the consumers
Summary of stakeholder issues
Proper and effective communication
Resource management
Transporting
Document Page
8
PROJECT MANAGEMENT: - ST. HELENA MARINA DEVELOPMENT
Legal agreements
Total cost
Experienced manager or leader
Stakeholder management plan
Brainstorming, regular meetings, discussing weekly report, regular meetings, and other medium
of interactions will be utilized for the delivery of the stakeholder management.
Key milestones
WBS Task Name Duration Start Finish
1 St. Helena Marina Development 781 days Wed 5/23/18 Wed 5/19/21
1.1 Phase 1: Project Initiation 130 days Wed 5/23/18 Tue 11/20/18
1.1.6 Milestone 1: Approval for the project 0 days Tue 11/20/18 Tue 11/20/18
1.2 Phase 2: Project Planning 127 days Wed 11/21/18 Thu 5/16/19
1.2.9 Milestone 2: project planning
Completed 0 days Thu 5/16/19 Thu 5/16/19
1.3 Phase 3: Project Execution 357 days Fri 5/17/19 Mon 9/28/20
1.3.9 Milestone 3: Project Execution
completed 0 days Mon 9/28/20 Mon 9/28/20
1.4 Phase 4: Monitoring and Auditing 110 days Tue 9/29/20 Mon 3/1/21
1.4.6 Milestone 4: completed 0 days Mon 3/1/21 Mon 3/1/21
1.5 Phase 5: Project Closure 57 days Tue 3/2/21 Wed 5/19/21
1.5.6 Milestone 5 completed 0 days Wed 5/19/21 Wed 5/19/21
High-Level Schedule
WBS Task Name Duration Start Finish
1 St. Helena Marina Development 781 days Wed
5/23/18 Wed 5/19/21
1.1 Phase 1: Project Initiation 130 days Wed Tue 11/20/18
Document Page
9
PROJECT MANAGEMENT: - ST. HELENA MARINA DEVELOPMENT
5/23/18
1.1.1 Analyzing the current problem 15 days Wed
5/23/18 Tue 6/12/18
1.1.2 Proposing solution 25 days Wed
6/13/18 Tue 7/17/18
1.1.3 Identifying the feasibility of the proposed
solution 20 days Wed
7/18/18 Tue 8/14/18
1.1.4 Proposing the Proposal of the project 25 days Wed
8/15/18 Tue 9/18/18
1.1.5 loan approval from the UK government 45 days Wed
9/19/18 Tue 11/20/18
1.1.6 Milestone 1: Approval for the project 0 days Tue
11/20/18 Tue 11/20/18
1.2 Phase 2: Project Planning 127 days Wed
11/21/18 Thu 5/16/19
1.2.1 Enlisting the requirements 25 days Wed
11/21/18 Tue 12/25/18
1.2.2 Identifying the resources 30 days Wed
12/26/18 Tue 2/5/19
1.2.3 Preparing work Breakdown Structure 10 days Wed 2/6/19 Tue 2/19/19
1.2.4 Assigning Architect 7 days Wed
2/20/19 Thu 2/28/19
1.2.5 Identifying key stakeholders 15 days Fri 3/1/19 Thu 3/21/19
1.2.6 Developing the schedule 15 days Fri 3/22/19 Thu 4/11/19
1.2.7 Assigning Stakeholders role and
responsibility 10 days Fri 4/12/19 Thu 4/25/19
1.2.8 Estimating the budget of the project 15 days Fri 4/26/19 Thu 5/16/19
1.2.9 Milestone 2: project planning Completed 0 days Thu 5/16/19 Thu 5/16/19
1.3 Phase 3: Project Execution 357 days Fri 5/17/19 Mon 9/28/20
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
10
PROJECT MANAGEMENT: - ST. HELENA MARINA DEVELOPMENT
1.3.1 Design of the Marina Complex 60 days Fri 5/17/19 Thu 8/8/19
1.3.2 Propose the design for approval 7 days Fri 8/9/19 Mon 8/19/19
1.3.3 Implement the Mooring Facilities 60 days Tue 8/20/19 Mon 11/11/19
1.3.4 Establishing the berthing facilities 70 days Tue
11/12/19 Mon 2/17/20
1.3.5 Develop permanent birthing facilities 65 days Tue 2/18/20 Mon 5/18/20
1.3.6 Establishing sheltered Marina complex 40 days Tue 5/19/20 Mon 7/13/20
1.3.7 Implementing government facilities 30 days Tue 7/14/20 Mon 8/24/20
1.3.8 Arrangements for service, fuel and
repairing facilities 25 days Tue 8/25/20 Mon 9/28/20
1.3.9 Milestone 3: Project Execution
completed 0 days Mon
9/28/20 Mon 9/28/20
1.4 Phase 4: Monitoring and Auditing 110 days Tue 9/29/20 Mon 3/1/21
1.4.1 evaluating every activity 15 days Tue 9/29/20 Mon 10/19/20
1.4.2 Project Evaluation checklist 20 days Tue
10/20/20 Mon 11/16/20
1.4.3 Identifying modifications 30 days Tue
11/17/20 Mon 12/28/20
1.4.4 Implementing changes 20 days Tue
12/29/20 Mon 1/25/21
1.4.5 Reviewing the project activities 25 days Tue 1/26/21 Mon 3/1/21
1.4.6 Milestone 4: completed 0 days Mon 3/1/21 Mon 3/1/21
1.5 Phase 5: Project Closure 57 days Tue 3/2/21 Wed 5/19/21
1.5.1 Project Documentation 15 days Tue 3/2/21 Mon 3/22/21
1.5.2 Stakeholder sign off 7 days Tue 3/23/21 Wed 3/31/21
1.5.3 Stakeholder releasing from contract 10 days Thu 4/1/21 Wed 4/14/21
1.5.4 resource releasing 10 days Thu 4/15/21 Wed 4/28/21
1.5.5 Lessons learned documentation 15 days Thu 4/29/21 Wed 5/19/21
1.5.6 Milestone 5 completed 0 days Wed Wed 5/19/21
Document Page
11
PROJECT MANAGEMENT: - ST. HELENA MARINA DEVELOPMENT
5/19/21
Project Budget
WBS Task Name Duration Resource Names Cost
1 St. Helena Marina
Development
781
days $2,121,760.00
1.1 Phase 1: Project
Initiation
130
days $207,600.00
1.1.1 Analyzing the current
problem 15 days Business Analyst, Market
Analyst, Project Manager $19,800.00
1.1.2 Proposing solution 25 days
Business Analyst, Market
Analyst, Project Manager,
Architect, Civil Engineers
$53,000.00
1.1.3 Identifying the feasibility
of the proposed solution 20 days
Business Analyst, Market
Analyst, Project Manager,
Architect, Civil Engineers
$42,400.00
1.1.4 Proposing the Proposal
of the project 25 days Business Analyst, Market
Analyst, Project Manager $33,000.00
1.1.5 loan approval from the
UK government 45 days Business Analyst, Market
Analyst, Project Manager $59,400.00
1.1.6 Milestone 1: Approval
for the project 0 days $0.00
1.2 Phase 2: Project Planning 127
days $337,280.00
1.2.1 Enlisting the
requirements 25 days
Architect, Business Analyst, Civil
Engineers, Market Analyst,
Project Manager, Resource
Manager, Resources[1],
Promotional Manager
$174,000.00
1.2.2 Identifying the resources 30 days
Architect, Civil Engineers,
Project Manager, Resource
Manager
$55,200.00
1.2.3 Preparing work
Breakdown Structure 10 days
Architect, Civil Engineers,
Project Manager, Resource
Manager
$18,400.00
1.2.4 Assigning Architect 7 days
Architect, Civil Engineers,
Project Manager, Resource
Manager
$12,880.00
1.2.5 Identifying key
stakeholders 15 days
Architect, Civil Engineers,
Project Manager, Resource
Manager
$27,600.00
1.2.6 Developing the schedule 15 days Architect, Civil Engineers,
Project Manager, Resource
$27,600.00
Document Page
12
PROJECT MANAGEMENT: - ST. HELENA MARINA DEVELOPMENT
Manager
1.2.7 Assigning Stakeholders
role and responsibility 10 days Project Manager $6,000.00
1.2.8 Estimating the budget of
the project 15 days Project Manager, Resource
Manager $15,600.00
1.2.9 Milestone 2: project
planning Completed 0 days $0.00
1.3 Phase 3: Project
Execution
357
days $1,248,000.00
1.3.1 Design of the Marina
Complex 60 days Architect, Civil Engineers,
Resources[1] $148,000.00
1.3.2 Propose the design for
approval 7 days Architect, Civil Engineers,
Resources[1] $105,600.00
1.3.3 Implement the Mooring
Facilities 60 days
Architect, Civil Engineers,
Resources[1], Human Labor,
Promotional Manager
$181,600.00
1.3.4 Establishing the berthing
facilities 70 days
Architect, Civil Engineers,
Resources[1], Human Labor,
Promotional Manager
$195,200.00
1.3.5 Develop permanent
birthing facilities 65 days
Architect, Civil Engineers,
Resources[1], Human Labor,
Promotional Manager
$188,400.00
1.3.6 Establishing sheltered
Marina complex 40 days
Architect, Civil Engineers,
Resources[1], Human Labor,
Promotional Manager
$154,400.00
1.3.7 Implementing
government facilities 30 days
Architect, Civil Engineers,
Resources[1], Human Labor,
Promotional Manager
$140,800.00
1.3.8
Arrangements for
service, fuel and repairing
facilities
25 days
Architect, Civil Engineers,
Resources[1], Human Labor,
Promotional Manager
$134,000.00
1.3.9 Milestone 3: Project
Execution completed 0 days $0.00
1.4 Phase 4: Monitoring and
Auditing
110
days $269,600.00
1.4.1 evaluating every activity 15 days
Business Analyst, Market
Analyst, Project Manager,
Resource Manager
$26,400.00
1.4.2 Project Evaluation
checklist 20 days
Architect, Business Analyst, Civil
Engineers, Market Analyst,
Project Manager, Resource
Manager
$51,200.00
1.4.3 Identifying modifications 30 days Architect, Business Analyst, Civil
Engineers, Market Analyst,
$76,800.00
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
13
PROJECT MANAGEMENT: - ST. HELENA MARINA DEVELOPMENT
Project Manager, Resource
Manager
1.4.4 Implementing changes 20 days
Architect, Business Analyst, Civil
Engineers, Market Analyst,
Project Manager, Resource
Manager
$51,200.00
1.4.5 Reviewing the project
activities 25 days
Architect, Business Analyst, Civil
Engineers, Market Analyst,
Project Manager, Resource
Manager
$64,000.00
1.4.6 Milestone 4: completed 0 days $0.00
1.5 Phase 5: Project Closure 57 days $59,280.00
1.5.1 Project Documentation 15 days Project Manager, Resource
Manager $15,600.00
1.5.2 Stakeholder sign off 7 days Project Manager, Resource
Manager $7,280.00
1.5.3 Stakeholder releasing
from contract 10 days Project Manager, Resource
Manager $10,400.00
1.5.4 resource releasing 10 days Project Manager, Resource
Manager $10,400.00
1.5.5 Lessons learned
documentation 15 days Project Manager, Resource
Manager $15,600.00
1.5.6 Milestone 5 completed 0 days $0.00
Risks
Increase in the budget
Increase in the schedule
Resource lagging or jumping
Transporting
Communication gap
Not meeting the project constraints
Assumptions
The project will be delivered within the expected time and budget and all the proposals
will be approved by the stakeholders. Waterfall methodology will be utilized and hence, the next
Document Page
14
PROJECT MANAGEMENT: - ST. HELENA MARINA DEVELOPMENT
activity will be dependent on the completion of the previous activities. Quality evaluation, and
project evaluation have not been considered for this business case.
Project communications
Regular meeting in every week will be executed considering the presence of every
necessary stakeholder in manner to measures and identify the growth and development of the
project.
Recommendation
The project manager should follow the budget and schedule as proposed in the above
report considering the proper and effective delivery of the project in far efficient and effective
manner.
Task 4
Following the case study, I get to know that establishing such big project needs an
experienced and educated manager that can deliver the project activities through utilizing the
knowledge and ideas related to the project management. I also identified that no matter what big
picture we consider for the delivery of the project, it can always be extended for the better and
effective consideration of the scope and project delivery. While identifying the business case I
get to know that researching about the project, its impact, and other aspects are very crucial and
vital for the consideration of the delivery of the project. I understand that cost and schedule are
the crucial constraints those should be considered while delivering any single activity throughout
the project.
Document Page
15
PROJECT MANAGEMENT: - ST. HELENA MARINA DEVELOPMENT
Bibliography
Ahern, T., Leavy, B., & Byrne, P. J. (2014). Complex project management as complex problem
solving: A distributed knowledge management perspective. International Journal of Project
Management, 32(8), 1371-1381.
Beringer, C., Jonas, D., & Kock, A. (2013). Behavior of internal stakeholders in project portfolio
management and its impact on success. International Journal of Project Management, 31(6), 830-
846.
Bresnen, M. (2016). Institutional development, divergence and change in the discipline of project
management. International journal of project management, 34(2), 328-338.
Burke, R. (2013). Project management: planning and control techniques. New Jersey, USA.
Hornstein, H. A. (2015). The integration of project management and organizational change
management is now a necessity. International Journal of Project Management, 33(2), 291-298.
Joslin, R., & Müller, R. (2015). Relationships between a project management methodology and
project success in different project governance contexts. International Journal of Project
Management, 33(6), 1377-1392.
Kaiser, M. G., El Arbi, F., & Ahlemann, F. (2015). Successful project portfolio management
beyond project selection techniques: Understanding the role of structural alignment. International
Journal of Project Management, 33(1), 126-139.
Kerzner, H. (2013). Project management: a systems approach to planning, scheduling, and
controlling. John Wiley & Sons.
Leach, L. P. (2014). Critical chain project management. Artech House.
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
16
PROJECT MANAGEMENT: - ST. HELENA MARINA DEVELOPMENT
Lock, M. D. (2014). The essentials of project management. Ashgate Publishing, Ltd..
Martinsuo, M. (2013). Project portfolio management in practice and in context. International
Journal of Project Management, 31(6), 794-803.
Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking
project management performance and project success. International Journal of Project
Management, 32(2), 202-217.
Reiss, G. (2013). Project management demystified: Today's tools and techniques. Routledge.
Svejvig, P., & Andersen, P. (2015). Rethinking project management: A structured literature
review with a critical look at the brave new world. International Journal of Project Management,
33(2), 278-290.
Teller, J., & Kock, A. (2013). An empirical investigation on how portfolio risk management
influences project portfolio success. International Journal of Project Management, 31(6), 817-
829.
Todorović, M. L., Petrović, D. Č., Mihić, M. M., Obradović, V. L., & Bushuyev, S. D. (2015).
Project success analysis framework: A knowledge-based approach in project management.
International Journal of Project Management, 33(4), 772-783.
Too, E. G., & Weaver, P. (2014). The management of project management: A conceptual
framework for project governance. International Journal of Project Management, 32(8), 1382-
1394.
Turner, J. R. (2014). The handbook of project-based management (Vol. 92). New York, NY:
McGraw-hill.
Document Page
17
PROJECT MANAGEMENT: - ST. HELENA MARINA DEVELOPMENT
Document Page
18
PROJECT MANAGEMENT: - ST. HELENA MARINA DEVELOPMENT
Appendix
Gantt Chart
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
19
PROJECT MANAGEMENT: - ST. HELENA MARINA DEVELOPMENT
Figure 1: Gantt chart
(Source: Created by Author)
WBS
Figure 2: WBS