This project plan details the development of a cab application for TripTastic. The project involves a series of processes, starting with requirement gathering and analysis, followed by detailed project planning, design of the app, procurement of resources, infrastructure development, app development, detailed testing, and finally, system deployment and integration. The plan includes a Work Breakdown Structure (WBS) with tasks, durations, start and finish dates, predecessors, and resource assignments. It also covers schedule management, including the identification of activities, activity logic, milestones, and critical paths. The project also includes a cost management plan, detailing the cost elements, estimation methods, and budget preparation. The goal is to create a user-friendly cab application that allows customers to book cabs from any location using their smartphones.
tabler-icon-diamond-filled.svg

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
Running Head: PROJECT MANAGEMENT
Project Management
Name of the Student
Name of the University
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
1PROJECT MANAGEMENT
Introduction
This project is based on the development of a cab application for TripTastic through the
customers will be able to hire cabs from any location using a smartphone. This application will
be very handy for the users when there are no regular cabs nearby. The users can just open the
app, select destination and search for cabs and one cab for the nearby area will be automatically
booked for them. This project aims to develop this proposed app through a series of process that
has been discussed in this project plan.
2. Project Activities, Schedule, Resource and Milestone Plan
A project schedule is defined as a representation of a breakdown of the project including
the durations of each activity. This process is followed in order to estimate the overall schedule
for the project. Once the project is broken down into individual activities under a number of
phases, each activity is assigned with an estimated duration and the total duration of the entire
project can then be determined by adding up the durations of the activities. Again, this schedule
can be used to assign responsibilities to the project team members. Once the team members are
defined, they can be allocated to each of the activities in the work breakdown structure.
Milestones are specific points in the project that define that closing of a phase or a particular
achievement in the project that is assigned with zero duration. The overall project schedule
including the activities, resources assigned and milestones are shown in the following table.
WBS Task Name Duration Start Finish Predecessors Resource Names
0 Development of Cab Application for TripTastic 255 days Tue 05-11-19 Mon 26-10-20
1 Requirement Gathering and Analysis 6 days Tue 05-11-19 Tue 12-11-19
1.1 Team Meeting Regarding the Project Requirements 2 days Tue 05-11-19 Wed 06-11-19
Document Page
2PROJECT MANAGEMENT
1.1.1 Identify Business Opportunities 1 day Tue 05-11-19 Tue 05-11-19 Project Manager
1.1.2 Identify Technical Requirements 1 day Tue 05-11-19 Tue 05-11-19 3SS Project Manager
1.1.3 Discuss Feasibility of the Project 1 day Tue 05-11-19 Tue 05-11-19 4SS Project Manager
1.1.4 Discuss Final End Goals of the Project 1 day Wed 06-11-19 Wed 06-11-19 5 Project Manager
1.1.5 Identify the Overall Scope for the Project 1 day Wed 06-11-19 Wed 06-11-19 6SS Project Manager
1.1.6 Estimate Time Required for the Project 1 day Wed 06-11-19 Wed 06-11-19 7SS Project Manager
1.1.7 Estimate Overall Budget for the Project 1 day Wed 06-11-19 Wed 06-11-19 8SS Project Manager
1.2 Propose SLA Requirements for the App to be
Developed 2 days Mon 11-11-19 Tue 12-11-19 9FS+2 days Project Manager
1.3 Requirements Gathering and Analysis Complete 0 days Tue 12-11-19 Tue 12-11-19 10 Project Manager
2 Detailed Project Planning 23 days Wed 13-11-19 Fri 13-12-19
2.1 Development of Project Charter and Project Plan
Document 20 days Wed 13-11-19 Tue 10-12-19
2.1.1 Develop List of Hardware Requirements for
Developing the App 2 days Wed 13-11-19 Thu 14-11-19 11 Information System
Developer
2.1.2 Develop List of Software Requirements for
Developing the App 2 days Wed 13-11-19 Thu 14-11-19 14FF Information System
Developer
2.1.3 Develop Hardware and Software Implementation
Strategy 1 day Fri 15-11-19 Fri 15-11-19 15 Information System
Developer
2.1.4 Identify Team Staffing Requirements for the Project
Purpose 1 day Mon 18-11-19 Mon 18-11-19 16 Information System
Developer
2.1.5 Identify Primary and Secondary Features Required for
the App 1 day Tue 19-11-19 Tue 19-11-19 17 Information System
Developer
2.1.6 Break Down the Project Work Requirements using
Work Breakdown Structure 3 days Wed 20-11-19 Fri 22-11-19 18 Information System
Developer
2.1.7 Prepare change management framework 3 days Mon 25-11-19 Wed 27-11-19 19 Information System
Developer
2.1.8 Identify contingency 3 days Thu 28-11-19 Mon 02-12-19 20 Information System
Developer
2.1.9 Identify security requirements 3 days Tue 03-12-19 Thu 05-12-19 21 Information System
Developer
2.1.10 Prepare appropriate execution plan 3 days Fri 06-12-19 Tue 10-12-19 22 Information System
Developer
2.2 Final Cost Estimation for the Project 1 day Wed 11-12-19 Wed 11-12-19 23 Project Manager
2.3 Conduct Second Meeting with the Team Members 1 day Thu 12-12-19 Thu 12-12-19 24 Project Manager
2.4 Finalise the Overall Project Plan 1 day Fri 13-12-19 Fri 13-12-19 25 Project Manager
2.5 Project Planning Complete 0 days Fri 13-12-19 Fri 13-12-19 26
3 Design of the Proposed App 36 days Mon 16-12-19 Mon 03-02-20
3.1 Develop Initial Prototype of the App 6 days Mon 16-12-19 Mon 23-12-19 27 Development Team
Member 1, Development
Document Page
3PROJECT MANAGEMENT
Team Member 2,
Development Team
Member 3, Development
Team Member 4
3.2 Develop Initial System Architecture 4 days Wed 18-12-19 Mon 23-12-19 29FF
Development Team
Member 1, Development
Team Member 2,
Development Team
Member 3, Development
Team Member 4
3.3 Develop Initial Interface for the App 6 days Fri 20-12-19 Fri 27-12-19 30FS-2 days
Development Team
Member 1, Development
Team Member 2,
Development Team
Member 3, Development
Team Member 4
3.4 Develop the Internal Structure for Data Flow 6 days Mon 30-12-19 Mon 06-01-20 31
Development Team
Member 1, Development
Team Member 2,
Development Team
Member 3, Development
Team Member 4
3.5 Develop Database Structure for the App 2 days Tue 07-01-20 Wed 08-01-20 32
Development Team
Member 1, Development
Team Member 2,
Development Team
Member 3, Development
Team Member 4
3.6 Develop In-App Server Connection Setup 2 days Thu 09-01-20 Fri 10-01-20 33
Development Team
Member 1, Development
Team Member 2,
Development Team
Member 3, Development
Team Member 4
3.7 Design network infrastructure 5 days Mon 13-01-20 Fri 17-01-20 34
Development Team
Member 1, Development
Team Member 2,
Development Team
Member 3, Development
Team Member 4
3.8 Build the Front End and Back End Setup of the App 10 days Mon 20-01-20 Fri 31-01-20 35
Development Team
Member 1, Development
Team Member 2,
Development Team
Member 3, Development
Team Member 4
3.9 Develop Architecture for Online Payment and
Accounting 4 days Mon 20-01-20 Thu 23-01-20 36SS
Development Team
Member 1, Development
Team Member 2,
Development Team
Member 3, Development
Team Member 4
3.10 Conduct Another Team Meeting for the Development
of the Final Design 2 days Fri 24-01-20 Mon 27-01-20 37
Development Team
Member 1, Development
Team Member 2,
Development Team
Member 3, Development
Team Member 4
3.11 Develop Design Documentation for the App 5 days Tue 28-01-20 Mon 03-02-20 38
Development Team
Member 1, Development
Team Member 2,
Development Team
Member 3, Development
Team Member 4
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
4PROJECT MANAGEMENT
3.12 System Design Complete 0 days Mon 03-02-20 Mon 03-02-20 39
4 Procurement of Resources for the Project 20 days Tue 04-02-20 Mon 02-03-20
4.1 Purchasing Process from the Reliable Vendors 18 days Tue 04-02-20 Thu 27-02-20
4.1.1 Purchase Hardware As Specified During the Planning
Phase 3 days Tue 04-02-20 Thu 06-02-20 40 Hardware Costs[1],
Procurement Manager
4.1.2 Purchase Software As Specified During the Planning
Phase 3 days Thu 06-02-20 Mon 10-02-20 43SS+2 days Procurement Manager,
Software Costs[1]
4.1.3 Purchase Resources in order to Set Up the Network
Connection 3 days Tue 11-02-20 Thu 13-02-20 44 Other Additional Costs[1],
Procurement Manager
4.1.4 Hire ISP Providers 3 days Fri 14-02-20 Tue 18-02-20 45 Procurement Manager
4.1.5 Procure Server Resources 3 days Wed 19-02-20 Fri 21-02-20 46 Procurement Manager
4.1.6 Purchase Collaborative Tools 2 days Mon 24-02-20 Tue 25-02-20 47 Procurement Manager
4.1.7 Procure System Security Resources 2 days Wed 26-02-20 Thu 27-02-20 48 Procurement Manager
4.2 Conduct meeting 1 day Fri 28-02-20 Fri 28-02-20 49 Project Manager
4.3 Prepare documentation on purchased resources 1 day Mon 02-03-20 Mon 02-03-20 50 Procurement Manager
4.4 Completion of resource purchase 0 days Mon 02-03-20 Mon 02-03-20 51
5 Infrastructure Development for the Final Version of
the App 8 days Tue 03-03-20 Thu 12-03-20
5.1 Design and Build the Overall Server Infrastructure 3 days Tue 03-03-20 Thu 05-03-20 52 Development Team
Member 1
5.2 Design and Build the Network Structure 3 days Tue 03-03-20 Thu 05-03-20 54FF Development Team
Member 2
5.3 Design and Build the Database Structure 2 days Mon 09-03-20 Tue 10-03-20 55FF+3 days Development Team
Member 3
5.4 Conduct Team Meeting 1 day Wed 11-03-20 Wed 11-03-20 56 Information System
Developer
5.5 Documentation of the Infrastructure Development 1 day Thu 12-03-20 Thu 12-03-20 57 Development Team
Member 4
5.6 Complete the Initial Infrastructure Development 0 days Thu 12-03-20 Thu 12-03-20 58
6 Development 73 days Fri 13-03-20 Tue 23-06-20
6.1 Develop Interface for App Management System 10 days Fri 13-03-20 Thu 26-03-20 59 Development Team
Member 1
6.2 Develop Final Version of the Back End System 12 days Fri 27-03-20 Mon 13-04-20 61 Development Team
Member 1
6.3 Develop Final Version of the Front End System 9 days Tue 14-04-20 Fri 24-04-20 62 Development Team
Member 1
6.4 Develop Final User Interface of the App 5 days Mon 27-04-20 Fri 01-05-20 63 Development Team
Member 2
6.5 Integrate with Internal Server 4 days Mon 04-05-20 Thu 07-05-20 64 Development Team
Member 2
6.6 Set Up Database for Storing User Data 5 days Fri 08-05-20 Thu 14-05-20 65 Development Team
Document Page
5PROJECT MANAGEMENT
Member 2
6.7 Integrate Front End and Back End Systems 6 days Fri 15-05-20 Fri 22-05-20 66 Development Team
Member 3
6.8 Build and Integrate Internal Security Systems 3 days Mon 25-05-20 Wed 27-05-20 67 Development Team
Member 3
6.9 Develop Online Network Security Systems 3 days Thu 28-05-20 Mon 01-06-20 68 Development Team
Member 3
6.10 Design and Build Back Up System for Contingency 4 days Tue 02-06-20 Fri 05-06-20 69 Development Team
Member 4
6.11 Build Backup Server Architecture 5 days Mon 08-06-20 Fri 12-06-20 70 Development Team
Member 4
6.12 Discuss with Team Members Regarding Further
Development 2 days Mon 15-06-20 Tue 16-06-20 71 Development Team
Member 4
6.13 Documentation of the Development 5 days Wed 17-06-20 Tue 23-06-20 72 Information System
Developer
6.14 Development of the App Complete 0 days Tue 23-06-20 Tue 23-06-20 73
7 Detailed Testing of the App before Launch 34 days Wed 24-06-20 Mon 10-08-20
7.1 Develop Test Cases for Initiating Testing of the App 4 days Wed 24-06-20 Mon 29-06-20 74 Development Team
Member 2
7.2 Conduct Detailed Smoke Testing 3 days Tue 30-06-20 Thu 02-07-20 76 Development Team
Member 2
7.3 Conduct Systems Testing 4 days Fri 03-07-20 Wed 08-07-20 77 Development Team
Member 2
7.4 Conduct Unit Testing 3 days Thu 09-07-20 Mon 13-07-20 78
Development Team
Member 1, Development
Team Member 3
7.5 Conduct Detailed Integration Testing 2 days Tue 14-07-20 Wed 15-07-20 79
Development Team
Member 1, Development
Team Member 3
7.6 Conduct user acceptance test 2 days Thu 16-07-20 Fri 17-07-20 80
Development Team
Member 1, Development
Team Member 3
7.7 Analyse test results 3 days Mon 20-07-20 Wed 22-07-20 81 Development Team
Member 4
7.8 Report bugs and errors 5 days Thu 23-07-20 Wed 29-07-20 82 Development Team
Member 4
7.9 Conduct Team Meeting Regarding Test Results 3 days Thu 30-07-20 Mon 03-08-20 83 Development Team
Member 4
7.10 Documentation 5 days Tue 04-08-20 Mon 10-08-20 84 Information System
Developer
7.11 Testing complete 0 days Mon 10-08-20 Mon 10-08-20 85
8 System Deployment and Integration 31 days Tue 11-08-20 Tue 22-09-20
8.1 Deploy the New Online Server for Supporting the App 10 days Tue 11-08-20 Mon 24-08-20 86 Development Team
Member 1, Development
Team Member 2,
Development Team
Member 3, Development
Document Page
6PROJECT MANAGEMENT
Team Member 4
8.2 Deploy the Database 10 days Tue 25-08-20 Mon 07-09-20 88
Development Team
Member 1, Development
Team Member 2,
Development Team
Member 3, Development
Team Member 4
8.3 Complete Integration and Launch the System for
Internal Testing 5 days Tue 08-09-20 Mon 14-09-20 89
Development Team
Member 1, Development
Team Member 2,
Development Team
Member 3, Development
Team Member 4
8.4 Conduct User End Testing for the App 2 days Tue 15-09-20 Wed 16-09-20 90
Development Team
Member 1, Development
Team Member 2,
Development Team
Member 3, Development
Team Member 4
8.5 Review the Test Results 1 day Thu 17-09-20 Thu 17-09-20 91
Development Team
Member 1, Development
Team Member 2,
Development Team
Member 3, Development
Team Member 4
8.6 Receive Approval to Go Live 1 day Fri 18-09-20 Fri 18-09-20 92
Development Team
Member 1, Development
Team Member 2,
Development Team
Member 3, Development
Team Member 4
8.7 Conduct Final Meeting with the Management 1 day Mon 21-09-20 Mon 21-09-20 93 Information System
Developer
8.8 Complete Documentation of the Development Process 1 day Tue 22-09-20 Tue 22-09-20 94 Information System
Developer
8.9 Completion of deployment 0 days Tue 22-09-20 Tue 22-09-20 95
9 Develop Customer Support for the App 10 days Wed 23-09-20 Tue 06-10-20
9.1 Form Help Desk for Customer Queries 2 days Wed 23-09-20 Thu 24-09-20 96 Development Team
Member 1
9.2 Implementation of Online Chat System 5 days Fri 25-09-20 Thu 01-10-20 98 Development Team
Member 2
9.3 Documentation 3 days Fri 02-10-20 Tue 06-10-20 99 Information System
Developer
9.4 Support Setup Complete 0 days Tue 06-10-20 Tue 06-10-20 100
10 Develop Maintenance Plan 14 days Wed 07-10-20 Mon 26-10-20
10.1 Develop Schedule for System Maintenance 2 days Wed 07-10-20 Thu 08-10-20 101 Development Team
Member 3
10.2 Develop Guidelines for System Maintenance 2 days Fri 09-10-20 Mon 12-10-20 103 Development Team
Member 3
10.3 Develop Infrastructure Network Maintenance Plan 2 days Tue 13-10-20 Wed 14-10-20 104 Development Team
Member 3
10.4 Develop Plan for Database Maintenance 2 days Thu 15-10-20 Fri 16-10-20 105 Development Team
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7PROJECT MANAGEMENT
Member 4
10.5 Develop Plan for Server Maintenance 2 days Mon 19-10-20 Tue 20-10-20 106 Development Team
Member 4
10.6 Check system status 2 days Wed 21-10-20 Thu 22-10-20 107 Development Team
Member 4
10.7 Maintenance Plan Fully Developed 2 days Fri 23-10-20 Mon 26-10-20 108 Information System
Developer
10.8 Sign Off 0 days Mon 26-10-20 Mon 26-10-20 109
In the above table, the project is divided into a number of different activities that are
further divided into a number of different deliverables. The milestones are denoted with zero
durations. The deliverables have different types of relationships between them that include (F_S,
S_S, S_F, F_F), lags, leading times and others.
Moreover, it is also seen that the activities above are divided into a number of different
phases as shown in the following.
Document Page
Start Requirement Gathering Project Planning
App DesignProcurementApp Infrastructure
Development App Testing System Deployment
Customer SupportMaintenance Plan
End
8PROJECT MANAGEMENT
Again, based on the schedule above, the Gantt Chart can be developed as follows.
Document Page
9PROJECT MANAGEMENT
Figure: Gantt Chart of the Project
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
10PROJECT MANAGEMENT
Again, this Gantt chart can be further developed into Network Diagram using MS Project
as follows.
Figure: Part of the Network Diagram of the Project (Generated in MS Project)
3. Cost Management Plan
In order to develop the costs associated with the project, the following standard rates are
first determined and set.
Resource Name Type Initials Max.
Units Std. Rate Ovt. Rate Cost/Use
Project Manager Work P 100% $200.00/hr $50.00/hr $200.00
Information System Developer Work I 100% $160.00/hr $40.00/hr $25.00
Development Team Member 1 Work D 100% $50.00/hr $15.00/hr $5.00
Development Team Member 2 Work D 100% $50.00/hr $15.00/hr $5.00
Development Team Member 3 Work D 100% $50.00/hr $15.00/hr $5.00
Development Team Member 4 Work D 100% $50.00/hr $15.00/hr $5.00
Procurement Manager Work P 100% $150.00/hr $35.00/hr $5.00
Hardware Costs Material H $2,500.00 $0.00
Document Page
11PROJECT MANAGEMENT
Software Costs Material S $1,000.00 $0.00
Other Additional Costs Material O $1,000.00 $0.00
Now, these resources are assigned to each activity in the project as shown in the table
earlier. Based on the costs specified here, the cost estimation table for the entire project is as
follows.
WBS Task Name Cost
0 Development of Cab Application for TripTastic $286,485.00
1 Requirement Gathering and Analysis $16,200.00
1.1 Team Meeting Regarding the Project Requirements $12,600.00
1.1.1 Identify Business Opportunities $1,800.00
1.1.2 Identify Technical Requirements $1,800.00
1.1.3 Discuss Feasibility of the Project $1,800.00
1.1.4 Discuss Final End Goals of the Project $1,800.00
1.1.5 Identify the Overall Scope for the Project $1,800.00
1.1.6 Estimate Time Required for the Project $1,800.00
1.1.7 Estimate Overall Budget for the Project $1,800.00
1.2 Propose SLA Requirements for the App to be Developed $3,400.00
1.3 Requirements Gathering and Analysis Complete $200.00
2 Detailed Project Planning $33,810.00
2.1 Development of Project Charter and Project Plan Document $28,410.00
2.1.1 Develop List of Hardware Requirements for Developing the App $2,585.00
2.1.2 Develop List of Software Requirements for Developing the App $2,585.00
2.1.3 Develop Hardware and Software Implementation Strategy $1,305.00
2.1.4 Identify Team Staffing Requirements for the Project Purpose $1,305.00
2.1.5 Identify Primary and Secondary Features Required for the App $1,305.00
2.1.6 Break Down the Project Work Requirements using Work Breakdown
Structure $3,865.00
2.1.7 Prepare change management framework $3,865.00
2.1.8 Identify contingency $3,865.00
2.1.9 Identify security requirements $3,865.00
2.1.10 Prepare appropriate execution plan $3,865.00
Document Page
12PROJECT MANAGEMENT
2.2 Final Cost Estimation for the Project $1,800.00
2.3 Conduct Second Meeting with the Team Members $1,800.00
2.4 Finalise the Overall Project Plan $1,800.00
2.5 Project Planning Complete $0.00
3 Design of the Proposed App $83,420.00
3.1 Develop Initial Prototype of the App $9,620.00
3.2 Develop Initial System Architecture $6,420.00
3.3 Develop Initial Interface for the App $9,620.00
3.4 Develop the Internal Structure for Data Flow $9,620.00
3.5 Develop Database Structure for the App $3,220.00
3.6 Develop In-App Server Connection Setup $3,220.00
3.7 Design network infrastructure $8,020.00
3.8 Build the Front End and Back End Setup of the App $16,020.00
3.9 Develop Architecture for Online Payment and Accounting $6,420.00
3.10 Conduct Another Team Meeting for the Development of the Final Design $3,220.00
3.11 Develop Design Documentation for the App $8,020.00
3.12 System Design Complete $0.00
4 Procurement of Resources for the Project $30,340.00
4.1 Purchasing Process from the Reliable Vendors $27,335.00
4.1.1 Purchase Hardware As Specified During the Planning Phase $6,105.00
4.1.2 Purchase Software As Specified During the Planning Phase $4,605.00
4.1.3 Purchase Resources in order to Set Up the Network Connection $4,605.00
4.1.4 Hire ISP Providers $3,605.00
4.1.5 Procure Server Resources $3,605.00
4.1.6 Purchase Collaborative Tools $2,405.00
4.1.7 Procure System Security Resources $2,405.00
4.2 Conduct meeting $1,800.00
4.3 Prepare documentation on purchased resources $1,205.00
4.4 Completion of resource purchase $0.00
5 Infrastructure Development for the Final Version of the App $4,925.00
5.1 Design and Build the Overall Server Infrastructure $1,205.00
5.2 Design and Build the Network Structure $1,205.00
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
13PROJECT MANAGEMENT
5.3 Design and Build the Database Structure $805.00
5.4 Conduct Team Meeting $1,305.00
5.5 Documentation of the Infrastructure Development $405.00
5.6 Complete the Initial Infrastructure Development $0.00
6 Development $33,685.00
6.1 Develop Interface for App Management System $4,005.00
6.2 Develop Final Version of the Back End System $4,805.00
6.3 Develop Final Version of the Front End System $3,605.00
6.4 Develop Final User Interface of the App $2,005.00
6.5 Integrate with Internal Server $1,605.00
6.6 Set Up Database for Storing User Data $2,005.00
6.7 Integrate Front End and Back End Systems $2,405.00
6.8 Build and Integrate Internal Security Systems $1,205.00
6.9 Develop Online Network Security Systems $1,205.00
6.10 Design and Build Back Up System for Contingency $1,605.00
6.11 Build Backup Server Architecture $2,005.00
6.12 Discuss with Team Members Regarding Further Development $805.00
6.13 Documentation of the Development $6,425.00
6.14 Development of the App Complete $0.00
7 Detailed Testing of the App before Launch $20,885.00
7.1 Develop Test Cases for Initiating Testing of the App $1,605.00
7.2 Conduct Detailed Smoke Testing $1,205.00
7.3 Conduct Systems Testing $1,605.00
7.4 Conduct Unit Testing $2,410.00
7.5 Conduct Detailed Integration Testing $1,610.00
7.6 Conduct user acceptance test $1,610.00
7.7 Analyse test results $1,205.00
7.8 Report bugs and errors $2,005.00
7.9 Conduct Team Meeting Regarding Test Results $1,205.00
7.10 Documentation $6,425.00
7.11 Testing complete $0.00
8 System Deployment and Integration $49,130.00
Document Page
14PROJECT MANAGEMENT
8.1 Deploy the New Online Server for Supporting the App $16,020.00
8.2 Deploy the Database $16,020.00
8.3 Complete Integration and Launch the System for Internal Testing $8,020.00
8.4 Conduct User End Testing for the App $3,220.00
8.5 Review the Test Results $1,620.00
8.6 Receive Approval to Go Live $1,620.00
8.7 Conduct Final Meeting with the Management $1,305.00
8.8 Complete Documentation of the Development Process $1,305.00
8.9 Completion of deployment $0.00
9 Develop Customer Support for the App $6,675.00
9.1 Form Help Desk for Customer Queries $805.00
9.2 Implementation of Online Chat System $2,005.00
9.3 Documentation $3,865.00
9.4 Support Setup Complete $0.00
10 Develop Maintenance Plan $7,415.00
10.1 Develop Schedule for System Maintenance $805.00
10.2 Develop Guidelines for System Maintenance $805.00
10.3 Develop Infrastructure Network Maintenance Plan $805.00
10.4 Develop Plan for Database Maintenance $805.00
10.5 Develop Plan for Server Maintenance $805.00
10.6 Check system status $805.00
10.7 Maintenance Plan Fully Developed $2,585.00
10.8 Sign Off $0.00
This cost estimation process is known as bottom up estimation process and generally
provides very accurate results.
The budget is also estimated using top down estimation technique as follows.
Resource Name Estimated Work Salary / Cost ($) Total ($)
Project Manager 100 hrs 200 20000
Information System Developer 325 hrs 160 52000
Document Page
15PROJECT MANAGEMENT
Development Team Member 1 1000 hrs 50 50000
Development Team Member 2 1000 hrs 50 50000
Development Team Member 3 1000 hrs 50 50000
Development Team Member 4 1000 hrs 50 50000
Procurement Manager 150 hrs 150 22500
Hardware Costs 1 2500 2500
Software Costs 1 1000 1000
Other Additional Costs 1 1000 1000
TOTAL $ 299000
This is the top down approach for cost estimation, which is somewhat very inaccurate
because it does not take into consideration overtime costs and cost / usage and furthermore, the
working hours are just roughly estimated instead of using the work breakdown structure and
schedule.
Moreover, the time phased budget and the earned value reports are generated and shown
in the following diagrams. These diagrams have been generated following EVA (Earned Value
Analysis) and reflect the various cost aspects of the project.
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
16PROJECT MANAGEMENT
January 2017
March 2017
May 2017
July 2017
September 2017
November 2017
January 2018
March 2018
May 2018
July 2018
September 2018
November 2018
January 2019
March 2019
May 2019
July 2019
September 2019
November 2019
January 2020
March 2020
May 2020
July 2020
September 2020
-$150,000.00
-$100,000.00
-$50,000.00
$0.00
$50,000.00
$100,000.00
$150,000.00
$200,000.00
$250,000.00
$300,000.00
$350,000.00
Actual Cost Actual Fixed Cost Fixed Cost CV
Cumulative Cost SV Cost Budget Cost
BCWS BCWP ACWP
January 2017
March 2017
May 2017
July 2017
September 2017
November 2017
January 2018
March 2018
May 2018
July 2018
September 2018
November 2018
January 2019
March 2019
May 2019
July 2019
September 2019
November 2019
January 2020
March 2020
May 2020
July 2020
September 2020
-$100,000.00
-$90,000.00
-$80,000.00
-$70,000.00
-$60,000.00
-$50,000.00
-$40,000.00
-$30,000.00
-$20,000.00
-$10,000.00
$0.00
CV SV
Document Page
17PROJECT MANAGEMENT
January 2017
March 2017
May 2017
July 2017
September 2017
November 2017
January 2018
March 2018
May 2018
July 2018
September 2018
November 2018
January 2019
March 2019
May 2019
July 2019
September 2019
November 2019
January 2020
March 2020
May 2020
July 2020
September 2020
0
20
40
60
80
100
120
SPI CPI
Cumulative Percent Complete CV%
Percent Complete Remaining Actual Tasks
Remaining Tasks SV%
In addition to these, the baselines have been set in the Microsoft Project File.
Cost control is an important aspect of project management and it deals with the control of
the expenses encountered within the project. Often unchecked expenditures lead to massive cost
overrun that cannot be recovered if it is exceeds the budget by excessive margin. Hence, it is
important to constantly monitor the costs and ensure there are no over-expenditure in any
activity.
4. Conclusion
It can be thus concluded that the app development project will proceed further with the
schedule developed in this report as well as the costs estimated for the entire project. Moreover,
profit projections can be done using the EVA based on the cost estimations and cash flow
provided in this report.
chevron_up_icon
1 out of 18
circle_padding
hide_on_mobile
zoom_out_icon
logo.png

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]