Project Management: Online System Development for a Stud Farm

Verified

Added on  2023/06/12

|17
|3224
|88
Project
AI Summary
This project outlines the development of an online management system for a stud farm, beginning with defining the Measurable Organizational Value (MOV) across operational, customer, financial, strategic, and social areas. It details the project's scope, including interface design, database development, breed registry, recording facilities, and communication customization, while excluding future plans and marketing strategies. The project assumes resource availability and team cooperation within a $108,920 budget, addressing constraints like quality management and scope creep. The resource plan specifies roles, rates, and technology, followed by project milestones, activities, and a Gantt chart for time estimation. Budget allocation, risk assessment, quality assurance, verification, and validation activities are also discussed, concluding with a closure checklist and project evaluation against MOV objectives. Desklib provides this and many other project solutions for students.
Document Page
Running head: PROJECT MANAGEMENT
Student Name
ID Development of Online
management system
for Stud Farm
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
1
PROJECT MANAGEMENT
Part One:
1.1 MOV - Measurable Organisational Value
Area of Impact Rank (1 to 5)
Operational 1
Customer 2
Financial 3
Strategic 4
Social 5
1.2 Value of the project
The significance that is delivered is illustrated below:
Faster: The service, which is mainly supplied to the customers, is faster as well as much
more appropriate and as a result, the clients have to opportunity of getting solution of their queries
in short period.
Better: The customers can be able to get breeding services and have the opportunity of
paying online for the services with the help of the online. The advancement within the services helps
in making the services of the company much better.
1.3 Appropriate metric
Rank Impact Metrics Timeframe
1 Operational Improvement occurs
within the business
functions and
operations due to
implementation of the
system.
3 months
2 Customer Positive impact is
created on the
customers due to the
services and as a
result, the customers
of the organization
increase.
2months
3 Financial The yearly revenue
that is collected is 0.3
times more than the
revenue that is
collected last year
because of business
expansion within the
new system.
3 months
4 Strategic For providing proper
customer experience,
2 months
Document Page
2
PROJECT MANAGEMENT
numbers of strategies
are implemented.
5 Social For advertisement,
the companies use the
social media.
1 month
2. Part Two:
2.1 Scope
The scope is:
Creating design for the interface
Developing the database
Breed registry facility
Developing facility of recording
Providing reviewing option
Option for customized communication
Developing database for marketing
Contract management facility
Location identification facility
Tracking cost facility
2.2 Out of Scope
The out scope is:
No future plan was included within the project
Marketing strategies are also excluded from the project
2.3 Assumptions
The assumptions are:
The hardware as well as software that are needed will be easily available
Protect team will cooperate for finishing the project
Budget $ 108,920 s considered for finishing the project.
2.4 Constraints
The constraints are:
Handling of project quality within the lifecycle of the project
Avoiding the chances of scope creep
The project should be finished within the expected time as well as budget.
2.5 Scope Management Plan
The steps include:
The authority of the organization is committed to create scope development plan
Setting the boundary of the scope
Identification of deliverables that is supported by MOV
Providing confirmation that the scope is appropriately managed
Making sure that the controls are appropriate to avoid changes in the scope
Document Page
3
PROJECT MANAGEMENT
2.6 Resource Plan
People
Resource Name Type Std. Rate
Project planner Work $ 35.00/hr.
Developer Work $ 30.00/hr.
Database administrator Work $ 30.00/hr.
Designer Work $ 35.00/hr.
Human resource manager Work $ 35.00/hr.
Financial manager Work $ 35.00/hr.
Quality analyst Work $ 30.00/hr.
risk manager Work $ 30.00/hr.
Project manager Work $ 50.00/hr.
Technical expert Work $ 35.00/hr.
Risk manager Work $ 30.00/hr.
System administrator Work $ 30.00/hr.
System administrator Work $ 35.00/hr.
Software engineer Work $ 30.00/hr.
Project sponsor Work $ 0.00/hr.
Technology
Hardware RAM, hardware, desktop
Software Operating system, Java and more.
Network Server
Facilities
High speed of internet connection is provided as a facility for the developing the
project.
Other
Travel Requirements No facility of traveling is given
Training Requirements The team members are given training if
they are facing any type of issues.
Part three:
3.1 Project Milestones
Milestone Completion date
Milestone 1: Initiation completion Mon 28-05-18
Milestone 2: Project planning completion Thu 07-06-18
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
4
PROJECT MANAGEMENT
Milestone 3: Design phase completion Thu 21-06-18
Milestone 4: Development completion Thu 30-08-18
Milestone 5: Testing phase completion Fri 14-09-18
Milestone 6: Completion of monitoring and control phase Wed 26-09-18
Milestone 7: Completion of closure phase Mon 01-10-18
3.2 Project activities
Task Name
Online management system development for Stud
Farm
Project initiation phase
Requirement identification
Development of project pan
Cost benefit analysis
Milestone 1: Initiation completion
Planning phase
Identifying needed resources
Scheduling project activities
Allocating work to the team members
Making communication plan
Assigning project resources
Milestone 2: Project planning completion
Design phase
Designing prototype
incorporating features
Determining functional and non-functional needs
Milestone 3: Design phase completion
Development phase
Developing features of breeding
Creating design for the interface
Developing the database
Breed registry facility
Developing mobile related features
Developing facility of recording
Providing reviewing option
Option for customized communication
Developing financial features
Developing database for marketing
Contract management facility
Location identification facility
Tracking cost facility
Milestone 4: Development completion
Testing phase
Black box testing
Document Page
5
PROJECT MANAGEMENT
performance testing
User-acceptance testing
White box testing
User-acceptability testing
Milestone 5: Testing phase completion
Monitoring and control
Facility of request management
Facility of issue management
Facility of risk management
Team meetings
Undertaking earned value analysis
Milestone 6: Completion of monitoring and
control phase
Closing Phase
Post project review
Stakeholder sign off
Milestone 7: Completion of closure phase
3.3 Project resources
Resource table
Task Name Duration Resource Names
Online management system development for
Stud Farm 97 days
Project initiation phase 97 days
Requirement identification 2 days Project planner, Developer
Development of project pan 3 days Project planner
Cost benefit analysis 2 days Database administrator, Technical
expert
Milestone 1: Initiation completion 0 days
Planning phase 8 days
Identifying needed resources 2 days Developer
Scheduling project activities 1 day Database administrator, Technical
expert
Allocating work to the team members 2 days Developer, Database administrator,
Technical expert
Making communication plan 2 days Project planner, Technical expert
Assigning project resources 1 day Developer, Technical expert
Milestone 2: Project planning
completion 0 days
Design phase 10 days
Designing prototype 4 days risk manager, Financial manager,
Human resource manager
incorporating features 3 days
Software engineer, System
administrator, Human resource
manager
Document Page
6
PROJECT MANAGEMENT
Determining functional and non-
functional needs 3 days risk manager, Technical expert,
System administrator
Milestone 3: Design phase completion 0 days
Development phase 50 days
Developing features of breeding 15 days
Creating design for the interface 4 days Designer, System administrator,
Software engineer
Developing the database 5 days Project manager, Human resource
manager
Breed registry facility 6 days
Hardware and software
requirements[1],System
administrator, Software engineer,
System administrator
Developing mobile related features 15 days
Developing facility of recording 6 days Software engineer, System
administrator
Providing reviewing option 5 days
Developer, Human resource
manager, Software engineer,
Quality analyst
Option for customized communication 4 days
Database administrator, Human
resource manager, System
administrator
Developing financial features 20 days
Developing database for marketing 5 days Project manager, Designer, System
administrator
Contract management facility 4 days Developer, Software engineer,
Human resource manager
Location identification facility 5 days Project manager, Software
engineer, Human resource manager
Tracking cost facility 6 days Designer, Software engineer,
System administrator
Milestone 4: Development completion 0 days
Testing phase 11 days
Black box testing 2 days Additional cost[1],Risk manager,
Quality analyst
performance testing 3 days Quality analyst
User-acceptance testing 3 days Risk manager, Quality analyst
White box testing 2 days Risk manager, Quality analyst
User-acceptability testing 1 day Risk manager, Quality analyst
Milestone 5: Testing phase completion 0 days Risk manager, Quality analyst
Monitoring and control 9 days
Facility of request management 2 days Project planner
Facility of issue management 3 days Risk manager
Facility of risk management 2 days Risk manager, Quality analyst
Team meetings 1 day Developer, Project planner
Undertaking earned value analysis 1 day Technical expert, Project planner
Milestone 6: Completion of monitoring 0 days
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7
PROJECT MANAGEMENT
and control phase
Closing Phase 3 days
Post project review 1 day Project planner
Stakeholder sign off 2 days Financial manager, Project planner
Milestone 7: Completion of closure
phase 0 days
Resource overview
Project planner
Developer
Database administrator
Designer
Human resource manager
Finanacial manager
Qulaity analyst
ris manager
Project manageer
Technical expert
Risk manager
System admnistrator
System administrator
Software engineer
Project sponsor
0 hrs
100 hrs
200 hrs
300 hrs
Actual Work Remaining Work Baseline Work
Figure 1: Resource overview
(Source: Created by author)
Resource plan
Figure 2: Resource plan
(Source: Created by author)
Document Page
8
PROJECT MANAGEMENT
3.4 Time estimation (Gantt chart)
Figure 3: Time estimation
Document Page
9
PROJECT MANAGEMENT
(Source: Created by Author)
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
10
PROJECT MANAGEMENT
3.5 Project budget
Figure 4: Project budget
(Source: Created by Author)
Document Page
11
PROJECT MANAGEMENT
3.6 Time phase budget
May 2018 June 2018 July 2018 August
2018 September
2018 October
2018
$ 0.00
$ 5,000.00
$ 10,000.00
$ 15,000.00
$ 20,000.00
$ 25,000.00
$ 30,000.00
$ 35,000.00
$ 40,000.00
$ 45,000.00
Time-phase budget
Cost
Figure 5: Time-phase budget
(Source: Created by Author)
Part four:
4.1 Assumptions
The system will be quite beneficial for the customers
The team members will work effectively for finishing the project
The time that is utilized will be around 97 days for finishing the work
4.2 Project risks and management strategy
Risk
ID
Description Probability Impact Rate Assigned
To
Response
Strategy
Threat or
Opportunity
R1 Need of new
requirements
due to
technology
advancement
50 4 200 Resource
manager
This risk can
accepted as
will be
helpful I
creating
advance
system
.Opportunity
R2 Low
understandin
g of project
requirements
80 3 240 Project
managers
The risk can
be
prevented
by
appointing
experienced
project
manager
Threat
R3 Inappropriate
testing
90 4 360 Tester The testing
must be
conducted
properly by
Threat
chevron_up_icon