This report presents a detailed analysis of Stinky Bathrooms Limited's supply chain, encompassing a supply chain diagram, DILO (Day in the Life of) analysis, and an activity schedule. The supply chain diagram illustrates the flow of goods from various origins (Far East, Europe, and the UK) to the company's outlets, considering palletization and sales distribution. The DILO analysis identifies time utilization and responsibilities within the organization, outlining steps for its development and improvement. The activity schedule outlines the sequence and dependencies of project activities, considering the company's product range (bathroom suites, accessories, and spare parts). Furthermore, the report addresses warehouse space allocation based on sales data and product characteristics, recommending optimal space distribution to maximize profitability. The analysis also highlights opportunities to reduce transportation costs by optimizing sourcing locations and palletization strategies.
tabler-icon-diamond-filled.svg

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
Answer 1
Supply Chain Diagram is a pictorial representation of the whole process from the raw material to
the manufacturer to mediator to final consumer in case of manufacturing entities. In case of
trading companies, it shows the whole process from purchases to sales.
Supply Chain Diagram:
DILO Analysis:
Far East
Not Palletised
Europe
Palletised
UK
Palletised
Bathroom Suites- 70%
Bathroom Accessories- 20%
Spare Parts 100%
Bathroom Suites- 20%
Bathroom Accessories-
30%
Bathroom Suites- 10%
Bathroom Accessories-
50%
Firm’s Outlet
70% sales to south of
England
70% sales evenly in UK
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
It is the techniaue which helps in identifying the total time spent in an organization. It gives an
understanding of roles and responsibilities performed by different members of the organization. Steps to
develop a DILO:
1. Determine the scope: Scope can be defined by analyzing the processes, objectives and other
functions.
2. Convey your objectives: Before performing DILO, we should convey the resn why we are
performing the DILO analysis.
3. Identify Core activities: All the activities to be performed needs to be analysed and then it has
to be bifurcated who will perform which activity.
4. Prepare DILO Worksheet: A worksheet needs to be prepared mentioning some questions
which every employee has to fill.
5. Analyse activities of collate participants: Every member of an organization were asked some
question regarding their activity and that can be analyzed by giving a score between 1 to 5 by
analyzing their time utilization.
6. Analyzing DILO worksheet: Analyze the worksheet filled up by the employee and find out
discrepancies if any.
7. Set up Plan for improvement: After analyzing, develop a plan for improving any discrepancy.
Activity Schedule:
Activity Schedule is the method of presenting the activities of the project that defines the sequence of
activities to be performed and the dependencies between them, if any.
Stinky Bathrooms limited sells bathroom furniture including bathroom accessories, suits and spare parts.
Activities are:
1. Stinky acquires different materials from different areas like from Far East, Europe and UK
2. Pallet configuration are done for all materials received from Europe and UK
3. After palletization, materials are sent to the outlets of the company which are scattered in south
of England and evenly across UK
4. All outbound materials are palletized
Document Page
5. All the outlets are open for 360 days in a year.
Answer 2
We need to deliver on 15 docks for delivering the goods on the required location within given deadline
i.e. 10 A.M. We need to ensure timely delivery on ports as materials need to be transferred by 10 am
daily.
Space required for one order
Own
Order
Liner Unit
Total
Unit
Space required
Cu.m
Bathroom
Accessories 25.00
10.0
0 250.00 41.50
Bathroom Suites 8.00 3.00 24.00 19.99
Spare Parts 50.00
50.0
0
2,500.0
0 0.69
2,774.0
0 62.18
Independent
Order
Liner Unit
Total
Unit
Space required
Cu.m
Bathroom
Accessories 10.00
10.0
0 100.00 16.60
Bathroom Suites
Document Page
3.00 3.00 9.00 7.50
Spare Parts 30.00
50.0
0
1,500.0
0 0.41
1,609.0
0 24.51
Answer 3
As per the current stock of all the parts Bathroom Accessories , Bathroom suites and Spare Parts it is
1,012.8 Cu.m , Maximum space is required for Bathroom suites as its one 1 SKU take approx. 0.83
cu.m. space in comparison of Bathroom Accessories which take only 0.167 cu.m. space for storage one
SKU.
As per the company sales data, Bathroom accessories has the highest sales value per cubic meter which
is 500 pond per cubic meter in compare to bathroom suites 100 pound per cubic meter. So highest rank
should be given to Bathroom Accessories and maximum space align to this. And minimum space for
Spare parts as it has least sales value.
Total Space required is given in the below table.
Sales Sales per cubic meter Totalt Cu.m
30,000,000 100 300,000
30,000,000 500 60,000
5,000,000 1000 5,000
Answer 4
In the present scenario, Company is picking material from Far East, UK and Europe. Materials from Far
East are not palletized. Pallet is nothing but a type of rack to store the goods while transportation. It will
require less space while transportation hence will reduce the transportation cost. As of now a large
chevron_up_icon
1 out of 4
circle_padding
hide_on_mobile
zoom_out_icon
logo.png

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]