In-Depth Analysis: Trans-Saharan Gas Pipeline Project Report

Verified

Added on  2023/06/04

|20
|6854
|394
Report
AI Summary
This report provides a comprehensive reflection on the Trans-Saharan Gas Pipeline mega project, which aimed to construct a natural gas pipeline between Nigeria and Algeria to diversify EU gas supplies. The project, initiated with agreements between the involved governments and a feasibility study, faced significant challenges including insufficient funding, security issues, and decision-making delays. The report delves into these complexities, highlighting gaps in risk assessment, budgeting, and stakeholder management. It explores opportunities for applying project and program management principles to improve the project's viability, focusing on procurement, risk, cost, and human resource management. The analysis also covers the complex business, organizational, commercial, and legal environments, along with stakeholder priorities and supply chain dynamics. Strategic risk management, time and cost control, change management, and governance aspects are discussed, concluding with recommendations for future improvements. The report emphasizes the need for better risk assessment, stakeholder engagement, and adaptive management strategies to navigate the project's inherent complexities and ensure its long-term stability and success.
Document Page
Trans-Saharan Mega Project Reflection Report
Trans-Saharan Mega Project Reflection
Report
1
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Trans-Saharan Mega Project Reflection Report
Executive Summary
A natural gas pipeline was to be constructed between Nigeria and Algeria for the diversification
of EU gas suppliers. The project was approved with the agreement signed between the two-
government followed by a feasibility study. The project begins with a route decided by three
governments and putting some funds for start. However, the project faced major issues during its
development such as lack of ability to gather sufficient funds, security issues affecting progress,
delays caused by decision authorities, and more. This report explores the case of the gas pipeline
project in depth and identifies various problems that the project had faced. It also identified
opportunities to explore project and project management so that the project that otherwise could
not be completed and is still facing issues could be helped with improvement in practices and
approach.
2
Document Page
Trans-Saharan Mega Project Reflection Report
Contents
Project and Program Management in Complex Mega Projects....................................................................5
1.1 Introduction.................................................................................................................................5
1.2 Gas Pipelines in the World..........................................................................................................5
1.3 Complexities................................................................................................................................5
1.4 Gap Analysis...............................................................................................................................6
1.5 Project Management Opportunities..............................................................................................6
1.6 Program Management opportunities............................................................................................7
Complex Business, Organizational and Commercial Environment.............................................................8
2.1 Nigerian Business Environment...................................................................................................8
2.2 Organizational Complexities.......................................................................................................8
2.3 Structural Complexities...............................................................................................................8
2.4 Institutional level relationship complexities.................................................................................9
2.5 Commercial and Legal complexities............................................................................................9
2.6 Project and Program management complexities........................................................................10
Stakeholder Priorities and Complexities....................................................................................................10
3.1 Stakeholder Management Problems, Issues and Challenges......................................................10
Optimum Bias...........................................................................................................................................11
Strategic Misrepresentation.......................................................................................................................11
Miscalculation of risks and value..............................................................................................................11
Phase wise complexities - Life Cycle Approach........................................................................................12
Supply Chain Management.......................................................................................................................13
8.1 Upstream Stakeholders..............................................................................................................13
8.2 Mid-Stream Stakeholders...........................................................................................................14
8.3 Downstream Stakeholders.........................................................................................................14
8.4 Supply Chain Stakeholder Matrix..............................................................................................14
Strategic Risk Management.......................................................................................................................15
9.1 Pipeline Security........................................................................................................................15
9.2 Environmental Impacts..............................................................................................................15
9.3 Cost and Time related risks........................................................................................................15
9.4 Long-term stability....................................................................................................................16
9.5 Global crisis...............................................................................................................................16
9.6 Quality Concerns.......................................................................................................................16
Time and Cost Control..............................................................................................................................16
Change Management.................................................................................................................................17
Governance................................................................................................................................................17
Conclusions...............................................................................................................................................17
Recommendations.....................................................................................................................................18
References.................................................................................................................................................19
3
Document Page
Trans-Saharan Mega Project Reflection Report
4
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Trans-Saharan Mega Project Reflection Report
Project and Program Management in Complex Mega Projects
1.1 Introduction
Construction of natural gas pipeline had been planned between Nigeria and Algeria for
diversifying EU gas supplies in 1970s and a memorandum was signed between the two
governments on 14th January 2002 (ESMAP, 2003). An agreement for feasibility study of the
project was signed with Penspen limited in 2005 and by September 2006, the project was found
to be feasible. On 3rd July 2009, an MOU was signed between Nigeria, Algeria, and Niger
governments for the construction of the pipeline. A 4,128 kilometers pipeline was planned
connecting Niger to Hassi R Mel with 1,037 kms spread in Nigeria, 841 kilometers in Niger and
2,310 kilometers in Algeria. The annual capacity planned for the pipeline was 30 million cubic
meters and it was expected to become operational by 2015. However, considering the
complexities at global levels, the project ran into many problems and complexities that hampered
the project progress. This report would explore these complexities and problems and would
apply project and program management principles to the case to identify scope for their
application to the project for improvement (Suzuki & Morikawa, 2004).
1.2 Gas Pipelines in the World
A gas pipeline consists of exploration, production, delivery, transmission, and distribution of gas
supplies. The demand for gas has increased across world over past few decades. However, EU-
27 countries have only 300 billion cubic meters of own capacity which is unable to satisfy the
huge demand which has to be covered from other regions including 115 bcm from Russia, 90
bcm from Norway, and 50 bcm from Algeria. The gas pipeline imports across EU regions are
spread in northern, south-western, south-eastern, and Baltic integration regions. Several new
pipeline construction projects have shaped in recent years to meet the increased demand for
natural gas. Some of the projects include Green Stream between Italy and Libya, Balgzand
between UK and Netherlands, Transmed II between Tunisia, Algeria, and Italy, TGI pipeline
between Greece and Italy, and Medgas between Spain and Algeria (Boon von Ochssée, 2010).
1.3 Complexities
The project was faced with many complexities that are required to be addressed. These include:
5
Document Page
Trans-Saharan Mega Project Reflection Report
The feasibility report of the project could not appropriately estimate the possibilities of
risks that could make the project unviable in future and thus, re-feasibility test was to be
conducted that made the project appear not viable at the later stage when partial
development had already started.
The project involved three different counties participating in it and the number of
stakeholders, decision makers, and their requirements also differed which made it
complicated causing delays in decision making.
The chosen route for the construction did not prove out to be safe as it faced vandalism
and terrorist activities. The workers had to be kept safe by deploying extra security
practices that escalated the cost of the project drastically and also resulted in the loss of
confidence among major stakeholders.
The initial estimation of cost was proved to be inaccurate as there was also rise in the
infrastructure, supplies, and contract costs on the project resulting into cost fluctuations
which further escalated the issues of cost.
There was a lack of funding as the project was unable to fetch the remining funds from
sponsors after the complexities suffered the project in the long run
1.4 Gap Analysis
On the project were found several gaps that resulted into major problems for the project. The
first gap was the lack of visibility and consideration of risks on the project. Safety for instance
had compromised which affected the cost of the management because of several attacks
happening in the Delta region at the time of the development of the project. Another major was
found in the budgeting and finance management. The project was unable to gather sufficient
funds to continue with the project.
1.5 Project Management Opportunities
The project has a number of different stakeholders coming from different regions and had
different perspectives and interests which cause major issues on the project. With the use of
appropriate project management approaches and principles, these stakeholders could be managed
better. Also, other issues like management of supplier organizations and contracts would be
6
Document Page
Trans-Saharan Mega Project Reflection Report
better managed using project management practices. A number of knowledge management areas
defined in the PMBOK guide can help here including:
Procurement Management: the pipeline construction project is largely affected by the suppliers
and vendors supplying on contracts. The fluctuations in material pricing could lead to increase in
the most of reports and thus, escalated the costs beyond the initial estimated budget. Also,
several different suppliers and contractors were involved on the project that added to the
complexities in execution. With the use of procurement management principles and practices, the
project could handle procurement system more effectively (Serova, 2015).
Risk Management: the project faced a lot of different risks that were not accurately estimated
such as position from local communities, vandalism from local groups, and terrorist activities in
the delta region. Also, the feasibility of the project was affected which resulted into lack of
funds. With the use of risk management practices and principles, these risks could be assessed
better and appropriate action plan can be taken (Obi & Rustad, 2011).
Cost management: The actual costs of the project was found to be much higher than the initial
estimation because of several issues cropping up such as security problems and raw material
price fluctuations. Cost management planning could be used on the project to tackle these
problems.
Human resource Management: As the project involved a large number of works and
employees working from different cultures together, it becomes essential that the workforce is
effectively managed as that would determine the possibilities of the success of the project. With
the use of human resource management plan and management, the project outcomes could be
improved with better management of engagement of people working on the project (Ushie,
2013).
1.6 Program Management opportunities
A mega project is a great size and it can be manager well if it is seen as a group of smaller
projects that are managed by different teams. The delta pipeline construction project involved a
number of different departments and countries working on the project. A number of ministries
can be divided into multiple projects for each ministry to handle and the who project could be
handled using a project management approach. Chances of failure can be reduced this way as
7
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Trans-Saharan Mega Project Reflection Report
individuals’ teams would be working on individual parts of the project thereby reducing
complications that would otherwise happen between different decision makers with different
interests (BOOM, 2009).
Complex Business, Organizational and Commercial Environment
2.1 Nigerian Business Environment
US has an oil and gas boom after it has discovered many new reserves of shale deposits which
has resulted into the reduction of natural gas prices which affected the viability of the project. A
revalidation of the earlier feasibility study had to be done that reflected uncertainty arising in
European market for oil and gas (Mandil, 2007).
2.2 Organizational Complexities
Key stakeholders who were the part of the trans-Saharan pipeline project were Sonatrach,
Government of Nigeria, Nigeria's Infrastructure, Concession, and Regulatory commission,
Nigeria National oil corporation, and Niger national oil company. A public Private partnership
was reached between the government and private bodies involved in the project (Mayaki, 2015).
Sonatrach that was one of the sponsors of the project was planning three projects at the time of
the delta project including OK LNG, brass ENI, and Escravos GTL. All these projects needed
significant investments to be made in millions. Thus, the company had internal conflicts within
their programs leaving them less inclined to give more funds to the mega project.
2.3 Structural Complexities
There can be several variables contributing to structural complexities in a pipeline construction
project. In the case of the Saharan Gas Pipe line project, following challenges were faced:
Land related complexities: Pipeline construction ideally happens on a leveled ground but with
the highly unleveled route selected for the triparty project, levelling had to be done for a lot of
area of construction which was a cost and time consuming. This can increase the soil movement
8
Document Page
Trans-Saharan Mega Project Reflection Report
in the area causing problems. Also, because of a lot of levelling needed, the construction width
also increased.
2.4 Institutional level relationship complexities
Different partners of the project had differences of opinion and interests. A prevailing delay in
liquefaction on Nigerian projects had reduced the confidence of TSGP partners. Also, Sonatrarch
was complaining on the amount reserves available with NNPC. A number of meeting discussions
hinted on the lack of sufficient networks such that NNPC planned for constructing a new
network. Niger having no own gas infrastructure needed to use this network and pay the royalties
against. Nigeria had existing pipelines that could be used but they did not guarantee any safety.
The problems were escalated by inability of finding the funder for the construction of the new
pipeline. By 2009, the viability of the project was to be tested again with another feasibility
analyzed based on the current situations.
2.5 Commercial and Legal complexities
A number of legal formalities and acts had to be taken care of on the project that regulated the
legal and commercial environment. The petroleum act 1969 has defined rules for managing
petroleum projects. It also defines penalties for utilization of gas and gas flaring. The act
exempts the gas from royalties and gave rights to the government for taking gas for free.
Association gas reinjection act. 1979 mandates companies to submit the plan for reinjection and
utilization of gas to government (Centre for Environmental Rights, 2014). Gas utilization
includes power plant, natural gas, fertilization plant, gas transmission, and distribution. A written
permission was needed before gas flaring project can happen. All these project requirements add
to legal hassles which was time consuming as the project involved legal ad commercial
regulations from three different countries making the complication higher than a single country
project (Sharif, Hammawa, Ibrahim, & Garba, 2016).
A new gas law was passed by the Nigerian government in 2010 which was dedicated to a master
plan for gas. As per this plan, all the oil and gas producing companies had to develop plans to
supply local power stations. As the delta project was constructed with an aim to supply gas to
other countries, this legislation kept them low on that supply as they have to first take care of the
domestic gas supply needs (du, 2011).
9
Document Page
Trans-Saharan Mega Project Reflection Report
Commercial issues were faced with the increase in the cost of construction in the industry. The
initial cost estimation was accurate but by the time, decision was taking, the prices fluctuated.
This increased the need for investments and thus, decision had to be taken accordingly causing
delays in execution of the project.
2.6 Project and Program management complexities
There can be several variables contributing to program or project related complexities in a
pipeline construction project. In the case of the Saharan Gas Pipe line project, following
challenges were faced:
Environmental and archeological complexities: While constructing the new pipeline, land
areas that have special environmental or archaeological significance must be avoided as it can
cause problems to nearby residents and community groups which can result into resistance from
them. In the case of trans-Saharan pipeline project, the selected areas were found to be intrusive
to a number of communities that opposed the move leading to security threats from specialist
groups (Taiao, 2014).
Vandalism: Delta region where the pipeline construction was planned had problems of
vandalism rising from the Movement of emancipation of Niger Delta (MEND). The movement
was run by small groups of federal fights who had advanced technology weapons and had
objectives to destroy Government’s capacity to export oil and gas. They already had shown the
acts of vandalism such as bowing of the pipeline and kidnapping of the site engineers. In 2009,
an agreement was signed between them and the Nigerian government to seek peace through a
cease fire but the disagreement remained between them and MEND could not be trusted as they
would steal crude cargo for their own benefits (Oviasuyi & Uwadiae, 2010).
Stakeholder Priorities and Complexities
3.1 Stakeholder Management Problems, Issues and Challenges
Major stakeholders of the project are NNPC, Sonatrach and republic of Niger, with first two
together holding 10% stake and the later holding 10% stake on the project. There were a few
companies that have shown interest for participation in the project and these include Gazprom
10
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Trans-Saharan Mega Project Reflection Report
from Russia, GAIL from India, Total S.A from France, Eni SpA and Royal Dutch Shell from
Italy. These together make the supplier stakeholder group of the project. Other stakeholders of
the project included the ministry of three governments, nearby residents, and community groups
such as Nigerian militants (Mot MacDonald, 2010).
Because of multiple authorities involved and several major stakeholders, the decisions on route
to follow, security, financing and contractors to hire took much time and caused delays in
execution of the project (Flyvbjerg & Garbuio, Delusion and Deception in Large Infrastructure
Projects: Two Models for Explaining and Preventing Executive Disaster, 2009).
Optimum Bias
There was a clear bias seen in the optimization plan as the projections or forecasts of costs and
schedule did not provide out to be realistic in the long run. At the start of the project, a joint
venture was established between Sonatrach and NNPC and it was expected the project would get
sufficient funding post examination and a long-term feasibility study was performed positively.
However, optimism did not play well as the project team was unable to receive sufficient funding
after the project began (Karev, et al., 2015).
Strategic Misrepresentation
Strategic misrepresentation happens when there is a deliberate distortion of facts in the budgeting
process such that a project is proposed with underestimated budget and overestimated benefits.
The initial estimates of the project were expecting $6 billion as per the feasibility report but later
the estimates were revised to $15 billion which discourages most investors who did not see the
benefits. Most of the increase in the cost was due to the security issues arising from terrorist and
other armed forces (Flyvbjerg, 2007).
Miscalculation of risks and value
The design was created with the estimation of least cost required for construction on the project
and whole pipeline was divided into small sub-sections with pressure calculated for each to
optimize the design (Egbe, Takim, Ibeh, & Onyewudiala, 2016).
11
Document Page
Trans-Saharan Mega Project Reflection Report
Phase wise complexities - Life Cycle Approach
The construction project has four key phases in its life cycle and these include:
Conceptualization: In this phase of the project, the development philosophy is presented and the
sponsors are attracted to invest into the project. A consultant was appointed on the project to
gather buy-in from the sponsors for the trans-Saharan project.
Feasibility Analysis: In this stage, the feasibility of the project was assessed by Penspen limited.
The study involved demand scenario analysis for gas, identification of supply sources,
establishment of the requirement for infrastructure, determination of issues, estimation of project
costs, development of policy and regulatory framework, and economic benefit analysis of the
project. The company proved the project to be feasible with enough potential to attract
sponsorships for completion. However, when the security issues were faced at the later stages of
the project and the costs were escalated, a revised study was conducted that reflected the need for
additional funds upward of $10 billion to proceed (Creedy, 2006).
Definitional phase: In this phase, the structure and framework of the partnership and other
project specifics are defined and finalized. This included development of sponsor agreements,
selection of consultants for advisory, identification of commitment from suppliers for long term,
establishment of associated companies, survey of the route, execution of commercial agreements
made, creation of the development plan, conducting due diligence for resources, tendering of
contracts, and land acquisition (Addisababa, 2013).
Construction: This phase involves mobilization of resources including personnel, materials, and
equipments. During mobilization, agreements and contracts are made with suppliers and
contractors for building of the infrastructure. The resources are then involved in cleaning and
excavation the site to prepare it for construction. During excavation, the land, habitation, and
plantation in the area is affected. If there is a vegetation existing in the area where pipeline has to
be built and it has to be cleaned then it would lead to erosion of the soil. There are also increased
risk of exposure of workers to dangerous situation such as facing poisonous snakes, spiders or
bees. Because of the involvement of these complexities, the site should be chosen carefully so
that nearby communities do not oppose. Also, minimum disruption should be caused to the
nearby habitat. The excavations and cleaning work also produce solid and liquid wastes that can
cause contamination of soil and water. The waste needs to be managed effectively to reduce the
12
Document Page
Trans-Saharan Mega Project Reflection Report
probability of such damages If the people working on the construction site face accidents and
injuries then can affect the reputation of the construction company and can also lead to agitations
rising (Malden, 2017).
Operations: It involves taking care of the land that has been acquired for building a pipeline
which includes maintenance of the pipeline facilities as well as the land vegetation. Even in this
phase, waste can be generated and incidences can happen that can damage the reputation of the
contracting firm.
Decommissioning: This phase involves supply of labor and materials, drilling, flow line
activities, as well as recruitment of workers. Existing structures are dismantled and resulting
waste is disposed. These activities can cause dust, emissions, and noise. The negative impacts
that are caused in this phase can be reduced by taking certain steps like monitoring environment,
inspection, training, hazard analysis, and more. A waste management plan may be developed at
this stage with the objectives to reduce waste and reuse wherever possible through recycling
(Joseph, et al., 2008). It completes the construction phase
Supply Chain Management
8.1 Upstream Stakeholders
The upstream processes involved in a gas pipeline construction project include designing and
exploitation of reservoirs for obtaining gas for the transfer through the pipeline. Upstream
stakeholders are the companies that supply these. Designer would be the supplier who would
provide the initial inputs for the construction of a pipe and thus, needs to have sufficient
knowledge of all the factors that could influence the pipeline area, construction, and operations.
Effective design is the first step to achieving success of the pipeline construction project. The
project management for the complete designing phase was signed with Osprey Investments
Nigeria Limited for Trans-Sahara Gas pipeline (Yousfi, 2005). For the supply of the natural gas,
the contract was given to Gazprom which would serve as the source of gas for the pipeline
operations. However, the company faced declines in production due to financial issues that were
delaying launches of gas fields for production and supply. Thus, the project needed new sources
for gas production. Gazprom planned to collaborate with the main oil company in Nigeria
through a joint venture to expand upon its joint production capacities (WSJ, 2009).
13
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Trans-Saharan Mega Project Reflection Report
8.2 Mid-Stream Stakeholders
Mid-stream involves companies that operate functions of gas pipeline supply including
collection, compression, treatment, and distribution. Trans-Saharan Natural Gas Consortium is
the key stakeholder as it is responsible for operating the pipeline. Major midstream stakeholders
of the project were security agencies that were taking care of the security of the workers involved
in the project work, companies or contractors who had taken the responsibility of installation of
the pipelines, and the contractors responsible for maintenance of the pipelines to be constructed.
8.3 Downstream Stakeholders
Downstream sector of the project includes the purification and delivery of the gas supplies. Thus,
downstream stakeholders include the customers who are delivered the gas for local utilities.
Major downstream stakeholders of the project were Oil and gas ministry that took decisions on
legal and commercial aspects of the project and the distribution companies who would be
handling the distribution of the gas through the pipeline.
8.4 Supply Chain Stakeholder Matrix
The table below presents the supply chain stakeholder matrix that identifies different stakeholder
groups of the project along with their key concerns and engagement approaches.
Workers and Employees: They are most concerned about the clarity of the work
responsibilities they get and the earning which should be sufficient for them. The workers would
include people from across the three cultures including Nigeria, Algeria, and Niger. They could
be closely involved in project planning and other decision making as well clear communication
was provided on the project responsibilities to ensure they are effective. The project faced major
difficulties in this area and need to apply human resource management principles of project
management for improvement.
Shareholders: These are the entities and people having share in the entity through sponsorship
or shareholding. These stakeholders are interested in the profit generation of the project.
Considering the difficulties of the project, it was difficult to convince them of the profits and
thus, the project faced difficulties in getting funds.
14
Document Page
Trans-Saharan Mega Project Reflection Report
Suppliers: Suppliers are the organizations supplying gas and construction facilities. These
companies were having contractual relationship and were participating in the development. The
engagement is done through appropriate flow of information to ensure that they had clarity on
what is expected of them and sufficient payment to be made on time (Domjan, 2004).
Communities: Community around included the people resident and the concerned groups. The
project faced major opposition from most local communities as well as terrorists because of
which the project suffered. A consideration of these communities in planning could have helped
as the project owners could identify methods to convince them of support (Hajsleiman, 2018).
Strategic Risk Management
9.1 Pipeline Security
At the time of the development of the project, Amenas hostage crisis was faced by Nigerians that
had affected the project. There were active terrorist activities happening between Nigeria and
Algeria. The presence of crisis resulted into the rise of prices of project management because of
increased concerns of safety in the construction areas (Nwachukwu, 2017). Even the militant
groups active in Nigeria was not in the support of building the pipeline considering it as an
exploitation of Nigerian delta and thus, posing security threats in the construction region. There
were other groups that could pose more threats in the Delta region such as Touregs in Niger and
Al Qaeda in Magreb that came in the route of the planned pipeline (Auge, 2010).
9.2 Environmental Impacts
European Union gas market is facing several challenges such as lack of certainty in availability
of gas reserves and impacts of climate changes.
9.3 Cost and Time related risks
The estimated cost of the project development was $20 billion but in 2013, Nigeria could get
limited support for $700 million from Ethiopian Capital Addis Ababa, $450 million raised from
Eurobonds, and $250 contribution direct through equity. The project still fell short of $19 billion
needed for gas pipeline construction. IN 2013, the project faced major delays and one of the
investors, Gazprom was concerned about the security at the pipeline on the route as well as about
15
Document Page
Trans-Saharan Mega Project Reflection Report
the costs that were rising. There were delays in Final Investment Decision because of the
commitment of financers affected by such factors (Okere, 2018).
9.4 Long-term stability
Although, Nigeria is the largest oil producer in the African region, the production in Nigeria is
affected by the supply chain disruptions and instability. The country lacks the infrastructure
needed for distribution of gas. Nigeria accounts for 10% of the natural gas flare across the world
but in past few years, it was reduced to 515 billion cubic feet in 2011 from 575 billion cubic feet
that was in 2007 (Akpabio & Akpan, 2010).
9.5 Global crisis
The world is experiencing energy crisis contributed by some major factors like increase in
consumption of energy sources like oil and gas with increase in population, poor infrastructure
requiring more production of energy, wastage of energy by many, natural calamities destroying
energy sources, and political events. Energy crises is increasing the demand for the oil and gas
which is why more exploration projects are emerging. Pipeline project is an opportunity to serve
the gas needs of the world (Bahgat, 2010).
9.6 Quality Concerns
In any construction project, quality of construction is important as it would ensure that the
construction is sound. Higher quality of gas has to be ensured with following proper
specifications. Quality issues in natural gas can impact safety, operational efficiency, and
merchantability of gas production. Thus, standards of quality have to be followed such as
freedom from contamination of toxic or corrosive elements and withstanding in standard
atmospheric conditions (Foss, 2004).
Time and Cost Control
The project would have a planned schedule and budget which would be followed and monitored
along the project life cycle. To establish control over the schedule and cost, a WBS would be
prepared listing all the tasks and activities that are required to be done along with the assigned
resources and associated costs that is budgeted. The actual progress of the project would be
monitored against the scheduled timeline and budget allotments such that if any variations are
16
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Trans-Saharan Mega Project Reflection Report
hinted then steps would be taken immediately to make corrections immediately to keep the costs
and delays in control.
Change Management
Changes may be needed during the project execution in the schedule, scope, and cost. For each
change needed, a change request would be placed by the project team members to the project
manager who would be evaluating every request to understand how changes would impact the
triple constraints that is cost, time and scope of the project as well as its quality. Based on if the
changes would create a significant impact on three with justification for the business case, the
change would be approved or rejected. Every change made on the project would also be updated
in the project plans and accordingly, the remaining project would be handled.
Governance
Nigeria stands at 40th rank in oil and gas production across the world. This low rank is due to
lack of infrastructure, lack of revenue accountability, and incomplete disclosure policies. The
region has oil and gas reserves but its governance structure is not favorable. It is handled by
weak and inefficient entities in lack of a standard governance framework (Golombok, 2015).
Nigerian government does not have effective environmental regulation policies and structures
which is why the ecosystem of the country is fragile and environmental problems have largely
remained unsolved. The impacts of oil and gas exploration have not been properly controlled.
However, in recent years, some measures have been taken to minimize impacts such as
community engagement, compliance to international standards, and involvement of petroleum
ministry in regulation. However, the country still lacks the capacity to implement the regulations
needed for environmental conservation (Ogele, 2016).
Conclusions
This report explored the case of a complex mega project of gas pipeline construction that was a
result of a collaboration between three governments including Nigeria, Nigel, and Nigeria. The
project faced many problems, challenges and complexities as were discovered during the study
such as security problems from forces causing rise in costs, lack of funds needed for
construction, and more. The report discussed various challenges faced by the project and
17
Document Page
Trans-Saharan Mega Project Reflection Report
explored the opportunities to overcome he. It also explored possibility of using project
management practices and program management discipline to improving project outcomes. It
was found that if the mega project could be handled like a program divide into sub projects
handled by individual ministries, the project complexities would be reduced. Also, the use of
project management knowledge areas such as cost management, procurement management, and
risk management can be used for improvement.
Recommendations
Based on the findings from the case of gas pipeline project discussed in this study, certain project
management related recommendations can be made that would have been critical to
improvement in the way the project was handled and could have helped reduce the complexities
that suffered the project. These recommendations can help manage other complex mega projects
with better probability of success. The recommendations are:
Instead of managing the work as one single project, the project could be died into sub-
project and a program management approach can be use for managing them in tandem.
With this approach, different teams and different ministries would be managing different
projects and there would be less relationship complexities as their interests would be
more cohesive on single projects.
A number of project management knowledge areas can be used such as cost management,
procurement and risk management such that plans are created for each project for
managing each of these areas and people are assigned responsibilities to manage them.
The project is unable to gather the funds from the stakeholder resources and thus,
authorities may go for other sources of funds to gather money such as public funding.
References
18
Document Page
Trans-Saharan Mega Project Reflection Report
Addisababa, 2013. Nigeria – Algeria Pipeline. [Online]
Available at: http://addisababa.mfa.ir/uploads/Nigeria_-_Algeria_Pipeline_19959.pdf
[Accessed 11 October 2018].
Akpabio, E. M. & Akpan, N. S., 2010. Governance and Oil Politics in Nigeria’s Niger Delta: The Question of
Distributive Equity. J Hum Eco, 30(2), pp. 111-121.
Auge, B., 2010. Trans-Saharan Gas Pipeline: An illustion ora real prospect, s.l.: Ifri.
Bahgat, G., 2010. The geopolitics of energy: Europe and North Africa. The Journal of North African
Studies, 15(1), pp. 39-49.
BOOM, A. K. V. D., 2009. FAILING OF MEGA PROJECTS , s.l.: University of Aarhus .
Boon von Ochssée, T. A., 2010. The dynamics of natural gas supply coordination in a New
World:cooperation or competition between gas-exporting countries from a Russian perspective , s.l.: The
Hague.
Centre for Environmental Rights, 2014. Minimum Requirements for the Regulation of Environmental
Impacts of Hydraulic Fracturing in South Africa, s.l.: Centre for Environmental Rights.
Creedy, G. D., 2006. Risk Factors Leading to Cost Overrun in the Delivery of Highway Construction
Projects, s.l.: Queensland Univesity of Technology.
Domjan, P., 2004. The Supplier Development in the Oil and Gas Sector of Kazakhstan , s.l.: Republic of
Kazakhstan .
du, M. p. p. l., 2011. EU-Russia Energy Relations : the Role of International Law from Energy Investment
and Transit Perspective, s.l.: INSTITUT EUROPEEN DE L'UNIVERSITÉ DE GENÈVE.
Egbe, J. G., Takim, S. A., Ibeh, M. I. & Onyewudiala, J. I., 2016. Design Approach for Trans –Sahara Gas
Pipeline Transmission, s.l.: Research Gate.
ESMAP, 2003. Cross-Border Oil and Gas Pipelines:Problems and Prospects, s.l.: World Bank Group.
Flyvbjerg, B., 2007. How Optimism Bias and Strategic Misrepresentation Undermine Implementation, s.l.:
NTNU.
Flyvbjerg, B. & Garbuio, M., 2009. Delusion and Deception in Large Infrastructure Projects: Two Models
for Explaining and Preventing Executive Disaster, s.l.: Delft University of Technology.
Foss, M. M., 2004. INTERSTATE NATURAL GAS—QUALITY SPECIFICATIONS & INTERCHANGEABILITY , s.l.:
Center for Energy Economics.
Golombok, R. J. M. I., 2015. Oil Governance in Uganda and Kenya:A review of efforts to establish baseline
indicators on the impact of the oil sector in Uganda and Kenya, s.l.: MacArthur Foundation .
Hajsleiman, H. M., 2018. How to manage complex projects - an adaptive approach highlighting the
Human Factor and Information Management and Communication, s.l.: Stavanger University.
Joseph, M. et al., 2008. The Shell Petroleum Development Company of Nigeria Limited Operator of the
NNPC/Shell/Agip/Total Joint Venture, s.l.: Shell.
Karev, A. et al., 2015. Driving operational performance in oil and gas, s.l.: EYGM Limited.
Malden, A., 2017. Nigeria’s Oil and Gas Revenues: Insights From New Company, s.l.: National Resource
Governance Institute.
Mandil, C., 2007. NATURAL GAS MARKET REVIEW, s.l.: OECD.
Mayaki, I., 2015. AFRICA POWER VISION CONCEPT NOTE & IMPLEMENTATION PLAN from Vision to
Action, s.l.: NEPAD Planning and Coordinating Agency.
Mot MacDonald, 2010. Supplying the EU Natural Gas Market, s.l.: Mot MacDonald.
Nwachukwu, I. O., 2017. Relationship Between Oil Theft, Pipeline Vandalism, and Security Costs With
Revenue Losses, s.l.: Walden University.
19
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Trans-Saharan Mega Project Reflection Report
Obi, C. & Rustad, S. A., 2011. Oil and insurgency in the Niger Delta: Managing the complex politics of
petroviolence, s.l.: Zed Books.
Ogele, F. O., 2016. Governance of Oil and Gas Sector in Nigeria: Implications for Biodiversity and
Ecosystem Services in the Niger Delta Region, s.l.: Newscastle University.
Okere, R., 2018. Nigeria: $12b Trans-Saharan Gas Project to Miss 2018 Deadline. [Online]
Available at: https://allafrica.com/stories/201803130193.html
[Accessed 10 June 2018].
Oviasuyi, P. O. & Uwadiae, J., 2010. The Dilemma of Niger-Delta Region as Oil Producing States of
Nigeria. Journal of Peace, Conflict and Development, Issue 16, pp. 111-126.
Serova, D., 2015. Petroleum fiscal system design and cost-related incentives in oil and gas projects, s.l.:
Norwegian School of Economics.
Sharif, H. A., Hammawa, D. D., Ibrahim, M. & Garba, I. B., 2016. Gas Flaring: When Will Nigeria
Decarbonise Its Oil and Gas Industry. International Journal of Economy, Energy and Environment, 1(3),
pp. 40-54.
Suzuki, T. & Morikawa, T., 2004. LNG Demand-Supply and Trends in Natural Gas in the Asia-Pacific
Region, s.l.: Ministry of Economy, Trade and Industry.
Taiao, M. M. T., 2014. Managing Environmental Effects of Onshore Petroleum Development Activities
(Including Hydraulic Fracturing): Guidelines for Local Government, s.l.: New Zealand GOvernment.
Ushie, V., 2013. Nigeria's Amnesty Programme as a Peacebuilding Infrastructure: A Silver Bullet?. Journal
of Peacebuilding & Development, 8(1), pp. 30-44.
WSJ, 2009. African Nations Sign Deal for Trans-Saharan Gas Pipeline. Wall Street Journal Online.
Yousfi, M., 2005. Trans - Saharan Gas Pipeline Project(TSGP) - Road Map For Success, s.l.: OnePetro.
20
chevron_up_icon
1 out of 20
circle_padding
hide_on_mobile
zoom_out_icon
logo.png

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]