The assignment is centered on the comprehensive understanding of project management in the context of developing murals. It begins by exploring the project lifecycle, detailing phases from initiation to closure, and emphasizes identifying stakeholders involved in mural projects, such as community members and artists. The importance of using a Gantt chart for scheduling tasks during implementation is discussed, alongside methodologies like the waterfall model for systematic execution. Risk assessment analysis highlights potential hazards and mitigation strategies, crucial for ensuring project success. Lastly, it elaborates on the multifaceted responsibilities of the project manager in overseeing mural development activities, ensuring adherence to plans, efficient resource utilization, and addressing risks effectively.

PROJECT MANAGEMENT
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

TABLE OF CONTENTS
Question1.........................................................................................................................................3
1.1 Project life cycle diagram......................................................................................................3
1.2 Identify possible stakeholders and choice for stakeholders...................................................4
Internal stakeholders..................................................................................................................4
Question 2........................................................................................................................................4
2.1 Steps needs to be taken to achieve project aims....................................................................4
2.2 GANTT chart.........................................................................................................................6
Question 3........................................................................................................................................7
3.1 Methodology and approach used for project.........................................................................7
Question 4........................................................................................................................................7
4.1 Risk assessment.....................................................................................................................7
4.2 Activities that will be overseen by the project manager........................................................8
REFERENCES................................................................................................................................9
Question1.........................................................................................................................................3
1.1 Project life cycle diagram......................................................................................................3
1.2 Identify possible stakeholders and choice for stakeholders...................................................4
Internal stakeholders..................................................................................................................4
Question 2........................................................................................................................................4
2.1 Steps needs to be taken to achieve project aims....................................................................4
2.2 GANTT chart.........................................................................................................................6
Question 3........................................................................................................................................7
3.1 Methodology and approach used for project.........................................................................7
Question 4........................................................................................................................................7
4.1 Risk assessment.....................................................................................................................7
4.2 Activities that will be overseen by the project manager........................................................8
REFERENCES................................................................................................................................9

Question1
1.1 Project life cycle diagram
Figure 1Project life cycle
Project life cycle diagram reflects the different stages through which project will passed.
It can be observed that under the current project 10 murals will be developed under which
different paintings will be prepared. Project life cycle stage will be divided in to three stages
planning, executive and ongoing operations. In the planning stage first of all survey will be done
1.1 Project life cycle diagram
Figure 1Project life cycle
Project life cycle diagram reflects the different stages through which project will passed.
It can be observed that under the current project 10 murals will be developed under which
different paintings will be prepared. Project life cycle stage will be divided in to three stages
planning, executive and ongoing operations. In the planning stage first of all survey will be done
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

about places where work can be done to attract tourism (Burke, 2013). In this regard at latter
stage feasibility study will be conducted and estimates about cost will be prepared. On the basis
of results entire project will be designed. In executive stage budget for developing murals will be
prepared and planning will be done accordingly. Finally, in last stage murals will be developed
and in this way project will be completed.
1.2 Identify possible stakeholders and choice for stakeholders
Internal stakeholders Manager: Manager will be senior in structure and will look after entire project related
activities. Finance controller: Finance controller will allocate budget among varied activities. Operation manager: Operation manager will look after entire project related operations. Supervisor: Supervisor will supervise workers at site.
External stakeholders
Government: Government is the important stakeholder as it is giving grant for project.
Thus, it will receive time to time update on current project.
Auditors: Auditors are important stakeholder as they will be appointed by government
for evaluating project and identify if any manipulation is done in money.
Private firm manager that support on current project: Assistance can be taken from the
private firm in order to implement project in better manner. Thus, its manager are the
important stakeholder in the current project (Blengini and et.al., 2012).
Private firm finance controller: Guidance will be taken from the finance controller for
managing cash in better manner.
Private firm operation manager: Operation manager will give guidance in respect to
managing project related operations.
Question 2
2.1 Steps needs to be taken to achieve project aims
Identify and select sites Teams
Application for grant funding Project manager
Contacting wall(site owners) Project manager
Taking sponsorship Teams
Arranging grant and sponsorship meeting Project manager
stage feasibility study will be conducted and estimates about cost will be prepared. On the basis
of results entire project will be designed. In executive stage budget for developing murals will be
prepared and planning will be done accordingly. Finally, in last stage murals will be developed
and in this way project will be completed.
1.2 Identify possible stakeholders and choice for stakeholders
Internal stakeholders Manager: Manager will be senior in structure and will look after entire project related
activities. Finance controller: Finance controller will allocate budget among varied activities. Operation manager: Operation manager will look after entire project related operations. Supervisor: Supervisor will supervise workers at site.
External stakeholders
Government: Government is the important stakeholder as it is giving grant for project.
Thus, it will receive time to time update on current project.
Auditors: Auditors are important stakeholder as they will be appointed by government
for evaluating project and identify if any manipulation is done in money.
Private firm manager that support on current project: Assistance can be taken from the
private firm in order to implement project in better manner. Thus, its manager are the
important stakeholder in the current project (Blengini and et.al., 2012).
Private firm finance controller: Guidance will be taken from the finance controller for
managing cash in better manner.
Private firm operation manager: Operation manager will give guidance in respect to
managing project related operations.
Question 2
2.1 Steps needs to be taken to achieve project aims
Identify and select sites Teams
Application for grant funding Project manager
Contacting wall(site owners) Project manager
Taking sponsorship Teams
Arranging grant and sponsorship meeting Project manager
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Determine and document legal responsibilities Project manager
Obtaining quotes Project manager
Research and development mural content Teams
Conduct site inspection Project team
Researching artists Project team
Meeting with community groups to confirm their
commitment Project manager
Contacting department of arts and culture Project team
Form teams and establish team leaders Project manager
Render walls Contractor
Determine criteria for murals
Team leaders, project
manager
Mural content to be approved Subcommittee of teams
Artists to be selected and briefed Teams
Assemble scaffolding Contractor
Paint murals Artists, community assistants
Launch murals to media and community
Team leaders, project
manager
Obtaining quotes Project manager
Research and development mural content Teams
Conduct site inspection Project team
Researching artists Project team
Meeting with community groups to confirm their
commitment Project manager
Contacting department of arts and culture Project team
Form teams and establish team leaders Project manager
Render walls Contractor
Determine criteria for murals
Team leaders, project
manager
Mural content to be approved Subcommittee of teams
Artists to be selected and briefed Teams
Assemble scaffolding Contractor
Paint murals Artists, community assistants
Launch murals to media and community
Team leaders, project
manager

2.2 GANTT chart
Figure 2GANTT chart
Figure 2GANTT chart
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Figure 3Network diagram
Question 3
3.1 Methodology and approach used for project
Waterfall model will be followed and under this first of all project scope will be
determined. The activities that must be performed in the project will be determined in this stage.
Clear goals and objectives will be determined in respect to each activity in the project. Different
teams will be prepared and under same different activities will be allocated. Traditional
approach will be used and under this first of all project will be initiated and preliminary
preparation about project will be done (Tsai and et.al., 2011). Then proper plan will be prepared
like way in which fund will be raise in respect to mural and allocation of team etc. Project will be
implemented and under this as per plan all acts related to mural will be performed by the teams.
Project control stage will be performed to ensure that all acts are performed according to
prepared plan. Finally, after completion of project it will be closed.
Question 4
4.1 Risk assessment
Table 1Risk assessment analysis
Probability Impacts Ranking
Canoie training exercises on the river and riverside
flats 0.1 5 2
Canoe rides may result in mishaps on theriver 0.4 4 4
Canoie rides entering and exiting canoes from river
back 0.5 3 5
Question 3
3.1 Methodology and approach used for project
Waterfall model will be followed and under this first of all project scope will be
determined. The activities that must be performed in the project will be determined in this stage.
Clear goals and objectives will be determined in respect to each activity in the project. Different
teams will be prepared and under same different activities will be allocated. Traditional
approach will be used and under this first of all project will be initiated and preliminary
preparation about project will be done (Tsai and et.al., 2011). Then proper plan will be prepared
like way in which fund will be raise in respect to mural and allocation of team etc. Project will be
implemented and under this as per plan all acts related to mural will be performed by the teams.
Project control stage will be performed to ensure that all acts are performed according to
prepared plan. Finally, after completion of project it will be closed.
Question 4
4.1 Risk assessment
Table 1Risk assessment analysis
Probability Impacts Ranking
Canoie training exercises on the river and riverside
flats 0.1 5 2
Canoe rides may result in mishaps on theriver 0.4 4 4
Canoie rides entering and exiting canoes from river
back 0.5 3 5
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Project manager should conduct risk assessment and analysis. This is because it is very important
to ensure that areas where risk is maximum is identified. By formulating strategy on time risk
can be mitigated in the business.
4.2 Activities that will be overseen by the project manager
There are number of activities that will be overlook by the manager. From start to end
manager will look after each and every activity that is associated with the project. Project
manager will ensure that activity of developing murals is performed in systematic way and all
employees are performing their responsibility in proper manner. It will also look after use of
fund in different project related activities to ensure that same is used effectively in the business.
to ensure that areas where risk is maximum is identified. By formulating strategy on time risk
can be mitigated in the business.
4.2 Activities that will be overseen by the project manager
There are number of activities that will be overlook by the manager. From start to end
manager will look after each and every activity that is associated with the project. Project
manager will ensure that activity of developing murals is performed in systematic way and all
employees are performing their responsibility in proper manner. It will also look after use of
fund in different project related activities to ensure that same is used effectively in the business.

REFERENCES
Books and journals
Burke, R., 2013. Project management: planning and control techniques. New Jersey. USA.
Blengini, G.A. and et.al., 2012. Life Cycle Assessment guidelines for the sustainable production
and recycling of aggregates: the Sustainable Aggregates Resource Management project
(SARMa). Journal of Cleaner Production. 27. pp.177-181.
Tsai, W.H. and et.al., 2011. Incorporating life cycle assessments into building project decision-
making: an energy consumption and CO 2 emission perspective. Energy. 36(5). pp.3022-
3029.
Books and journals
Burke, R., 2013. Project management: planning and control techniques. New Jersey. USA.
Blengini, G.A. and et.al., 2012. Life Cycle Assessment guidelines for the sustainable production
and recycling of aggregates: the Sustainable Aggregates Resource Management project
(SARMa). Journal of Cleaner Production. 27. pp.177-181.
Tsai, W.H. and et.al., 2011. Incorporating life cycle assessments into building project decision-
making: an energy consumption and CO 2 emission perspective. Energy. 36(5). pp.3022-
3029.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 9
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.