This project plan addresses the BSBPMG522 Undertake Project Work unit, focusing on the initiation and planning phases for a project at Max Lionel Realty (MLR). The project aims to implement a program to enhance client goodwill and ensure ethical and legal compliance. The document includes a project brief outlining the purpose, background, and strategic context, along with a project scope document detailing in-scope and out-of-scope items, assumptions, and constraints. Stakeholder analysis, a communication plan, roles and responsibilities, and a project snapshot are also provided. The planning phase encompasses a work breakdown structure, project plan, Gantt chart, activities schedule, budget, risk register, and risk assessment form. The project involves informing agents about ethical obligations, promoting professional conduct, and developing various communication materials. The plan also considers resource management, deadlines, and potential risks. The project's success hinges on clearly defined requirements, active worker involvement, and effective communication. The provided templates guide the project's progression from initiation to planning, setting the stage for successful project execution.

Project Planning
Templates
BSBPMG522 Undertake project
work
Templates
BSBPMG522 Undertake project
work
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Table of Contents
1.1 – Initiation and scope........................................................................1
Project brief........................................................................................ 1
Project scope document.........................................................................2
Stakeholder analysis..............................................................................3
Communication plan (example)................................................................4
Roles and responsibilities.......................................................................5
Project snapshot.................................................................................. 6
1.2 – Planning......................................................................................... 7
Work breakdown structure.....................................................................7
Project plan........................................................................................ 8
Gantt chart....................................................................................... 12
Activities schedule.............................................................................. 13
Budget............................................................................................. 14
Risk register...................................................................................... 15
Risk assessment form..........................................................................16
1.3 – Implementation............................................................................17
Change requests................................................................................ 17
Issues log......................................................................................... 18
1.4 – Monitoring.................................................................................... 19
Status update report...........................................................................19
1.5 – Finalising and review....................................................................20
Budget variation report........................................................................20
Post-project review meeting.................................................................21
Handover report................................................................................ 22
Post-project review report....................................................................23
1.1 – Initiation and scope........................................................................1
Project brief........................................................................................ 1
Project scope document.........................................................................2
Stakeholder analysis..............................................................................3
Communication plan (example)................................................................4
Roles and responsibilities.......................................................................5
Project snapshot.................................................................................. 6
1.2 – Planning......................................................................................... 7
Work breakdown structure.....................................................................7
Project plan........................................................................................ 8
Gantt chart....................................................................................... 12
Activities schedule.............................................................................. 13
Budget............................................................................................. 14
Risk register...................................................................................... 15
Risk assessment form..........................................................................16
1.3 – Implementation............................................................................17
Change requests................................................................................ 17
Issues log......................................................................................... 18
1.4 – Monitoring.................................................................................... 19
Status update report...........................................................................19
1.5 – Finalising and review....................................................................20
Budget variation report........................................................................20
Post-project review meeting.................................................................21
Handover report................................................................................ 22
Post-project review report....................................................................23

BSBPMG522 Undertake project work Project Planning Templates
Page 1 of 17
Page 1 of 17
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

BSBPMG522 Undertake project work Project Planning Templates
1.1 – Initiation and scope
Project brief
Project purpose and rationale
Project title
Organizing program for Max Lionel Realty (MLR)
Project purpose
The organization “MLR” wants to implement a program in order to develop proper
good-will for the clients and for keeping the organization satisfied in context to
both legal as well as ethical based obligations.
Background and strategic context
Max Lionel Realty (MLR) is generally founded in 2008 by one of the property
developers that is Max Lionel. The company presently employs 100 people out
them 80 are agents of real estate who are licensed. The main mission of the
organization is to get highest return from the clients for delivering proper client
experience. In addition to this, in context to strategic, the organization wants to
achieve both its mission as well as vision by engaging the customers as well as
clients and well as by building goodwill reputation for integrity.
Priority
This project is the first priority before the organization in order to inform the
different agents about ethical obligations and for successfully encouraging high
standards for proper professional conduct.
Related projects
No such type of projects is undertaken in the past which are connected with the
implementation of the program in order to develop customer good-will and for
informing clients about the MLR commitments.
Project client/owner
The client is the person who generally wants to undertake the entire project
successfully so that the various goals and objectives of the project can be
achieved effectively.
Project sponsor
The project sponsor mainly funds the amount of money that is needed in order to
make an effective arrangement about the program in order to create proper
client-based goodwill and for keeping the organization satisfied in context to legal
as well as ethical related obligations. Additionally, they align the project with the
goals, objectives as well as business strategies.
Project manager
They help in organizing a program so that the legal as well as ethical obligations
of the customers get satisfied. In addition to this, they take the responsibility of
activity and resource planning, controlling time management as well as proper
estimation of the project budget.
Project status
Page 2 of 17
1.1 – Initiation and scope
Project brief
Project purpose and rationale
Project title
Organizing program for Max Lionel Realty (MLR)
Project purpose
The organization “MLR” wants to implement a program in order to develop proper
good-will for the clients and for keeping the organization satisfied in context to
both legal as well as ethical based obligations.
Background and strategic context
Max Lionel Realty (MLR) is generally founded in 2008 by one of the property
developers that is Max Lionel. The company presently employs 100 people out
them 80 are agents of real estate who are licensed. The main mission of the
organization is to get highest return from the clients for delivering proper client
experience. In addition to this, in context to strategic, the organization wants to
achieve both its mission as well as vision by engaging the customers as well as
clients and well as by building goodwill reputation for integrity.
Priority
This project is the first priority before the organization in order to inform the
different agents about ethical obligations and for successfully encouraging high
standards for proper professional conduct.
Related projects
No such type of projects is undertaken in the past which are connected with the
implementation of the program in order to develop customer good-will and for
informing clients about the MLR commitments.
Project client/owner
The client is the person who generally wants to undertake the entire project
successfully so that the various goals and objectives of the project can be
achieved effectively.
Project sponsor
The project sponsor mainly funds the amount of money that is needed in order to
make an effective arrangement about the program in order to create proper
client-based goodwill and for keeping the organization satisfied in context to legal
as well as ethical related obligations. Additionally, they align the project with the
goals, objectives as well as business strategies.
Project manager
They help in organizing a program so that the legal as well as ethical obligations
of the customers get satisfied. In addition to this, they take the responsibility of
activity and resource planning, controlling time management as well as proper
estimation of the project budget.
Project status
Page 2 of 17
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

BSBPMG522 Undertake project work Project Planning Templates
It is decided that the program will be organized within 35 days by utilizing budget
of around $15,000. The project status helps in showcasing that both the initiation
as well as planning phase of the project is complete. Moreover, the project
manager creates an assumption according to which the entire work of the project
generally gets finished as per the initial planning and the project team members
will be able to manage the hurdles of the project efficiently.
Special provisions
The different types of provisions which are undertaken are:
Health and safety: The organization wants to promote both health as
well as safety of the workers in the workplace so that so accidents issue
would occur. Additionally, the team members must work ethically in the
project for avoiding ethical issues.
Culture of workplace: It is quite necessary to develop proper working
culture such that the project workers can be capable of managing the
project work quite efficiently.
Project approvals
.
<Please fill> <Please fill>
Project Manager Project Sponsor
<Please fill> <Please fill>
Project Client/Owner Other
Project Title: Organizing program for
Max Lionel Realty (MLR)
Project Client:
<Please fill>
Date: 20-01-
2020
Version:
Project
Sponsor: Max
Lionel
Project
Manager:
<Please fill>
File Name: BSBPMG522
Undertake project work
Page x
of y
Project scope document
In Scope Out of scope
(exclusions)
Assumptions Constraints
In-scope of the
project include:
Organizing
a program
for MLR
Informing
clients as
well as
tenants
Out of scope
includes:
The facility of
training is not
given to the
workers
Project related
information is
not given to the
suppliers.
The assumptions
include:
Proper
arrangement for
the program will
generally get
completed
within $15,000.
The
stakeholders
The constraints
are mainly listed
below:
Increase of
project
budget can
cause
financial
issue.
Lack of
Page 3 of 17
It is decided that the program will be organized within 35 days by utilizing budget
of around $15,000. The project status helps in showcasing that both the initiation
as well as planning phase of the project is complete. Moreover, the project
manager creates an assumption according to which the entire work of the project
generally gets finished as per the initial planning and the project team members
will be able to manage the hurdles of the project efficiently.
Special provisions
The different types of provisions which are undertaken are:
Health and safety: The organization wants to promote both health as
well as safety of the workers in the workplace so that so accidents issue
would occur. Additionally, the team members must work ethically in the
project for avoiding ethical issues.
Culture of workplace: It is quite necessary to develop proper working
culture such that the project workers can be capable of managing the
project work quite efficiently.
Project approvals
.
<Please fill> <Please fill>
Project Manager Project Sponsor
<Please fill> <Please fill>
Project Client/Owner Other
Project Title: Organizing program for
Max Lionel Realty (MLR)
Project Client:
<Please fill>
Date: 20-01-
2020
Version:
Project
Sponsor: Max
Lionel
Project
Manager:
<Please fill>
File Name: BSBPMG522
Undertake project work
Page x
of y
Project scope document
In Scope Out of scope
(exclusions)
Assumptions Constraints
In-scope of the
project include:
Organizing
a program
for MLR
Informing
clients as
well as
tenants
Out of scope
includes:
The facility of
training is not
given to the
workers
Project related
information is
not given to the
suppliers.
The assumptions
include:
Proper
arrangement for
the program will
generally get
completed
within $15,000.
The
stakeholders
The constraints
are mainly listed
below:
Increase of
project
budget can
cause
financial
issue.
Lack of
Page 3 of 17

BSBPMG522 Undertake project work Project Planning Templates
Promoting
different
types of
professional
conduct
will be helpful in
executing the
project within
the time-period
Execution of all
the activities of
the project will
be done within
35 days.
management
knowledge
within the
team leaders
can block the
project
progress.
Project Title: Organizing program for
Max Lionel Realty (MLR)
Project Client:
<Please fill>
Date: 20-01-
2020
Version:
Project
Sponsor: Max
Lionel
Project
Manager:
<Please fill>
File Name: BSBPMG522
Undertake project work
Page x
of y
Stakeholder analysis
Name Work area Stakeholder
type (client,
end-user)
Impact on/by
project,
requirements,
success criteria
Pat
They take the
responsibility of
managing
commercial realty
aspects and also
assists in
successful
managing different
types of commercial
agents.
Manager of
commercial realty
The work activities related
with commercial gets
managed effectively.
Sam Lee
They help
managing
residential realty
and provides help
to residential
agents.
Manager of
residential realty
The work activities which
are associated with
residential realty gets
managed effectively.
Kim
They take the
responsibility of
effectively
managing the
operations.
Operational
manager
The program for creating
goodwill among the
customers gets
implemented on time.
Candidate 1 The project Project manager They help in directing and
Page 4 of 17
Promoting
different
types of
professional
conduct
will be helpful in
executing the
project within
the time-period
Execution of all
the activities of
the project will
be done within
35 days.
management
knowledge
within the
team leaders
can block the
project
progress.
Project Title: Organizing program for
Max Lionel Realty (MLR)
Project Client:
<Please fill>
Date: 20-01-
2020
Version:
Project
Sponsor: Max
Lionel
Project
Manager:
<Please fill>
File Name: BSBPMG522
Undertake project work
Page x
of y
Stakeholder analysis
Name Work area Stakeholder
type (client,
end-user)
Impact on/by
project,
requirements,
success criteria
Pat
They take the
responsibility of
managing
commercial realty
aspects and also
assists in
successful
managing different
types of commercial
agents.
Manager of
commercial realty
The work activities related
with commercial gets
managed effectively.
Sam Lee
They help
managing
residential realty
and provides help
to residential
agents.
Manager of
residential realty
The work activities which
are associated with
residential realty gets
managed effectively.
Kim
They take the
responsibility of
effectively
managing the
operations.
Operational
manager
The program for creating
goodwill among the
customers gets
implemented on time.
Candidate 1 The project Project manager They help in directing and
Page 4 of 17
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

BSBPMG522 Undertake project work Project Planning Templates
manager is
responsible for
directing and
managing the
project work
managing the project so
that it gets executed on
time.
Candidate 2 They help in
implementing
proper rules,
regulations as well
as code of conduct.
Legal manager They want to implement
proper rules and
regulations for avoiding
code of conduct.
Candidate 3 They take proper
responsibility of
supervising the
project work
Supervisor The supervisors generally
guide the project team and
assures that the project
work will be properly done.
Project Title: Organizing program for
Max Lionel Realty (MLR)
Project Client:
<Please fill>
Date: 20-01-
2020
Version:
Project
Sponsor: Max
Lionel
Project
Manager:
<Please fill>
File Name: BSBPMG522
Undertake project work
Page x
of y
Communication plan
What Who Purpose When/
frequency
Type/
methods
Project
kick off
informa
tion
All stakeholders Proper
information
about the
project roles of
stakeholders are
provided.
Before starting
of the project.
Report
Status
report
All project
stakeholders
Significant
information
about the
project progress
is generally
conveyed to the
stakeholders
During the
project progress
Progress report
is provided with
the help of
email.
Team
meeting
s
To the project
team
The team
leaders discuss
the problems
due to which
the project is
facing delay.
Weekly Face to face
conversation
Page 5 of 17
manager is
responsible for
directing and
managing the
project work
managing the project so
that it gets executed on
time.
Candidate 2 They help in
implementing
proper rules,
regulations as well
as code of conduct.
Legal manager They want to implement
proper rules and
regulations for avoiding
code of conduct.
Candidate 3 They take proper
responsibility of
supervising the
project work
Supervisor The supervisors generally
guide the project team and
assures that the project
work will be properly done.
Project Title: Organizing program for
Max Lionel Realty (MLR)
Project Client:
<Please fill>
Date: 20-01-
2020
Version:
Project
Sponsor: Max
Lionel
Project
Manager:
<Please fill>
File Name: BSBPMG522
Undertake project work
Page x
of y
Communication plan
What Who Purpose When/
frequency
Type/
methods
Project
kick off
informa
tion
All stakeholders Proper
information
about the
project roles of
stakeholders are
provided.
Before starting
of the project.
Report
Status
report
All project
stakeholders
Significant
information
about the
project progress
is generally
conveyed to the
stakeholders
During the
project progress
Progress report
is provided with
the help of
email.
Team
meeting
s
To the project
team
The team
leaders discuss
the problems
due to which
the project is
facing delay.
Weekly Face to face
conversation
Page 5 of 17
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

BSBPMG522 Undertake project work Project Planning Templates
What Who Purpose When/
frequency
Type/
methods
Sponsor
meeting
s
Financial
manager
The sponsor
provides details
about the
funded budget
to the
managers such
that the entire
project get
accomplished
within that
budget.
Once Meeting
Project Title: Organizing program for
Max Lionel Realty (MLR)
Project Client:
<Please fill>
Date: 20-01-
2020
Version:
Project
Sponsor: Max
Lionel
Project
Manager:
<Please fill>
File Name: BSBPMG522
Undertake project work
Page x
of y
Page 6 of 17
What Who Purpose When/
frequency
Type/
methods
Sponsor
meeting
s
Financial
manager
The sponsor
provides details
about the
funded budget
to the
managers such
that the entire
project get
accomplished
within that
budget.
Once Meeting
Project Title: Organizing program for
Max Lionel Realty (MLR)
Project Client:
<Please fill>
Date: 20-01-
2020
Version:
Project
Sponsor: Max
Lionel
Project
Manager:
<Please fill>
File Name: BSBPMG522
Undertake project work
Page x
of y
Page 6 of 17

BSBPMG522 Undertake project work Project Planning Templates
Roles and responsibilities
Role Name/s Responsibilities Signature/s
(if required)
Project client/owner <Please fill> The clients want to
undertake the project
such that the goals of
Max Lionel realty can
be fulfilled.
<Please fill>
Project sponsor/project
director/project board
<Please fill> They fund budget for
the project and
assists in providing
accounting success to
the entire project.
<Please fill>
Project manager <Please fill> They direct, plan as
well as manages the
activities of the
program so that the
clients can be
informed about the
plan.
<Please fill>
Manager of the project
manager
<Please fill> They assists in
finishing the work on
time so that the
organized program
helps in
communicating legal
obligations.
<Please fill>
Project team members <Please fill> The team members
help in promoting
professional conduct
and inform different
agents about legal
and ethical
obligations.
<Please fill>
Steering committee/
working party.
<Please fill> They give advice as
well as
recommendations for
successful project
execution.
<Please fill>
Project Title: Organizing program for
Max Lionel Realty (MLR)
Project Client:
<Please fill>
Date: 20-01-
2020
Version:
Project
Sponsor: Max
Project
Manager:
File Name: BSBPMG522
Undertake project work
Page x
of y
Page 7 of 17
Roles and responsibilities
Role Name/s Responsibilities Signature/s
(if required)
Project client/owner <Please fill> The clients want to
undertake the project
such that the goals of
Max Lionel realty can
be fulfilled.
<Please fill>
Project sponsor/project
director/project board
<Please fill> They fund budget for
the project and
assists in providing
accounting success to
the entire project.
<Please fill>
Project manager <Please fill> They direct, plan as
well as manages the
activities of the
program so that the
clients can be
informed about the
plan.
<Please fill>
Manager of the project
manager
<Please fill> They assists in
finishing the work on
time so that the
organized program
helps in
communicating legal
obligations.
<Please fill>
Project team members <Please fill> The team members
help in promoting
professional conduct
and inform different
agents about legal
and ethical
obligations.
<Please fill>
Steering committee/
working party.
<Please fill> They give advice as
well as
recommendations for
successful project
execution.
<Please fill>
Project Title: Organizing program for
Max Lionel Realty (MLR)
Project Client:
<Please fill>
Date: 20-01-
2020
Version:
Project
Sponsor: Max
Project
Manager:
File Name: BSBPMG522
Undertake project work
Page x
of y
Page 7 of 17
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

BSBPMG522 Undertake project work Project Planning Templates
Lionel <Please fill>
Project snapshot
Project snapshot
Name of project: Organizing program for Max Lionel Realty (MLR)
Project purpose:
The main purpose of the project is to create effective goodwill for different
customers and to effectively develop legal as well as ethical based obligations in
order to develop a program. This program will be organized for informing the
clients and for maintaining proper quality standards for the different
deliverables for successfully achieving client-based initiative.
Deliverables with timeframes
Deliverables Start Finish
Informing the
agents about
legal
obligations
Mon 10-
02-20
Tue 11-02-
20
High standards
promotion
Mon 10-
02-20
Tue 11-02-
20
Informing
clients
Wed 12-
02-20
Wed 12-02-
20
Developing
posters
Wed 12-
02-20
Thu 13-02-
20
Videos for
professional
illustration
Thu 13-
02-20 Fri 14-02-20
Literature and
flyer
development
Fri 14-
02-20
Thu 20-02-
20
Webpage
development
Mon 17-
02-20
Thu 20-02-
20
Training Fri 21-
02-20
Wed 26-02-
20
Undertaking
presentation
Fri 21-
02-20 Fri 21-02-20
Creating proper
ethical charter
Thu 27-
02-20 Fri 28-02-20
Stakeholders
The stakeholders mainly include:
Sponsor
Project manager
Supervisor
Legal manager
Manager of residential realty
Manager of commercial realty
Resources
The different resource include:
Cashflow: Budget of around $15,000
is funded for organizing the program
Human resources: The human
resources include:
Sponsor
Project manager
Risks
The risks that are mainly associated
with the entire project are elaborated
below:
Resource limitation: If the resources
that is required for the arrangement of
the program is not in proper quantity
then the project faces resource
limitation and due to which delay can
Page 8 of 17
Lionel <Please fill>
Project snapshot
Project snapshot
Name of project: Organizing program for Max Lionel Realty (MLR)
Project purpose:
The main purpose of the project is to create effective goodwill for different
customers and to effectively develop legal as well as ethical based obligations in
order to develop a program. This program will be organized for informing the
clients and for maintaining proper quality standards for the different
deliverables for successfully achieving client-based initiative.
Deliverables with timeframes
Deliverables Start Finish
Informing the
agents about
legal
obligations
Mon 10-
02-20
Tue 11-02-
20
High standards
promotion
Mon 10-
02-20
Tue 11-02-
20
Informing
clients
Wed 12-
02-20
Wed 12-02-
20
Developing
posters
Wed 12-
02-20
Thu 13-02-
20
Videos for
professional
illustration
Thu 13-
02-20 Fri 14-02-20
Literature and
flyer
development
Fri 14-
02-20
Thu 20-02-
20
Webpage
development
Mon 17-
02-20
Thu 20-02-
20
Training Fri 21-
02-20
Wed 26-02-
20
Undertaking
presentation
Fri 21-
02-20 Fri 21-02-20
Creating proper
ethical charter
Thu 27-
02-20 Fri 28-02-20
Stakeholders
The stakeholders mainly include:
Sponsor
Project manager
Supervisor
Legal manager
Manager of residential realty
Manager of commercial realty
Resources
The different resource include:
Cashflow: Budget of around $15,000
is funded for organizing the program
Human resources: The human
resources include:
Sponsor
Project manager
Risks
The risks that are mainly associated
with the entire project are elaborated
below:
Resource limitation: If the resources
that is required for the arrangement of
the program is not in proper quantity
then the project faces resource
limitation and due to which delay can
Page 8 of 17
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

BSBPMG522 Undertake project work Project Planning Templates
Supervisor
Legal manager
Manager of residential realty
Manager of commercial realty
Equipment’s: It mainly includes
software, computers, hard disk and
more.
occur.
Deadlines: Deadline issue occur due
to inappropriate tracking and it further
block the progress of the project and
increases required financial budget.
Budget: Lack of budget estimation
while undertaking the project can
cause a lot of financial hurdles during
the project progress.
Interdependencies
The project is mainly dependents on
the human resources as well as
financial resources. If both of the
resources are used properly then the
project can gets accomplished on
time.
Success criteria
The ways through which the project
can be made successful are listed
below:
Defining the needs and
requirements of the project
properly in the initial phase.
Ensuring proper involvement of the
workers for making sure that the
entire work will get accomplished
within the time as estimated.
Ensuring proper communication
with the team members of the
project.
Project Title: Organizing program for
Max Lionel Realty (MLR)
Project Client:
<Please fill>
Date: 20-01-
2020
Version:
Project
Sponsor: Max
Lionel
Project
Manager:
<Please fill>
File Name: BSBPMG522
Undertake project work
Page x
of y
Page 9 of 17
Supervisor
Legal manager
Manager of residential realty
Manager of commercial realty
Equipment’s: It mainly includes
software, computers, hard disk and
more.
occur.
Deadlines: Deadline issue occur due
to inappropriate tracking and it further
block the progress of the project and
increases required financial budget.
Budget: Lack of budget estimation
while undertaking the project can
cause a lot of financial hurdles during
the project progress.
Interdependencies
The project is mainly dependents on
the human resources as well as
financial resources. If both of the
resources are used properly then the
project can gets accomplished on
time.
Success criteria
The ways through which the project
can be made successful are listed
below:
Defining the needs and
requirements of the project
properly in the initial phase.
Ensuring proper involvement of the
workers for making sure that the
entire work will get accomplished
within the time as estimated.
Ensuring proper communication
with the team members of the
project.
Project Title: Organizing program for
Max Lionel Realty (MLR)
Project Client:
<Please fill>
Date: 20-01-
2020
Version:
Project
Sponsor: Max
Lionel
Project
Manager:
<Please fill>
File Name: BSBPMG522
Undertake project work
Page x
of y
Page 9 of 17

BSBPMG522 Undertake project work Project Planning Templates
1.2 – Planning
Work breakdown structure
Level 1 Level 2 Level 3
Implementation of
program for Max
Lionel realty
Initiation phase
Developing the
business plan
Undertaking proper
feasibility study
Developing charter for
the project
Appointing project
team
Planning phase
Developing the project
plan
Developing resource
plan
Developing financial
plan
Developing quality
management plan
Project design phase
Developing the design
phase of the project
Getting approval
Approval received
Project development
phase
Page 10 of 17
1.2 – Planning
Work breakdown structure
Level 1 Level 2 Level 3
Implementation of
program for Max
Lionel realty
Initiation phase
Developing the
business plan
Undertaking proper
feasibility study
Developing charter for
the project
Appointing project
team
Planning phase
Developing the project
plan
Developing resource
plan
Developing financial
plan
Developing quality
management plan
Project design phase
Developing the design
phase of the project
Getting approval
Approval received
Project development
phase
Page 10 of 17
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 37
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.