COIT20248: Information Systems Analysis and Design Report, 2018

Verified

Added on  2023/05/30

|12
|2485
|230
Report
AI Summary
This report analyzes the development of an information system for the charitable organization "Go Help Me," which seeks to improve its crowdfunding efforts. The report details the approach to systems development, including client portals, automatic payment gateways, and online customer chat support. Functional and non-functional system requirements are outlined, followed by a cost-benefit analysis demonstrating a project ROI of approximately 0.8898. A project schedule, including WBS and Gantt charts, is presented to illustrate project timelines and task management. The report also explores system information requirement investigation techniques, such as personal interviews, monthly system testing, and monitoring, to ensure the system meets organizational needs. The conclusion reflects on the benefits of the new system, emphasizing improved online operations and successful achievement of organizational goals.
tabler-icon-diamond-filled.svg

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
COIT 20248: Information Systems Analysis and Design
Term 3, 2018
Assessment 1 - Systems Development
Lecturer: Lecturer Name
Tutor: Tutor Name
Prepared by:
Student Name
Student Number
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Executive Summary
The paper mainly reflects on the organization “Get Help Me” is one of the charitable organizations
that helps people as well as needy with the procedure of crowdfunding. It is identified that the
organization uses manual system for getting funds and therefore faces lot of problems. In order to
mitigate the issues, the organization generally wants to develop an appropriate information
system. The paper elaborates the approaches of system development as well as system
requirements. In addition to this, proper cost benefit analysis as well as project schedule is mainly
developed. In addition to this, the paper also discusses the techniques of system investigation in
order to analyze the methods as well as techniques that are mainly utilized for analyzing the system.
Page 1
Document Page
Table of Contents
1. Introduction.......................................................................................................................................2
2. Approach to Systems Development..................................................................................................2
3. Systems Requirements......................................................................................................................2
4. Project Cost Benefit Analysis.............................................................................................................3
5. Project Schedule................................................................................................................................6
6. System Information Requirement Investigation Techniques.............................................................7
7. Reflections and Conclusions..............................................................................................................8
Page 2
Document Page
1. Introduction
The paper mainly reflects on a charitable organization named “Go Help Me” which is
mainly run by a group of volunteers as well as chairperson of the organization. It is found
that the organization generally wants to engage within a crowd funding event in order to
raise funds for treatment of ill child, for destroying fire as well as for single parent. It is
identified that the organization mainly uses manual system in order to raise money however
utilization of manual system creates number of issues as well as challenges. It is found that
for resolving the issues, the organization needs to successfully develop proper information
system.
The project objectives are generally elaborated below:
To develop an information system
To provide proper online facility of donating money
To resolve the challenges that are mainly associated with the manual system
2. Approach to Systems Development
It is identified that before developing an information system for an organization “Go
Help Me” it is very much necessary for the organization to determine the different needs of
the system. The various features as well as requirements that are needed within the system
are generally illustrated below:
Clients portal: It is found that it is very much significant to have proper portal for the
clients of the organization such that they can be able to easily donate money online and can
be able to track their payment contribution in the past (Chen and Shen 2015). Moreover, the
clients can also be able to receive proper receipt for donation and yearly statement of the
contribution.
Automatic payment gateway: Automatic payment gateway is generally required by
the organization so that they can be able to donate money online and can easily get the
receipt for the payment procedure.
Online customer chat support: Online chat support system must be there so that
the staff does not always need to be available for answering the phone class as well as
messages in order to note the details of the tax voices (Polivka 2015).
It is identified that rapid application system development method is generally
utilized in for the development of an information system for “Go Help Me” which is one of
the charitable organizations (Kerzner and Kerzner 2017). This method is generally selected in
order to develop the information system as the process of prototyping is mainly utilized in
order to properly design as well as test the various features of the project prototype that
are generally mentioned. After the completion of the testing, it is found that the entire
version of the system will be developed quite successfully.
Page 3
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
3. Systems Requirements
The functional requirements of the new information system are generally elaborated
below:
Functional requirements Role in the system
Enrolment of database It is found that the individuals who generally
requires support from the organization
needs to enrol their name within the
database so that the organization can be
able to provide proper support.
Customer service Proper facility of online chat to the
customers must be provided for resolving
the challenges and issues which are
associated with taking calls of the clients 24
hours.
Automatic payment gateway It is found that automatic payment gateway
is generally required within the organization
so that the clients will be able to pay the
amount of money online.
The non-functional requirements of the new information system are generally
elaborated below:
Non-functional requirements Role in the system
Facility of downloading the contents that
are accessed
It is found that by utilizing this function, the
users can be able to download content
including the consolidated statement or
account statement.
Payment security It is found that proper security of the money
must be present while transferring money
from the bank account so that the clients
does not face any challenges or issues.
Data and history tracking It is identified that with the help of the new
information system, the clients are capable
of tracking the data as well as history of their
contribution quite easily. In addition to this,
they also use this feature in order to track
the amount of money that they have
contributed in a year with the help of yearly
statement.
4. Project Cost Benefit Analysis
Cost benefit analysis considered as the significant business processes that is mainly
used for analyzing the decisions. The people who are associated with the project generally
sums the benefits that is gained after the project implementation for analyzing the
Page 4
Document Page
feasibility of the project financially (Kerzner 2017). It is identified that the cost benefit
analysis which is generally created for the information system development helps in
reflecting that project ROI will be around 0.8898. The cost benefit analysis is mainly
analyzed with the help of the calculation that is generally done for determining the project
feasibility. It is found that the entire calculation that are generally done for analyzing the
benefit is reflected in the below table.
Economic Feasibility Analysis for " Go Help
Me"
Cost Benefit Analysis
Report
Year of
Project
year 0 year1 year 2 year 3 year 4 year 5 TOTALS
Net economic
benefit $ -
$
78,000.0
0
$
78,000.0
0
$
78,000.0
0
$
78,000.0
0
$
78,000.0
0
Discount Rate
8% 1
0.92592
5926
0.857338
82
0.79383
2241
0.73502
9853
0.68058
3197
PV Of
Benefits $0
$
72,222.2
2
$
66,872.4
3
$
61,918.9
1
$
57,332.3
3
$
53,085.4
9
NPV of all
BENEFITS $0
$
72,222.2
2
$
1,39,094.
65
$
2,01,013
.57
$
2,58,345
.89
$
3,11,431
.38
$
3,11,431
.38
One Time
Costs
$1,25,0
00.00
Recurring
Costs $ -
$
9,750.00
$
9,750.00
$
9,750.00
$
9,750.00
$
9,750.00
Discount Rate
8% 1
0.92592
5926
0.857338
82
0.79383
2241
0.73502
9853
0.68058
3197
PV Of
Recurring
Costs
$
9,027.78
$
8,359.05
$
7,739.86
$
7,166.54
$
6,635.69
Page 5
Document Page
NPV Of All
Costs
$1,25,0
00.00
$
1,34,027
.78
$
1,42,386.
83
$
1,50,126
.70
$
1,57,293
.24
$
1,63,928
.92
$
1,63,928
.92
Overall NPV
$
1,47,502
.46
Overall ROI = (Overall NPV / NPV Of
All Costs 0.90
Break-Even
Analysis
Yearly NPV
Cash Flow $ -
$
63,194.4
4
$
58,513.3
7
$
54,179.0
5
$
50,165.7
9
$
46,449.8
0
Overall NPV
Cash Flow
$1,25,0
00.00
$
(61,805.
56)
$
(3,292.18
)
$
50,886.8
7
$
1,01,052
.66
$
1,47,502
.46
Project break-even occurs between
years 1 and 2
Use 1st year of positive cash flow to calculate
break-even fraction
(15,162.74-
15,045.70/15,162.74) = 1.056
Table 1: Cost-benefit analysis
Page 6
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
5. Project Schedule
FIGURE 1: WBS
Page 7
Document Page
FIGURE 2: GANTT CHART
It is identified that the WBS is considered as the hierarchical structures which is generally
used in order to reflect the structure of the entire project and how the work that is related with the
project can be executed. Moreover, it is one of the organized views with which the work of the
project can be easily identified (Joslin and Muller 2015). On the other hand, it is found that Gantt
chart is reflected as the project sequential view which mainly showcase the entire work of the
project is planned and how it will be successfully completed over the assumed time period. In
addition to this, it is identified that the project utilizes both the WBS as well as Gantt chart for
developing the information system quite successfully so that the needs of the organization can be
met easily.
It is found that as the system requirements as well as goals are properly understood, the
project schedule that is generally created is very much reasonable. The project schedule is
considered to be reasonable as it will be helpful in executing the information system successfully by
meeting the objectives as well as goals of the project.
Page 8
Document Page
6. System Information Requirement Investigation Techniques
The people who are generally involved with the work of the project are generally listed
below:
Project manager
Developer
IT manager
Supervisor
Trainer
Finance manager
System analyst
System investigation technique is mainly utilized in order to investigate the work that is needed to
be done within the entire system by determining the challenges as well as issues which generally can
create disruption within the entire system Ricci, Rokach and Shapira 2015). It is found that there are
number of system investigation techniques that generally can be used. The system investigation
techniques include:
Personal interview
Monthly system testing
Monitoring
The justification for the different useful investigation techniques are generally elaborated below:
Personal interview: It is identified as one of the best methods for investigating the system. It is
found that with the help of this method, the staffs are generally interviewed for gathering
information about the problems which are mainly related with the operation of the new information
system.
Monthly system testing: It is considered as one of the methods that is used for testing the
system so that the challenges as well as issues of the system can be identified quite easily (Chen et
al., 2015).
Monitoring: Monitoring is one of the continuous procedures that is used for monitoring the
operation of the entire system for making sure that the entire system is working properly for
meeting the needs as well as requirements of the organization.
7. Reflections and Conclusions
I have identified that the development of information system is mainly done for mitigating
the challenges as well as issues that are associated with the organization in crowdfunding. With the
help of the upgraded information system, the organization can reach to a greater number of clients
Page 9
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
and can be capable of managing all its operations online. Moreover, I have analyzed that as the
project manager keeps track on every activity or task that is performed, the entire project will be
completed on time.
From the entire report, it can concluded that the project development for the
charitable organization is very much beneficial as it not only assists in making all the
operations of the organization online but also assist in achieving the needs and requirement
of the organization successfully. In addition to this, it is found that proper cost benefit
analysis is generally conducted in order to analyze the return on investments. Moreover,
proper schedule for the project is developed such that the work of the project can be
completed quite successfully in the expected time.
Page 10
Document Page
References
Chen, J. and Shen, X.L., 2015. Consumers' decisions in social commerce context: An
empirical investigation. Decision Support Systems, 79, pp.55-64.
Chen, X., Zhang, Z., Chen, H.H. and Zhang, H., 2015. Enhancing wireless information and
power transfer by exploiting multi-antenna techniques. IEEE communications
Magazine, 53(4), pp.133-141.
Joslin, R. and Müller, R., 2015. Relationships between a project management methodology
and project success in different project governance contexts. International Journal of Project
Management, 33(6), pp.1377-1392.
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
Kerzner, H., 2017. Project management metrics, KPIs, and dashboards: a guide to measuring
and monitoring project performance. John Wiley & Sons.
Polivka, G.B., Laureate Education Inc, 2015. System and method for collaborative
development of online courses and programs of study. U.S. Patent 8,934,832.
Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking
project management performance and project success. International journal of project
management, 32(2), pp.202-217.
Ricci, F., Rokach, L. and Shapira, B., 2015. Recommender systems: introduction and
challenges. In Recommender systems handbook (pp. 1-34). Springer, Boston, MA.
Sánchez, M.A., 2015. Integrating sustainability issues into project management. Journal of
Cleaner Production, 96, pp.319-330.
Sears, S.K., Sears, G.A., Clough, R.H., Rounds, J.L. and Segner, R.O., 2015. Construction
project management. John Wiley & Sons.
Todorović, M.L., Petrović, D.Č., Mihić, M.M., Obradović, V.L. and Bushuyev, S.D., 2015.
Project success analysis framework: A knowledge-based approach in project
management. International Journal of Project Management, 33(4), pp.772-783.
Too, E.G. and Weaver, P., 2014. The management of project management: A conceptual
framework for project governance. International Journal of Project Management, 32(8),
pp.1382-1394.
Page 11
chevron_up_icon
1 out of 12
circle_padding
hide_on_mobile
zoom_out_icon
logo.png

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]