MAN6325: Project Initiation Document for Addiction Treatment Centre
VerifiedAdded on  2022/08/27
|30
|6264
|28
Project
AI Summary
This Project Initiation Document (PID) details the plan for the development of a new addiction treatment centre in Apple Vale, Western Australia. The project, initiated by Tun Therapies (TT) and supported by the WA Government, involves demolishing an existing resort to construct the 'Ander Reach Treatment Complex' (ARTC). The PID outlines the project's scope, objectives, deliverables, requirements, and constraints, including compliance with private hospital guidelines. It encompasses a comprehensive project management plan, covering scope, scheduling, cost, quality, stakeholder, procurement, and risk management. The document details milestones, WBS, and budget allocations. The project's objectives include providing quality patient care, meeting government standards, and establishing necessary facilities. The project has a budget of $26,729,373 and faces constraints such as limited work hours and fixed holidays. The successful completion of the project will provide a new charitable treatment center in Apple Vale.

Running head: PROJECT INITIATION DOCUMENT FOR PROPOSED ADDICTION TREATMENT CENTRE
Project Initiation Document for Proposed Addiction Treatment Centre
Name of the Student
Name of the University
Author note
Project Initiation Document for Proposed Addiction Treatment Centre
Name of the Student
Name of the University
Author note
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1PROJECT INITIATION DOCUMENT FOR PROPOSED ADDICTION TREATMENT CENTRE
Executive Summary
The project is based on designing and development of a new treatment centre for patients and
visitors who would be visiting Apple Vale. The proposal for the design of the treatment centre
has been planned by TT who would be responsible for designing the centre and incur various
hospital infrastructure within the system. This centre would be completely based on charity and
thus would no additional charges would be procured for the development and construction of the
centre. The project have been supported by the WA Government who would perform a close
monitoring over the development progress. The following Project Proposal document thus
focuses on the different elements to be included within the project and which could be
considered as important inclusions to be proposed during the development of the initial project
plan. Thus, the following parts of the discussion within the proposal would focus on the defining
of milestones, setting of the WBS and budget for the project.
The discussion would also focus on the project scope statement in which different inclusions
such as the project scope, the deliverables, expected outcomes, assumptions and budget for the
project have been planned accordingly. The next part of the PID thus focuses on the project
management plan. Under this planning aspect, the aspect of scope management plan have been
discussed. The scheduling and cost management plan for the project have been discussed in
accordance to the requirements as outlined within the case. After determining the schedule
management plan, the quality management plan would be discussed, which outlines the quality
needed and outcomes after the plan of the project. The report further also discusses on the
procurement management plan, stakeholder management plan and risk management plan, which
are also discussed as important inputs, which needs to be discussed well in order to gain proper
delivery and successful business outcomes after the completion of the project.
Executive Summary
The project is based on designing and development of a new treatment centre for patients and
visitors who would be visiting Apple Vale. The proposal for the design of the treatment centre
has been planned by TT who would be responsible for designing the centre and incur various
hospital infrastructure within the system. This centre would be completely based on charity and
thus would no additional charges would be procured for the development and construction of the
centre. The project have been supported by the WA Government who would perform a close
monitoring over the development progress. The following Project Proposal document thus
focuses on the different elements to be included within the project and which could be
considered as important inclusions to be proposed during the development of the initial project
plan. Thus, the following parts of the discussion within the proposal would focus on the defining
of milestones, setting of the WBS and budget for the project.
The discussion would also focus on the project scope statement in which different inclusions
such as the project scope, the deliverables, expected outcomes, assumptions and budget for the
project have been planned accordingly. The next part of the PID thus focuses on the project
management plan. Under this planning aspect, the aspect of scope management plan have been
discussed. The scheduling and cost management plan for the project have been discussed in
accordance to the requirements as outlined within the case. After determining the schedule
management plan, the quality management plan would be discussed, which outlines the quality
needed and outcomes after the plan of the project. The report further also discusses on the
procurement management plan, stakeholder management plan and risk management plan, which
are also discussed as important inputs, which needs to be discussed well in order to gain proper
delivery and successful business outcomes after the completion of the project.

2PROJECT INITIATION DOCUMENT FOR PROPOSED ADDICTION TREATMENT CENTRE
Table of Contents
1. Scope Statement...........................................................................................................................4
1.1 Threats and Opportunities......................................................................................................4
1.2 Project Objectives..................................................................................................................5
1.3 Deliverables...........................................................................................................................5
1.4 Requirements.........................................................................................................................7
1.5 Exclusions..............................................................................................................................8
1.6 Constraints.............................................................................................................................8
1.7 Assumptions..........................................................................................................................9
2. Milestones..................................................................................................................................10
3. WBS and Budget.......................................................................................................................10
4. Project Management Plan..........................................................................................................13
4.1 Project Management Methodology......................................................................................13
4.2 Scope Management Plan......................................................................................................14
4.2.1 Collect Requirements....................................................................................................14
4.2.2 Define scope.................................................................................................................15
4.2.3 Create WBS..................................................................................................................15
4.2.4 Validate Scope..............................................................................................................15
4.2.5 Control Scope...................................................................................................................15
4.3 Scheduling and Cost Management Plan..............................................................................16
Table of Contents
1. Scope Statement...........................................................................................................................4
1.1 Threats and Opportunities......................................................................................................4
1.2 Project Objectives..................................................................................................................5
1.3 Deliverables...........................................................................................................................5
1.4 Requirements.........................................................................................................................7
1.5 Exclusions..............................................................................................................................8
1.6 Constraints.............................................................................................................................8
1.7 Assumptions..........................................................................................................................9
2. Milestones..................................................................................................................................10
3. WBS and Budget.......................................................................................................................10
4. Project Management Plan..........................................................................................................13
4.1 Project Management Methodology......................................................................................13
4.2 Scope Management Plan......................................................................................................14
4.2.1 Collect Requirements....................................................................................................14
4.2.2 Define scope.................................................................................................................15
4.2.3 Create WBS..................................................................................................................15
4.2.4 Validate Scope..............................................................................................................15
4.2.5 Control Scope...................................................................................................................15
4.3 Scheduling and Cost Management Plan..............................................................................16
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3PROJECT INITIATION DOCUMENT FOR PROPOSED ADDICTION TREATMENT CENTRE
4.4. Quality Management Plan..................................................................................................19
4.5 Stakeholder and Communication Management Plan...........................................................20
4.6 Procurement Management Plan...........................................................................................21
4.7 Risk Management Plan........................................................................................................22
References......................................................................................................................................25
4.4. Quality Management Plan..................................................................................................19
4.5 Stakeholder and Communication Management Plan...........................................................20
4.6 Procurement Management Plan...........................................................................................21
4.7 Risk Management Plan........................................................................................................22
References......................................................................................................................................25
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4PROJECT INITIATION DOCUMENT FOR PROPOSED ADDICTION TREATMENT CENTRE
1. Scope Statement
1.1 Threats and Opportunities
Apple Vale is considered to be a small coastal town, which is situated at a distance of 300
km from Perth. In the present times, ‘Anders Reach’, which is one of the medium-sized and low-
size resorts was being decided to be sold. The resort had a capacity to accommodate nearly 100
guests in out-buildings, tents and caravans (Gálvez-Martos et al., 2018). During the auction of
Anders Reach, it was bought by ‘Tun Therapies’ (TT). The organization TT was established
nearly 10 years ago and the major dependency of the business was based on treating alcoholism
and different other kinds of substance addictions, which were primarily dependent on drugs.
The major threat that is being recently posed over the TT is based on their decision of
demolishing the present resort and develop a treatment centre for patients. However, it has been
confirmed by TT that with the design and implementation of the new charitable organization, it
would be highly beneficial for patients (Walker, 2015). The major proposal that was being made
by TT were based on demolishing the existing of old buildings and thus for the creation of
‘Ander Reach Treatment Complex’ (ARTC). The charity would help in understanding towards
the specifications that would be sent by ARTC that would be in collaboration with various
private hospitals outlined within the WA Government.
Based on the understanding of the developmental prospects of TT, some of the major
opportunities before ARTC are:
ï‚· Development of a new treatment centre for patients who would be visiting the hospital.
ï‚· Supporting catering facilities for visitors, staff and patients.
1. Scope Statement
1.1 Threats and Opportunities
Apple Vale is considered to be a small coastal town, which is situated at a distance of 300
km from Perth. In the present times, ‘Anders Reach’, which is one of the medium-sized and low-
size resorts was being decided to be sold. The resort had a capacity to accommodate nearly 100
guests in out-buildings, tents and caravans (Gálvez-Martos et al., 2018). During the auction of
Anders Reach, it was bought by ‘Tun Therapies’ (TT). The organization TT was established
nearly 10 years ago and the major dependency of the business was based on treating alcoholism
and different other kinds of substance addictions, which were primarily dependent on drugs.
The major threat that is being recently posed over the TT is based on their decision of
demolishing the present resort and develop a treatment centre for patients. However, it has been
confirmed by TT that with the design and implementation of the new charitable organization, it
would be highly beneficial for patients (Walker, 2015). The major proposal that was being made
by TT were based on demolishing the existing of old buildings and thus for the creation of
‘Ander Reach Treatment Complex’ (ARTC). The charity would help in understanding towards
the specifications that would be sent by ARTC that would be in collaboration with various
private hospitals outlined within the WA Government.
Based on the understanding of the developmental prospects of TT, some of the major
opportunities before ARTC are:
ï‚· Development of a new treatment centre for patients who would be visiting the hospital.
ï‚· Supporting catering facilities for visitors, staff and patients.

5PROJECT INITIATION DOCUMENT FOR PROPOSED ADDICTION TREATMENT CENTRE
ï‚· Develop treatment rooms, which would be more spacious for accommodating sufficient
medical instruments (Osei-Kyei & Chan, 2017).
ï‚· Hiring the best staff who would take care of patients and their well-being.
1.2 Project Objectives
The objectives that have been set forth by ARTC for the designing of the new treatment
centre at Apple Vale are as follows:
ï‚· Meeting the code of private hospitals as mentioned by WA Government
ï‚· Outlining the different facilities that should be incorporated within the hospital.
ï‚· Defining the staff who would be required for different specializations set within the
organization
ï‚· Providing the best class of accommodation facilities for patients getting treated within the
centre
ï‚· Defining the different administrative departments and their individual functionalities
ï‚· Including a proper infrastructure for car parking for the visitors who would arrive at
ARTC
1.3 Deliverables
In consideration of the new proposal based on building ARTC, which is a new treatment
centre at Apple Vale, it can be discussed that some of the major deliverables includes the
understanding of specifications that would need to be supported within ARTC (MartÃnez-
Rocamora, SolÃs-Guzmán & Marrero, 2016). It would also be able to include the specifications
that would be supporting the various objectives set by ARTC.
ï‚· Develop treatment rooms, which would be more spacious for accommodating sufficient
medical instruments (Osei-Kyei & Chan, 2017).
ï‚· Hiring the best staff who would take care of patients and their well-being.
1.2 Project Objectives
The objectives that have been set forth by ARTC for the designing of the new treatment
centre at Apple Vale are as follows:
ï‚· Meeting the code of private hospitals as mentioned by WA Government
ï‚· Outlining the different facilities that should be incorporated within the hospital.
ï‚· Defining the staff who would be required for different specializations set within the
organization
ï‚· Providing the best class of accommodation facilities for patients getting treated within the
centre
ï‚· Defining the different administrative departments and their individual functionalities
ï‚· Including a proper infrastructure for car parking for the visitors who would arrive at
ARTC
1.3 Deliverables
In consideration of the new proposal based on building ARTC, which is a new treatment
centre at Apple Vale, it can be discussed that some of the major deliverables includes the
understanding of specifications that would need to be supported within ARTC (MartÃnez-
Rocamora, SolÃs-Guzmán & Marrero, 2016). It would also be able to include the specifications
that would be supporting the various objectives set by ARTC.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6PROJECT INITIATION DOCUMENT FOR PROPOSED ADDICTION TREATMENT CENTRE
The required deliverables that would be included within the ARTC are discussed as
follows:
ID Deliverable Scope of Work
1 New Building
1 Interior Building elements
1.1.1 Accommodation rooms Structural work, Fit-out, Earthwork
1.1.2 Treatment rooms Structural work, Fit-out, Earthwork
1.1.3 Joint-counseling classrooms Structural work, Fit-out, Earthwork
1.1.4 Dining room Structural work, Fit-out, Earthwork
1.1.5 TV room Structural work, Fit-out, Earthwork
1.1.6 Library Structural work, Fit-out, Earthwork
1.1.7 Quiet spaces Structural work, Fit-out, Earthwork
1.2 Staffing sections
1.2.1 Staff showers Structural work, Fit-out, Earthwork
1.2.2 Staff meeting rooms Structural work, Fit-out, Earthwork
1.2.3 Staff locker rooms Structural work, Fit-out, Earthwork
1.2.4 Staff classroom Structural work, Fit-out, Earthwork
1.2.5 Staff meal preparation areas Structural work, Fit-out, Earthwork
1.3 Kitchen Rooms Structural work, Fit-out, Earthwork
1.4 Patient-treatment rooms Structural work, Fit-out, Earthwork
1.4.1 Patient joint-counseling classrooms Structural work, Fit-out, Earthwork
1.4.2 Out-patient treatment rooms Structural work, Fit-out, Earthwork
1.5 Medical dispensary Structural work, Fit-out, Earthwork
1.6 Showers and public toilets Structural work, Fit-out, Earthwork
2. Exterior Elements
2.1 Small public restaurants Structural work, Fit-out, Earthwork
2.2 Garden Structural work, Fit-out, Earthwork
2.3 Fitness suite Structural work, Fit-out, Earthwork
2.4 Administrative and Reception offices Structural work, Fit-out, Earthwork
2.5 Added Spaces Structural work, Fit-out, Earthwork
2.5.1 Car parking spaces Structural work, Fit-out, Earthwork
2.5.2 Ambulance bay Structural work, Fit-out, Earthwork
2.5.3 Waste disposal Structural work, Fit-out, Earthwork
2.5.4 On-site utilities Structural work, Fit-out, Earthwork
The required deliverables that would be included within the ARTC are discussed as
follows:
ID Deliverable Scope of Work
1 New Building
1 Interior Building elements
1.1.1 Accommodation rooms Structural work, Fit-out, Earthwork
1.1.2 Treatment rooms Structural work, Fit-out, Earthwork
1.1.3 Joint-counseling classrooms Structural work, Fit-out, Earthwork
1.1.4 Dining room Structural work, Fit-out, Earthwork
1.1.5 TV room Structural work, Fit-out, Earthwork
1.1.6 Library Structural work, Fit-out, Earthwork
1.1.7 Quiet spaces Structural work, Fit-out, Earthwork
1.2 Staffing sections
1.2.1 Staff showers Structural work, Fit-out, Earthwork
1.2.2 Staff meeting rooms Structural work, Fit-out, Earthwork
1.2.3 Staff locker rooms Structural work, Fit-out, Earthwork
1.2.4 Staff classroom Structural work, Fit-out, Earthwork
1.2.5 Staff meal preparation areas Structural work, Fit-out, Earthwork
1.3 Kitchen Rooms Structural work, Fit-out, Earthwork
1.4 Patient-treatment rooms Structural work, Fit-out, Earthwork
1.4.1 Patient joint-counseling classrooms Structural work, Fit-out, Earthwork
1.4.2 Out-patient treatment rooms Structural work, Fit-out, Earthwork
1.5 Medical dispensary Structural work, Fit-out, Earthwork
1.6 Showers and public toilets Structural work, Fit-out, Earthwork
2. Exterior Elements
2.1 Small public restaurants Structural work, Fit-out, Earthwork
2.2 Garden Structural work, Fit-out, Earthwork
2.3 Fitness suite Structural work, Fit-out, Earthwork
2.4 Administrative and Reception offices Structural work, Fit-out, Earthwork
2.5 Added Spaces Structural work, Fit-out, Earthwork
2.5.1 Car parking spaces Structural work, Fit-out, Earthwork
2.5.2 Ambulance bay Structural work, Fit-out, Earthwork
2.5.3 Waste disposal Structural work, Fit-out, Earthwork
2.5.4 On-site utilities Structural work, Fit-out, Earthwork
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7PROJECT INITIATION DOCUMENT FOR PROPOSED ADDICTION TREATMENT CENTRE
1.4 Requirements
ID Requirement Features and Deliverables
1 Different shared facilities
and developmental savings
towards cost
The facilities provided within the treatment centre would
need to be highly efficient in nature. These include
efficient staffroom infrastructure, treatment rooms and
sufficient accommodation spaces
2 Location of building should
be in an optimal reach to
visitors
1. Car parking facilities would be included within ARTC
and should be visible to visitors.
2. Waste disposal facilities would be included at the back
side of the building
3. Inclusion of public restaurants, gymnasium and other
wide ranging fitness suites
3 Safety 1. Ambulance access would be provided at a provision of
24/7.
2. Special vehicles would be provided within the car
parking facility
3. Securing the campus of ARTC with safety personnel,
improved safety equipment and improved infrastructure.
4. Alarm system and contracted security.
5. Special provisions for emergency cases
4 Increased participation from
tourists and other visitors of
Apple Vale
1. Inclusion of public restaurant, counseling classrooms
2. Designing showers and public toilets
5 Availability of treatment
centre facilities during night
hours
1. Accommodation facilities for patients including special
treatment rooms. These would include bedside table, call
button, personal locker
2. Special treatment rooms supporting special
infrastructure
3. Staff who would be serving patients during night hours
6 Car Parking and other
infrastructure facilities
1. Ambulance access for support during peak situations
2. Special spaces for pick-up and drop-off facility
7 Energy saving equipment
and infrastructure
1. Solar cars to be provided for bringing visitors from the
gate till the treatment centre
2. Solar panels to be supported at the rooftop and solar
electricity to be used in different administrative blocks of
the ARTC
8 Efficiency in partnership 1. Partnering with local hospitals for transferring critical
1.4 Requirements
ID Requirement Features and Deliverables
1 Different shared facilities
and developmental savings
towards cost
The facilities provided within the treatment centre would
need to be highly efficient in nature. These include
efficient staffroom infrastructure, treatment rooms and
sufficient accommodation spaces
2 Location of building should
be in an optimal reach to
visitors
1. Car parking facilities would be included within ARTC
and should be visible to visitors.
2. Waste disposal facilities would be included at the back
side of the building
3. Inclusion of public restaurants, gymnasium and other
wide ranging fitness suites
3 Safety 1. Ambulance access would be provided at a provision of
24/7.
2. Special vehicles would be provided within the car
parking facility
3. Securing the campus of ARTC with safety personnel,
improved safety equipment and improved infrastructure.
4. Alarm system and contracted security.
5. Special provisions for emergency cases
4 Increased participation from
tourists and other visitors of
Apple Vale
1. Inclusion of public restaurant, counseling classrooms
2. Designing showers and public toilets
5 Availability of treatment
centre facilities during night
hours
1. Accommodation facilities for patients including special
treatment rooms. These would include bedside table, call
button, personal locker
2. Special treatment rooms supporting special
infrastructure
3. Staff who would be serving patients during night hours
6 Car Parking and other
infrastructure facilities
1. Ambulance access for support during peak situations
2. Special spaces for pick-up and drop-off facility
7 Energy saving equipment
and infrastructure
1. Solar cars to be provided for bringing visitors from the
gate till the treatment centre
2. Solar panels to be supported at the rooftop and solar
electricity to be used in different administrative blocks of
the ARTC
8 Efficiency in partnership 1. Partnering with local hospitals for transferring critical

8PROJECT INITIATION DOCUMENT FOR PROPOSED ADDICTION TREATMENT CENTRE
with doctor, nurse and other
businesses
patients who need special care
2. Employing highly qualified doctors, staff and nurses to
serve patients
3. Contracting reputable pharmacies to support medicines
of all types to all patients
1.5 Exclusions
Based on understanding the different aspects to be included as facilities within the
ARTC, some of the particular exclusions from the designed project are discussed as follows:
1. Current escalation
2. Imported fill
3. Subsoil drainage
4. Headwork charges
5. Compound and transformed
6. Green-building requirements
1.6 Constraints
Based on understanding of the type of inclusions and exclusions and the understood work
to be supported at ARTC, the constraints to be considered for the current project under
consideration are:
1. Employees working for the project would be limited to a working time of 8 hours per
day.
with doctor, nurse and other
businesses
patients who need special care
2. Employing highly qualified doctors, staff and nurses to
serve patients
3. Contracting reputable pharmacies to support medicines
of all types to all patients
1.5 Exclusions
Based on understanding the different aspects to be included as facilities within the
ARTC, some of the particular exclusions from the designed project are discussed as follows:
1. Current escalation
2. Imported fill
3. Subsoil drainage
4. Headwork charges
5. Compound and transformed
6. Green-building requirements
1.6 Constraints
Based on understanding of the type of inclusions and exclusions and the understood work
to be supported at ARTC, the constraints to be considered for the current project under
consideration are:
1. Employees working for the project would be limited to a working time of 8 hours per
day.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

9PROJECT INITIATION DOCUMENT FOR PROPOSED ADDICTION TREATMENT CENTRE
2. Saturday and Sunday would be considered as fixed holidays for the construction
workers and all other staff.
3. The budget allocated for the project has been set at $26,729,373.
1.7 Assumptions
The different assumptions that could be made for the project based on designing a new
treatment centre are:
1. The different structural, construction and included architectural diagrams for each of
the buildings would be made available to the management at Apple Vale.
2. The project would be completed within the estimated schedule and budget as set within
the initial plan (Brook, 2016).
3. Coffee shops and restaurants would be designed and each facility would be made
available during the opening of ARTC.
4. During the site opening, each of the facilities such as car parking, waste disposal area
should be prepared as planned.
5. Safety equipment should be procured at the earliest and installed at particular segments
as mentioned.
6. Each of the equipment and facilities to be provided within the hospital rooms should be
made ready, checked and approved (Wu, Wang & Wang, 2016).
2. Saturday and Sunday would be considered as fixed holidays for the construction
workers and all other staff.
3. The budget allocated for the project has been set at $26,729,373.
1.7 Assumptions
The different assumptions that could be made for the project based on designing a new
treatment centre are:
1. The different structural, construction and included architectural diagrams for each of
the buildings would be made available to the management at Apple Vale.
2. The project would be completed within the estimated schedule and budget as set within
the initial plan (Brook, 2016).
3. Coffee shops and restaurants would be designed and each facility would be made
available during the opening of ARTC.
4. During the site opening, each of the facilities such as car parking, waste disposal area
should be prepared as planned.
5. Safety equipment should be procured at the earliest and installed at particular segments
as mentioned.
6. Each of the equipment and facilities to be provided within the hospital rooms should be
made ready, checked and approved (Wu, Wang & Wang, 2016).
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

10PROJECT INITIATION DOCUMENT FOR PROPOSED ADDICTION TREATMENT CENTRE
2. Milestones
The different milestones that would need to be performed for the project are being
discussed as follows:
1. Acquiring of the site
2. Finishing the preparation works over the site
3. Finishing the building construction
4. Completion of external area
5. Finish of payments and construction
3. WBS and Budget
The WBS for the project along with the given dates of start and completion of each of the
project have been considered as follows:
Task Name Duration Start Finish
Development of ARTC at Apple Vale 513 days Wed 25-03-20 Fri 11-03-22
Setting up of site 66 days Wed 25-03-20 Wed 24-06-20
Planning and setting up of site 30 days Wed 25-03-20 Tue 05-05-20
Costs of preparation and demolition 36 days Wed 06-05-20 Wed 24-06-20
Construction of new building 209 days Thu 25-06-20 Tue 13-04-21
Construction of main building 150 days Thu 25-06-20 Wed 20-01-21
Preparation of walkways 34 days Thu 21-01-21 Tue 09-03-21
Preparation of courtyards 25 days Wed 10-03-21 Tue 13-04-21
Construction of exterior elements 234 days Wed 14-04-21 Mon 07-03-22
2. Milestones
The different milestones that would need to be performed for the project are being
discussed as follows:
1. Acquiring of the site
2. Finishing the preparation works over the site
3. Finishing the building construction
4. Completion of external area
5. Finish of payments and construction
3. WBS and Budget
The WBS for the project along with the given dates of start and completion of each of the
project have been considered as follows:
Task Name Duration Start Finish
Development of ARTC at Apple Vale 513 days Wed 25-03-20 Fri 11-03-22
Setting up of site 66 days Wed 25-03-20 Wed 24-06-20
Planning and setting up of site 30 days Wed 25-03-20 Tue 05-05-20
Costs of preparation and demolition 36 days Wed 06-05-20 Wed 24-06-20
Construction of new building 209 days Thu 25-06-20 Tue 13-04-21
Construction of main building 150 days Thu 25-06-20 Wed 20-01-21
Preparation of walkways 34 days Thu 21-01-21 Tue 09-03-21
Preparation of courtyards 25 days Wed 10-03-21 Tue 13-04-21
Construction of exterior elements 234 days Wed 14-04-21 Mon 07-03-22

11PROJECT INITIATION DOCUMENT FOR PROPOSED ADDICTION TREATMENT CENTRE
Allowance for excavation of rocks 32 days Wed 14-04-21 Thu 27-05-21
Constructing the paved areas 21 days Fri 28-05-21 Fri 25-06-21
Preparing parking 35 days Mon 28-06-21 Fri 13-08-21
Preparing roadworks 46 days Mon 16-08-21 Mon 18-10-21
Planning and designing stormwater drainage 29 days Mon 28-06-21 Thu 05-08-21
Preparing the sewer drainage 29 days Tue 19-10-21 Fri 26-11-21
Cold water services 32 days Mon 29-11-21 Tue 11-01-22
Defining gas services 12 days Wed 12-01-22 Thu 27-01-22
Defining telecom and external electrical supply 15 days Wed 12-01-22 Tue 01-02-22
Reticulation and landscaping 24 days Wed 02-02-22 Mon 07-03-22
On Costs 4 days Tue 08-03-22 Fri 11-03-22
Contractual contingencies 2 days Tue 08-03-22 Wed 09-03-22
Preliminaries 2 days Thu 10-03-22 Fri 11-03-22
Allowance for excavation of rocks 32 days Wed 14-04-21 Thu 27-05-21
Constructing the paved areas 21 days Fri 28-05-21 Fri 25-06-21
Preparing parking 35 days Mon 28-06-21 Fri 13-08-21
Preparing roadworks 46 days Mon 16-08-21 Mon 18-10-21
Planning and designing stormwater drainage 29 days Mon 28-06-21 Thu 05-08-21
Preparing the sewer drainage 29 days Tue 19-10-21 Fri 26-11-21
Cold water services 32 days Mon 29-11-21 Tue 11-01-22
Defining gas services 12 days Wed 12-01-22 Thu 27-01-22
Defining telecom and external electrical supply 15 days Wed 12-01-22 Tue 01-02-22
Reticulation and landscaping 24 days Wed 02-02-22 Mon 07-03-22
On Costs 4 days Tue 08-03-22 Fri 11-03-22
Contractual contingencies 2 days Tue 08-03-22 Wed 09-03-22
Preliminaries 2 days Thu 10-03-22 Fri 11-03-22
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 30
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
 +13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.