This report, addressing MAN6325 Assignment 1, presents a comprehensive business case and project plan for implementing a training program at 'Best Care' in response to new legislation. The executive summary highlights the expected six-week timeline and $10,000 budget, emphasizing the application of PRINCE2 methodology for effective project delivery. The report details the rationale for the training, expected benefits like employee motivation, and potential risks such as low attendance or ineffective training materials. A project plan outlines a 65-day schedule with phases for planning, execution, and project closure, including budget estimations for each task. The benefits review plan establishes objectives for successful legislation implementation, and the report concludes with a bibliography of relevant sources.

Running head: MAN6325 ASSIGNMENT 1
MAN6325 Assignment 1
Name of the Student
Name of the University
Author Note
MAN6325 Assignment 1
Name of the Student
Name of the University
Author Note
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1
Running head: MAN6325 ASSIGNMENT 1
Table of Contents
1. Executive Summary.....................................................................................................................2
2. Business Case..............................................................................................................................2
2.1 Description and Rationale......................................................................................................2
2.2 Expected Benefits..................................................................................................................2
2.3 Potential Risks.......................................................................................................................3
2.4 Product Risks.........................................................................................................................3
2.5 Ethical Issues.........................................................................................................................3
3. Project Plan..................................................................................................................................5
3.1 Schedule.................................................................................................................................5
3.2 Budget....................................................................................................................................6
4. Benefits Review Plan...................................................................................................................7
5. Bibliography................................................................................................................................9
Running head: MAN6325 ASSIGNMENT 1
Table of Contents
1. Executive Summary.....................................................................................................................2
2. Business Case..............................................................................................................................2
2.1 Description and Rationale......................................................................................................2
2.2 Expected Benefits..................................................................................................................2
2.3 Potential Risks.......................................................................................................................3
2.4 Product Risks.........................................................................................................................3
2.5 Ethical Issues.........................................................................................................................3
3. Project Plan..................................................................................................................................5
3.1 Schedule.................................................................................................................................5
3.2 Budget....................................................................................................................................6
4. Benefits Review Plan...................................................................................................................7
5. Bibliography................................................................................................................................9

2
Running head: MAN6325 ASSIGNMENT 1
1. Executive Summary
Imposing new legislations within the existing processes and laws of the organization is
capable of affecting the overall functioning of the organization. This report emphasizes on the
issues and influences caused to the fiction organization ‘Best Care’ because of the introduction
of the new legislations within the existing system. The expected time and budget for the
implementation and training to the employees will be six weeks and $ 10,000. Application of the
PRINCE2 methodology will be helpful in delivering the proposed solution in an effective and
sequential manner considering every sector and aspect of the project. This report concludes that
new legislations is capable of affecting the overall functioning of the organization and its
processes however; proper planning and effective management can lead to the successful
deployment of the legislations resulting in the efficiency on the output of this imposing.
2. Business Case
2.1 Description and Rationale
The project will be needed for the accomplishment of the successful and efficient output
from the proposed solution as the proposed solution is training to the employees that will be
ensuring successful compliance within the existing system of the Best Care. The purpose of the
project will be to train to the employees about the new legislations; it’s functioning, benefits, and
how to accomplish them successfully. The training will assure that every individual connected
with the organization is capable of understanding the aspects related to the newly imposed
training.
Running head: MAN6325 ASSIGNMENT 1
1. Executive Summary
Imposing new legislations within the existing processes and laws of the organization is
capable of affecting the overall functioning of the organization. This report emphasizes on the
issues and influences caused to the fiction organization ‘Best Care’ because of the introduction
of the new legislations within the existing system. The expected time and budget for the
implementation and training to the employees will be six weeks and $ 10,000. Application of the
PRINCE2 methodology will be helpful in delivering the proposed solution in an effective and
sequential manner considering every sector and aspect of the project. This report concludes that
new legislations is capable of affecting the overall functioning of the organization and its
processes however; proper planning and effective management can lead to the successful
deployment of the legislations resulting in the efficiency on the output of this imposing.
2. Business Case
2.1 Description and Rationale
The project will be needed for the accomplishment of the successful and efficient output
from the proposed solution as the proposed solution is training to the employees that will be
ensuring successful compliance within the existing system of the Best Care. The purpose of the
project will be to train to the employees about the new legislations; it’s functioning, benefits, and
how to accomplish them successfully. The training will assure that every individual connected
with the organization is capable of understanding the aspects related to the newly imposed
training.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3
Running head: MAN6325 ASSIGNMENT 1
2.2 Expected Benefits
It will be helpful in motivating the employees and staffs of the Best care to adopt the new
legislation and accept it as a part of the organization that can be helpful in boosting the
operational activities of the organization. Training allows the staffs to look the matter from
different ways and from different perspective, and indulge in a program where several members
will express their point of view on the same context. A time taking process has not any benefit in
the current situation as the output can only be measured after successful accomplishment.
2.3 Potential Risks
There are numbers of risks associated with the development of a training program that
includes less number of employees attending program, escalation in the schedule, less effective
training materials, lack of contribution by the trainer, lack of formal contracting, and lack of
marketing and provision. Lack of contribution and dedication by the learner, no process drawing,
complexity, and poor planning are the possible cause those could possibly affect the deployment
of the training.
2.4 Product Risks
The deployment of training program in failure manner could limit the understanding of
the new imposed legislations and thus, possibly affect the overall execution of the project.
2.5 Ethical Issues
The proposed solution does not abide any law as, according to law everyone have the
right to information and employees are not bound with any restriction that will have to enter the
training program. PMI code of ethics does not bind any relation with the training program and
hence, the proposed solution has theoretically not any ethical issue. However; practically the
Running head: MAN6325 ASSIGNMENT 1
2.2 Expected Benefits
It will be helpful in motivating the employees and staffs of the Best care to adopt the new
legislation and accept it as a part of the organization that can be helpful in boosting the
operational activities of the organization. Training allows the staffs to look the matter from
different ways and from different perspective, and indulge in a program where several members
will express their point of view on the same context. A time taking process has not any benefit in
the current situation as the output can only be measured after successful accomplishment.
2.3 Potential Risks
There are numbers of risks associated with the development of a training program that
includes less number of employees attending program, escalation in the schedule, less effective
training materials, lack of contribution by the trainer, lack of formal contracting, and lack of
marketing and provision. Lack of contribution and dedication by the learner, no process drawing,
complexity, and poor planning are the possible cause those could possibly affect the deployment
of the training.
2.4 Product Risks
The deployment of training program in failure manner could limit the understanding of
the new imposed legislations and thus, possibly affect the overall execution of the project.
2.5 Ethical Issues
The proposed solution does not abide any law as, according to law everyone have the
right to information and employees are not bound with any restriction that will have to enter the
training program. PMI code of ethics does not bind any relation with the training program and
hence, the proposed solution has theoretically not any ethical issue. However; practically the
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4
Running head: MAN6325 ASSIGNMENT 1
employees might not be comfortable with the change and thus, they could impose the imposing
of new legislations.
CRT
Running head: MAN6325 ASSIGNMENT 1
employees might not be comfortable with the change and thus, they could impose the imposing
of new legislations.
CRT

5
Running head: MAN6325 ASSIGNMENT 1
Figure 1: CRT for Training program
(Source: Created by Author)
Running head: MAN6325 ASSIGNMENT 1
Figure 1: CRT for Training program
(Source: Created by Author)
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6
Running head: MAN6325 ASSIGNMENT 1
EC Diagram
Figure 2: New legislation imposition
(Source: Created by Author)
3. Project Plan
3.1 Schedule
Task Name Duration Start Finish
Training Program 65 days Mon 5/14/18 Fri 8/10/18
Phase 1: Planning 12 days Mon 5/14/18 Tue 5/29/18
Identification of the changes 3 days Mon 5/14/18 Wed 5/16/18
Identification of dissatisfaction 2 days Thu 5/17/18 Fri 5/18/18
Running head: MAN6325 ASSIGNMENT 1
EC Diagram
Figure 2: New legislation imposition
(Source: Created by Author)
3. Project Plan
3.1 Schedule
Task Name Duration Start Finish
Training Program 65 days Mon 5/14/18 Fri 8/10/18
Phase 1: Planning 12 days Mon 5/14/18 Tue 5/29/18
Identification of the changes 3 days Mon 5/14/18 Wed 5/16/18
Identification of dissatisfaction 2 days Thu 5/17/18 Fri 5/18/18
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7
Running head: MAN6325 ASSIGNMENT 1
identification of less
understandings 3 days Mon 5/21/18 Wed 5/23/18
identification of the volunteers 4 days Thu 5/24/18 Tue 5/29/18
Phase 2: Planning 41 days Wed 5/30/18 Wed 7/25/18
Venue selection 2 days Wed 5/30/18 Thu 5/31/18
Resource Selection 3 days Fri 6/1/18 Tue 6/5/18
Trainer appointment 1 day Wed 6/6/18 Wed 6/6/18
Roles and responsibilities of the
stakeholders 3 days Thu 6/7/18 Mon 6/11/18
Schedule estimation 4 days Tue 6/12/18 Fri 6/15/18
Budget estimation 4 days Mon 6/18/18 Thu 6/21/18
Approval 3 days Fri 6/22/18 Tue 6/26/18
Phase 3: Execution 4 days Wed 6/27/18 Mon 7/2/18
Motivating employees to
participate 3 days Tue 7/3/18 Thu 7/5/18
Meetings 2 days Fri 7/6/18 Mon 7/9/18
Training program 5 days Tue 7/10/18 Mon 7/16/18
Satisfaction level identification 7 days Tue 7/17/18 Wed 7/25/18
Phase 4: Project closing 12 days Thu 7/26/18 Fri 8/10/18
Documentation of the project
learning 5 days Thu 7/26/18 Wed 8/1/18
Project sign-off 7 days Thu 8/2/18 Fri 8/10/18
3.2 Budget
Task Name Duration Resource Names Cost
Training Program 61 days $41,280.00
Phase 1: Planning 12 days $5,760.00
Identification of the changes 3 days $0.00
Identification of 2 days Manager, Trainer $1,280.00
Running head: MAN6325 ASSIGNMENT 1
identification of less
understandings 3 days Mon 5/21/18 Wed 5/23/18
identification of the volunteers 4 days Thu 5/24/18 Tue 5/29/18
Phase 2: Planning 41 days Wed 5/30/18 Wed 7/25/18
Venue selection 2 days Wed 5/30/18 Thu 5/31/18
Resource Selection 3 days Fri 6/1/18 Tue 6/5/18
Trainer appointment 1 day Wed 6/6/18 Wed 6/6/18
Roles and responsibilities of the
stakeholders 3 days Thu 6/7/18 Mon 6/11/18
Schedule estimation 4 days Tue 6/12/18 Fri 6/15/18
Budget estimation 4 days Mon 6/18/18 Thu 6/21/18
Approval 3 days Fri 6/22/18 Tue 6/26/18
Phase 3: Execution 4 days Wed 6/27/18 Mon 7/2/18
Motivating employees to
participate 3 days Tue 7/3/18 Thu 7/5/18
Meetings 2 days Fri 7/6/18 Mon 7/9/18
Training program 5 days Tue 7/10/18 Mon 7/16/18
Satisfaction level identification 7 days Tue 7/17/18 Wed 7/25/18
Phase 4: Project closing 12 days Thu 7/26/18 Fri 8/10/18
Documentation of the project
learning 5 days Thu 7/26/18 Wed 8/1/18
Project sign-off 7 days Thu 8/2/18 Fri 8/10/18
3.2 Budget
Task Name Duration Resource Names Cost
Training Program 61 days $41,280.00
Phase 1: Planning 12 days $5,760.00
Identification of the changes 3 days $0.00
Identification of 2 days Manager, Trainer $1,280.00

8
Running head: MAN6325 ASSIGNMENT 1
dissatisfaction
identification of less
understandings 3 days Manager, Trainer $1,920.00
identification of the
volunteers 4 days Manager, Trainer $2,560.00
Phase 2: Planning 20 days $14,960.00
Venue selection 2 days Manager, Trainer,
Volunteers $1,760.00
Resource Selection 3 days Manager, Trainer,
Volunteers $2,640.00
Trainer appointment 1 day Manager, Trainer,
Volunteers $880.00
Roles and responsibilities of
the stakeholders 3 days Manager, Trainer,
Volunteers $2,640.00
Schedule estimation 4 days Manager, Trainer $2,560.00
Budget estimation 4 days Manager, Trainer $2,560.00
Approval 3 days Manager, Trainer $1,920.00
Phase 3: Execution 17 days $12,880.00
Motivating employees to
participate 3 days Manager, Trainer $1,920.00
Meetings 2 days Manager, Trainer,
Resources[1] $2,280.00
Training program 5 days Manager, Trainer,
Resources[1] $4,200.00
Satisfaction level
identification 7 days Manager, Trainer $4,480.00
Phase 4: Project closing 12 days $7,680.00
Documentation of the project
learning 5 days Manager, Trainer $3,200.00
Project sign-off 7 days Manager, Trainer $4,480.00
Running head: MAN6325 ASSIGNMENT 1
dissatisfaction
identification of less
understandings 3 days Manager, Trainer $1,920.00
identification of the
volunteers 4 days Manager, Trainer $2,560.00
Phase 2: Planning 20 days $14,960.00
Venue selection 2 days Manager, Trainer,
Volunteers $1,760.00
Resource Selection 3 days Manager, Trainer,
Volunteers $2,640.00
Trainer appointment 1 day Manager, Trainer,
Volunteers $880.00
Roles and responsibilities of
the stakeholders 3 days Manager, Trainer,
Volunteers $2,640.00
Schedule estimation 4 days Manager, Trainer $2,560.00
Budget estimation 4 days Manager, Trainer $2,560.00
Approval 3 days Manager, Trainer $1,920.00
Phase 3: Execution 17 days $12,880.00
Motivating employees to
participate 3 days Manager, Trainer $1,920.00
Meetings 2 days Manager, Trainer,
Resources[1] $2,280.00
Training program 5 days Manager, Trainer,
Resources[1] $4,200.00
Satisfaction level
identification 7 days Manager, Trainer $4,480.00
Phase 4: Project closing 12 days $7,680.00
Documentation of the project
learning 5 days Manager, Trainer $3,200.00
Project sign-off 7 days Manager, Trainer $4,480.00
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

9
Running head: MAN6325 ASSIGNMENT 1
WBS
Figure 3: WBS
(Source; Created by Author)
4. Benefits Review Plan
Objective developed for the developed project plan can be listed as follows:
To allow the implementation of the new legislations
Running head: MAN6325 ASSIGNMENT 1
WBS
Figure 3: WBS
(Source; Created by Author)
4. Benefits Review Plan
Objective developed for the developed project plan can be listed as follows:
To allow the implementation of the new legislations
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

10
Running head: MAN6325 ASSIGNMENT 1
To promote and motivate the employees to participate in the project
To developed an efficient and effective project
To allow smooth implementation of the new legislations
Current situation is that new legislation is replacing with the existing one and the
organization needs to set a path that can be effectively applied to the project in m manner to
allow the adoption of the effective training and practices that can enhance the feasibility of the
situation.
After the deployment of the project documentation, the project coordinator can assess the
final project.
Running head: MAN6325 ASSIGNMENT 1
To promote and motivate the employees to participate in the project
To developed an efficient and effective project
To allow smooth implementation of the new legislations
Current situation is that new legislation is replacing with the existing one and the
organization needs to set a path that can be effectively applied to the project in m manner to
allow the adoption of the effective training and practices that can enhance the feasibility of the
situation.
After the deployment of the project documentation, the project coordinator can assess the
final project.

11
Running head: MAN6325 ASSIGNMENT 1
5. Bibliography
Binder, J. (2016). Global project management: communication, collaboration and management
across borders. Routledge.
Joseph. Phillips, P. M. P., CBAP, I., & PMP, C. (2018). PMP Project Management Professional
Study Guide. McGraw-Hill Education.
Kerzner, H. (2018). Project management best practices: Achieving global excellence. John
Wiley & Sons.
Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
Lock, D. (2017). The essentials of project management. Routledge.
Ramazani, J., & Jergeas, G. (2015). Project managers and the journey from good to great: The
benefits of investment in project management training and education. International
Journal of Project Management, 33(1), 41-52.
Schwalbe, K. (2015). Information technology project management. Cengage Learning.
Svejvig, P., & Andersen, P. (2015). Rethinking project management: A structured literature
review with a critical look at the brave new world. International Journal of Project
Management, 33(2), 278-290.
Running head: MAN6325 ASSIGNMENT 1
5. Bibliography
Binder, J. (2016). Global project management: communication, collaboration and management
across borders. Routledge.
Joseph. Phillips, P. M. P., CBAP, I., & PMP, C. (2018). PMP Project Management Professional
Study Guide. McGraw-Hill Education.
Kerzner, H. (2018). Project management best practices: Achieving global excellence. John
Wiley & Sons.
Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
Lock, D. (2017). The essentials of project management. Routledge.
Ramazani, J., & Jergeas, G. (2015). Project managers and the journey from good to great: The
benefits of investment in project management training and education. International
Journal of Project Management, 33(1), 41-52.
Schwalbe, K. (2015). Information technology project management. Cengage Learning.
Svejvig, P., & Andersen, P. (2015). Rethinking project management: A structured literature
review with a critical look at the brave new world. International Journal of Project
Management, 33(2), 278-290.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 12
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.