BSBPMG522 AT2 Task 2.3: Project Status Report for Superior Implements

Verified

Added on  2023/04/20

|3
|448
|92
Report
AI Summary
This document presents a project status report for a renovation project at Superior Implements (SIM Co.), as of April 30, 2019. The report details the project's progress, which is 87% complete, with all major phases (Initialization, Planning, and Renovation) completed and the Closure phase at 46%. It includes a summary of deliverables and milestones, their planned and actual completion dates, and their current status. A budget status section outlines approved and actual expenditures, variances, and remaining budget. The report also provides a work breakdown structure (WBS) indicating tasks completed during the last period and those planned for the next, specifically focusing on the Closure phase and integration management. The report is a comprehensive overview of the project's financial and operational status, demonstrating the use of project management principles to monitor progress and identify areas for improvement.
Document Page
TASK 2.3 STATUS REPORT
Project Status Summary Percent Complete of total project:
87%
The status date for the project status report is 4/30/19 and the work completed is
87% till date. All the major project works has been completed till date and only the
closure phase is left for achievement. The Initialization Phase, Planning Phase, and
Renovation Phase has been completed 100% and the closure phase is 46% for
completion. The project status report would imply the formation of the innovative
analysis of the project.
Deliverables and Milestones
Deliverable WBS # Planned
Date
Actual
Date
Status
Letters 1.3 1/28/19 1/28/19 Completed
Cost Estimation 2.2 1/0/19 1/0/19 Completed
Renovation works 3.0 2/1/19 2/1/19 Completed
Integration 4.2 5/13/19 - Yet to start
Milestone WBS # Planned
Date
Actual
Date
Status
Project kick off 1.4 1/31/19 1/31/19 Completed
Approval of the plan 2.4 1/30/19 1/30/19 Completed
Completion of the renovation 3.10 4/12/19 4/12/19 Completed
Closed 4.3 5/20/19 - Yet to start
BSBPMG522_AT2_Task2.3_StatusReport
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Budget Status
Budget Status
Approved Budget Planned
Expenditures to Date
Actual
Expenditures to
Date
Variance
(planned –
actual)
$60000.00 $55000.00 $56000.00 -$1000.00
Planned Remaining
Budget
Actual Remaining
Budget
Variance
(planned –
actual)
$5000.00 $4000.00 $1000.00
Additional $ needed (if required) $1000.00
Work Completed During Last Period
WBS Task Name % Complete
0 Renovation of head office of Superior Implements (SIM Co.) 87%
1 Initialization Phase 100%
1.1 Analysis of the requirements 100%
1.2 Finalizing the works required in the Head Office 100%
1.3 Letter to sponsor for approval 100%
1.4 Project kick off 100%
2 Planning Phase 100%
2.1 Selection of Plan methodology 100%
2.2 Schedule development and Cost estimation 100%
2.3 Developing plan for the project 100%
2.4 Approval of the plan 100%
3 Renovation Phase 100%
3.1 Clearing of the Kitchen and Bathroom 100%
3.2 Fixing of the flooring 100%
3.3 Washing the house 100%
3.4 Bathroom Fixation 100%
3.5 Installing wash basin 100%
3.6 Painting the Head Office 100%
3.7 Installing new equipment 100%
3.8 Furniture fixation 100%
3.9 Change of drapes and curtains 100%
3.10 Completion of the renovation 100%
4 Closure 46%
4.1 Evaluation of the implementation 60%
BSBPMG522_AT2_Task2.3_StatusReport
Document Page
Work Planned For Next Period
WBS Task Name % Complete
4 Closure 46%
4.1 Evaluation of the implementation 60%
4.2 Integration Management 0%
4.3 Closed 0%
Project Manager’s Name: ____________________________________
Date: / / 20
BSBPMG522_AT2_Task2.3_StatusReport