Development of Online Management System for Stud Farm: A Project
VerifiedAdded on 2021/06/17
|15
|2241
|40
Project
AI Summary
This project details the development of an online management system for a stud farm, encompassing various aspects of project management. It begins with the Measurable Organizational Value (MOV) assessment, evaluating the project's impact across operational, customer, financial, social, and strategic areas. The project scope is defined, including interface design, database development, and contract management, while also outlining elements out of scope, such as training. Assumptions, constraints, and a scope management plan are established. Resource planning covers people, technology, and facilities, alongside project milestones, activities, and budget estimations. Risk management identifies potential threats, such as design issues and lack of resources, and proposes mitigation strategies. The project emphasizes quality management through software testing and verification activities. The document concludes with an annotated bibliography and a closure checklist, offering a comprehensive overview of the project's lifecycle.

Student Name
ID Development of Online
management system for
Stud Farm
ID Development of Online
management system for
Stud Farm
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1. Part One:
1.1 MOV - Measurable Organisational Value
Area of Impact Rank (1 to 5)
Operational 1st
Customer 2nd
Financial 3rd
Social 4th
Strategy 5th
1.2 Value of the project plan
Delivered value are:
Better: The services of online breeding are provided is better in comparison to the services
that are provided by the company.
Faster: It is found that the management system within the organization is quite easy to
reach to the customers and the clients of the organization are benefitted due to reduction in the
response time.
2.3 Appropriate metric
Rank Impact Metrics Timeframe
1st Operational Efficiency of the
operation increases.
2 months
2nd Customer The customer’s
number will increase
due to the services as
well as benefits that is
delivered by the
organization.
3 months
3rd Financial The investment,
which is done, helps in
generating proper
financial outcome for
the project.
2 months
4th Social Social platform is used
for advertisement as
well as promoting the
services delivered by
the company.
1 month
5th Strategy It is necessary to
utilize proper
organizational
strategies for
managing the
customers.
2 months
1.1 MOV - Measurable Organisational Value
Area of Impact Rank (1 to 5)
Operational 1st
Customer 2nd
Financial 3rd
Social 4th
Strategy 5th
1.2 Value of the project plan
Delivered value are:
Better: The services of online breeding are provided is better in comparison to the services
that are provided by the company.
Faster: It is found that the management system within the organization is quite easy to
reach to the customers and the clients of the organization are benefitted due to reduction in the
response time.
2.3 Appropriate metric
Rank Impact Metrics Timeframe
1st Operational Efficiency of the
operation increases.
2 months
2nd Customer The customer’s
number will increase
due to the services as
well as benefits that is
delivered by the
organization.
3 months
3rd Financial The investment,
which is done, helps in
generating proper
financial outcome for
the project.
2 months
4th Social Social platform is used
for advertisement as
well as promoting the
services delivered by
the company.
1 month
5th Strategy It is necessary to
utilize proper
organizational
strategies for
managing the
customers.
2 months

2. Part Two:
2.1 Scope
The project scope are as follows:
Interface design
Database development
Breed registry development
Easy recording of services
Reviewing breeding services
Personalized communication facility
Developing database for marketing
Facility of contract management
Development of location facility
Facility of cost tracking
2.2 Out of Scope
The out scope of the project:
Facility of training is excluded from the project
Information about the project suppliers are excluded
2.3 Assumptions
The assumptions are:
All the project stakeholders will be present within the project meetings
The resources that are needed will quite easily available
The development of the entire project will get finished within the expected time.
2.4 Constraints
The constraints that are developed within this project are listed below:
Necessary resources will be present otherwise time of the project will exceed.
Proper quality required to be maintained otherwise both cost and time of the project
will increase
Project scope creep must be avoided.
2.5 Scope Management Plan
The project scope can be successfully managed including steps:
It is quite essential to determine the items that are associated with the project scope
The factors that generally helps in creating negative impact on the scope must be effectively
determined
It is quite essential to develop scope incorporation plan for retentive project quality.
Proper deployment of project scope in order to improve the organizational operation.
2.6 Resource Plan
People
2.1 Scope
The project scope are as follows:
Interface design
Database development
Breed registry development
Easy recording of services
Reviewing breeding services
Personalized communication facility
Developing database for marketing
Facility of contract management
Development of location facility
Facility of cost tracking
2.2 Out of Scope
The out scope of the project:
Facility of training is excluded from the project
Information about the project suppliers are excluded
2.3 Assumptions
The assumptions are:
All the project stakeholders will be present within the project meetings
The resources that are needed will quite easily available
The development of the entire project will get finished within the expected time.
2.4 Constraints
The constraints that are developed within this project are listed below:
Necessary resources will be present otherwise time of the project will exceed.
Proper quality required to be maintained otherwise both cost and time of the project
will increase
Project scope creep must be avoided.
2.5 Scope Management Plan
The project scope can be successfully managed including steps:
It is quite essential to determine the items that are associated with the project scope
The factors that generally helps in creating negative impact on the scope must be effectively
determined
It is quite essential to develop scope incorporation plan for retentive project quality.
Proper deployment of project scope in order to improve the organizational operation.
2.6 Resource Plan
People
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Technology
Hardware RAM, hard drive, laptop
Software Tools of designing, tools of
development
Network Server
Facilities
Facility of internet and extranet related infrastructure needs to be developed for providing
proper opportunity of system implementation to the employees of the organization.
Other
Travel Requirements Travelling expense is provided to the
organizational members.
Training Requirements Training manuals are delivered before
the arrangement of training sessions
Hardware RAM, hard drive, laptop
Software Tools of designing, tools of
development
Network Server
Facilities
Facility of internet and extranet related infrastructure needs to be developed for providing
proper opportunity of system implementation to the employees of the organization.
Other
Travel Requirements Travelling expense is provided to the
organizational members.
Training Requirements Training manuals are delivered before
the arrangement of training sessions
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Part three:
3.1 Project Milestones
Milestone Completion date
Milestone 1: Completion of project starting phase Mon 28-05-18
Milestone 2: Completion of planning phase Thu 07-06-18
Milestone 3: Completion of designing phase Thu 21-06-18
Milestone 4: Completion of development phase Thu 30-08-18
Milestone 5: Completion of testing phase Fri 14-09-18
Milestone 6: Completion of monitoring and control phase Wed 26-09-18
Milestone 7: Completion of closure phase Mon 01-10-18
3.2 Project activities
Figure 1: Project activities
3.1 Project Milestones
Milestone Completion date
Milestone 1: Completion of project starting phase Mon 28-05-18
Milestone 2: Completion of planning phase Thu 07-06-18
Milestone 3: Completion of designing phase Thu 21-06-18
Milestone 4: Completion of development phase Thu 30-08-18
Milestone 5: Completion of testing phase Fri 14-09-18
Milestone 6: Completion of monitoring and control phase Wed 26-09-18
Milestone 7: Completion of closure phase Mon 01-10-18
3.2 Project activities
Figure 1: Project activities

(Source: Created by Author)
3.3 Project resources
Figure 2: Project resources
(Source: Created by Author)
3.3 Project resources
Figure 2: Project resources
(Source: Created by Author)
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3.4 Time estimation
Figure 3: Time estimation
Figure 3: Time estimation
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

(Source: Created by Author)
3.5 Project budget
Figure 4: Project budget
(Source: Created by Author)
3.5 Project budget
Figure 4: Project budget
(Source: Created by Author)

3.6 Time phase budget
May 2018 June 2018 July 2018 August
2018
September
2018
October
2018
$ 0.00
$ 5,000.00
$ 10,000.00
$ 15,000.00
$ 20,000.00
$ 25,000.00
$ 30,000.00
$ 35,000.00
$ 40,000.00
$ 45,000.00
Cost
Cost
Figure 5: Time-phase budget
(Source: Created by Author)
Part four:
4.1 Assumptions
The assumptions are:
All project stakeholders will be present within the project meetings
The resources that are needed will quite easily available
The development of project will get over in the expected time.
4.2 Project risks and management strategy
Risk
ID
Description Probability Impact Rate Assigned
To
Response
Strategy
Threat or
Opportunity
R1 Inappropriate
design: The
design for the
project is not
made
properly then
it generally
creates
design issues.
80% 4 320 Technical
engineer
The risk
related with
design issues
can be
prevented by
designing
the
prototype of
the system
properly.
Threat
R2 Lack of
management
: If proper
strategies
related with
85% 5 425 Human
resource
manager
The risks
that is
associated
with
management
Threat
May 2018 June 2018 July 2018 August
2018
September
2018
October
2018
$ 0.00
$ 5,000.00
$ 10,000.00
$ 15,000.00
$ 20,000.00
$ 25,000.00
$ 30,000.00
$ 35,000.00
$ 40,000.00
$ 45,000.00
Cost
Cost
Figure 5: Time-phase budget
(Source: Created by Author)
Part four:
4.1 Assumptions
The assumptions are:
All project stakeholders will be present within the project meetings
The resources that are needed will quite easily available
The development of project will get over in the expected time.
4.2 Project risks and management strategy
Risk
ID
Description Probability Impact Rate Assigned
To
Response
Strategy
Threat or
Opportunity
R1 Inappropriate
design: The
design for the
project is not
made
properly then
it generally
creates
design issues.
80% 4 320 Technical
engineer
The risk
related with
design issues
can be
prevented by
designing
the
prototype of
the system
properly.
Threat
R2 Lack of
management
: If proper
strategies
related with
85% 5 425 Human
resource
manager
The risks
that is
associated
with
management
Threat
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

management
are not
utilized then
it will be quite
challenging to
finish the
project.
can be
solved by
utilizing
proper
strategies.
R3 Poor quality
of materials:
If the
resources
that are used
are of poor
quality the
quality
related
challenges
occurs.
80 4 320 Quality
analyst
The risks can
be
prevented by
utilizing
proper
quality of
resources
within the
project.
Threat
R4 Lack of
proper
resources: If
the resources
of the project
are not in
proper
appropriate
for finishing
the project.
70 4 280 Human
resource
manager
It is very
much
necessary to
estimate the
needed
resources for
preventing
the issue.
Opportunity
R5 Inappropriate
training
facility: As
training
facility is not
provided, the
team
members
faces lot of
difficulties in
managing the
project.
70 4 280 Trainer Proper
training
facility
arrangement
is necessary
for
mitigating
the issues
quite
effectively.
Threat
Part Five:
Statement on project quality
The quality of the project “development of stud farm management system” is managed
successfully by undertaking number of steps that are listed below:
Focussing on quality: It is quite necessary to arrange proper meetings on a weekly basis for
making sure that proper quality is maintained.
are not
utilized then
it will be quite
challenging to
finish the
project.
can be
solved by
utilizing
proper
strategies.
R3 Poor quality
of materials:
If the
resources
that are used
are of poor
quality the
quality
related
challenges
occurs.
80 4 320 Quality
analyst
The risks can
be
prevented by
utilizing
proper
quality of
resources
within the
project.
Threat
R4 Lack of
proper
resources: If
the resources
of the project
are not in
proper
appropriate
for finishing
the project.
70 4 280 Human
resource
manager
It is very
much
necessary to
estimate the
needed
resources for
preventing
the issue.
Opportunity
R5 Inappropriate
training
facility: As
training
facility is not
provided, the
team
members
faces lot of
difficulties in
managing the
project.
70 4 280 Trainer Proper
training
facility
arrangement
is necessary
for
mitigating
the issues
quite
effectively.
Threat
Part Five:
Statement on project quality
The quality of the project “development of stud farm management system” is managed
successfully by undertaking number of steps that are listed below:
Focussing on quality: It is quite necessary to arrange proper meetings on a weekly basis for
making sure that proper quality is maintained.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Conducting proper software tests: Proper software tests must be conducted for making sure
that proper quality is maintained within the project.
Safeguarding the entire time of testing: The time of testing should not be cut and it must
be properly done for analyzing that the project development is done properly.
Buying software packages in order to ensure quality: Software solutions needs to be
purchased by the organizations for ensuring that proper quality of the project is maintained.
A set of verification activities
Verification Activity When?
External audits The External audits are
accomplished on the suppliers after
the delivery of the resources.
End product testing Product testing is performed in the
last phase of the project.
Testing on software and software Testing is done on resources before
utilizing them in the project
development.
A set of validation activities
Validation Activity When?
Proceeding to approval This is done before initiation of the
project.
Finish working This is performed after the entire
project is finished.
Development of activities In the planning phase of the project.
that proper quality is maintained within the project.
Safeguarding the entire time of testing: The time of testing should not be cut and it must
be properly done for analyzing that the project development is done properly.
Buying software packages in order to ensure quality: Software solutions needs to be
purchased by the organizations for ensuring that proper quality of the project is maintained.
A set of verification activities
Verification Activity When?
External audits The External audits are
accomplished on the suppliers after
the delivery of the resources.
End product testing Product testing is performed in the
last phase of the project.
Testing on software and software Testing is done on resources before
utilizing them in the project
development.
A set of validation activities
Validation Activity When?
Proceeding to approval This is done before initiation of the
project.
Finish working This is performed after the entire
project is finished.
Development of activities In the planning phase of the project.

Part Six:
a. Annotated bibliography
Refer to appendices
b. Develop a closure checklist
Closure checklist Checklist options
Is testing finished? Yes
Approval and review of documents finished ? Yes
Requirements Traceability Matrix been
checked?
No
Closure of the risks are done? Yes
Is project handover completed ? Yes
Training completed? No
c. Develop a project evaluation
Evaluation Criteria Option
Is project plan feasible? Yes No
Does the project design is feasible? Yes No
Does the resources and cost are within the scope of the project? Yes No
Does project get over within the budget? Yes No
a. Annotated bibliography
Refer to appendices
b. Develop a closure checklist
Closure checklist Checklist options
Is testing finished? Yes
Approval and review of documents finished ? Yes
Requirements Traceability Matrix been
checked?
No
Closure of the risks are done? Yes
Is project handover completed ? Yes
Training completed? No
c. Develop a project evaluation
Evaluation Criteria Option
Is project plan feasible? Yes No
Does the project design is feasible? Yes No
Does the resources and cost are within the scope of the project? Yes No
Does project get over within the budget? Yes No
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 15
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.