This project provides a comprehensive plan for renovating a kitchen, detailing the various stages from initiation to completion. It includes a project description outlining the goals and objectives, estimated duration, and the approximate number of work breakdown structure (WBS) activities. The statement of work outlines deliverables, required resources, and governing factors such as budget and deadlines. The WBS breaks down the project into manageable tasks, including design, renovation, and installation phases. A workflow diagram visualizes the project's timeline and dependencies, while a risk analysis table identifies potential risks and mitigation strategies. The project covers various aspects, from designing the demolition plan, procuring materials, installing appliances, and conducting tests. The project is designed to be completed within 6 months and a budget of $52,000. The successful completion of this project involves stakeholder approval and payment procedures, ensuring the renovated kitchen is ready for use, and the project is signed off. The project concludes with a bibliography of resources used.
Document Page
Running head: PROJECT ON RENOVATING A KITCHEN SETUP
Project on Renovating a Kitchen Setup
Name of the Student
Name of the University
Author’s note
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
1PROJECT ON RENOVATING A KITCHEN SETUP
Table of Contents
1. Project Description......................................................................................................................2
2. Estimated Duration of Project.....................................................................................................3
3. Approximate Number of WBS Activities....................................................................................3
4. Statement of Work.......................................................................................................................3
5. Work Breakdown Structure.........................................................................................................5
6. Workflow Diagram......................................................................................................................6
7. Risk Analysis Table.....................................................................................................................7
Bibliography....................................................................................................................................8
Document Page
2PROJECT ON RENOVATING A KITCHEN SETUP
1. Project Description
This project is based on the topic of ‘Kitchen Renovation’. This project is based on
detailing the structure of work that would be done during the renovation phase of an existing
kitchen. This project would be extremely be useful for the generation of a vast number of ideas
that could be implemented during designing of the schedule of the project. Each of the tasks that
would be performed within the project have to be dealt with perfection in order to complete the
renovation project within the proper time.
The project based on renovating an existing kitchen would require an intense form of
designing and planning. During the initiation phase of the project, the project manager who
would be entitled for the project would be responsible for designing a plan for conducting the
entire set of activities within the later part of the project. A proper kind of source of investment
would be required for conducting the entire list of activities. After the investor would secure the
source of funding, the project manager would select the proper interior designers who would be
responsible for renovating the entire kitchen. After conducting the research on selection of the
proper interior designer, the procurement of materials needed to be installed in the new kitchen
would be chosen and assembled together.
In the next phase of the project, the interior designer would hire different contractors and
thus start with the work of the project. They would clean the interiors of the kitchen and thus
make a proper form of work setup for the project. The interiors of the kitchen would be properly
cleaned and then a new coating of paint would be applied. The electric supply would be checked
by a group of efficient electricians and then the previously bought appliances would be installed
within the kitchen. After a proper installation of the cabinetry, refrigerator, dishwasher and
Document Page
3PROJECT ON RENOVATING A KITCHEN SETUP
microwave within the kitchen, each of the appliances would be checked. This step would be
highly required for checking that the appliances are in proper working condition and would suit
the needs of the homeowner. After a proper check of each of the appliances, the contractors
would again be called for cleaning the entire trash that had been made within the kitchen during
the work of renovation. This would take a few amount of time to complete the phase.
After finishing off with the cleaning part of the kitchen, the project manager would hand
over the newly renovated kitchen to the homeowner for their approval. During the period of
approval, each of the documents that were made during the design phase of the project would be
signed by the homeowner and thus the project would reach till its completion. The procedure of
each of the payments would be made to the recipients based on their inputs within the project.
The homeowner would also check whether the project has been completed within the limited
time period and budget. Based on the entire success of the project, the project would be signed
off and thus the entire renovated kitchen would be ready for use. The successful completion of
the project is highly needed in order to receive a proper feedback from the stakeholders involved
within the project.
2. Estimated Duration of Project
The estimated duration of the project is 6 months.
3. Approximate Number of WBS Activities
The approximate number of WBS activities is 50.
4. Statement of Work
In the statement of work based on the ‘Kitchen Renovation’ project, the entire list of
detail of work that would be done within the project would be included. The entire set of
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
4PROJECT ON RENOVATING A KITCHEN SETUP
deliverables included within the project are – Real-time updates on weekly status and financial
reports of each of the phases. The project would also be completed as per the required success
criteria.
The project would be completed within 6 months.
The individual tasks that would lead to the completion of the entire project deliverable
are – Project Initiation, Designing of demolition of existing kitchen setup, designing the new
setup as per the plan, Installation of appliances, testing of equipment, Procedure of Clean-up and
Closure of Project.
The resources required within the project are – Project Manager, Kitchen Interior
Designer, Sub-Contractors and Loan Officer. The different equipment that would be required
within the new developed kitchen are refrigerator, dishwasher, kitchen chimney and stove.
The project would mainly be governed by the homeowner who has assigned the task of
renovation to the project manager and designer. However, the project would need to be finished
within a limited budget of $52,000. The deadline for the entire project is also limited to a period
of 6 months.
Document Page
5PROJECT ON RENOVATING A KITCHEN SETUP
5. Work Breakdown Structure
Project on Kitchen
Renovation
Start Initiation of the Project
Design of goals and
objectives of the project
Development of
Preliminary design
Preparing of investment
papers for the project
Hiring of funding source
for the project
Selection of Kitchen
Interior Designer
Selection of
subcontractors
Procurement of materials
based on installation
within kitchen
Completion of Initiation
Phase
Design Phase
Preparing of Demolition
plan of Existing Kitchen
Plan Pass by Project
manager and Homeowner
Shifting the Kitchen Space
to a separate location
Setting up of a temporary
kitchen during the
renovation phase
Demolishing of old
kitchen workspace
Rubbing and cleaning of
Kitchen walls
Applying a temporary
paint coating on the walls
Completion of Design
Phase
Renovation Phase
Plan for new kitchen
design
Plan Pass by Homeowner
Preparing of
Subcontractors and
detailing the task workout
Bringing the initial
procurement materials
Painting the walls
Installation of appliances
Checking of Electric
Supply
Installation of cabinetry
Installation of Refrigerator,
Microwave and
Dishwasher
Shifting the Temporary
Kitchen
Completion of Installation
Phase
Testing of Equipments
Testing of the installed
components
Testing of the entire
kitchen setup
Performing of a demo
Kitchen work
Completion of Testing
Phase
Clean-up Procedural
Phase
Shifting of the leftover
paint boxes
Removal of unused
material
Removal of trash
Performing of clean-up
Completion of clean-up
phase
Project Closure
Assuring project manager
of fulfillment of renovation
work
Sign off on procurement
Sign off on contractors
Sign off of designer
Completing the payment
procedures
Completion of Project
Closure Phase
Stop
(Fig 1: Diagram of Work Breakdown Structure)
(Source: Created by author)
Document Page
6PROJECT ON RENOVATING A KITCHEN SETUP
6. Workflow Diagram
ES DUR EF 1 5 6 9 5 14 14 4 18 18 1 19 19 12 31 31 0 31
LS SLACK LF 130 5 135 135 0 135 135 0 135 135 0 135 135 0 135 135 0 135
0 1 1
126 2 128
1 8 9 9 8 17 17 8 25
128 0 128 128 0 128 128 7 135 31 5 36 36 0 36 36 3 39 39 1 40 40 8 48 48 8 56 56 9 65 65 0 65
135 0 135 135 0 135 135 0 135 135 0 135 135 0 135 135 0 135 135 0 135 135 0 135
65 7 72 72 0 72 72 5 77 77 9 86 86 19 105
139 0 139
135 0 135 135 0 135 135 0 135 135 0 135 135 0 135
139 0 139
105 4 109 109 7 116 116 4 120 120 3 123 123 0 123
135 2 137 137 0 137 137 0 137 137 0 137 137 0 137 123 2 125 127 0 127
137 2 139 139 0 139
123 3 126 126 1 127 127 2 129 129 2 131 131 1 132 132 2 134 134 0 134
139 0 139 139 0 139 139 0 139 139 0 139 139 0 139 139 0 139 139 0 139
134 0 134 134 1 135 135 1 136 136 1 137 137 2 139 139 0 139
139 0 139 139 0 139 139 0 139 139 0 139 139 0 139 139 0 139
2.1 Pre paring of Demolition plan
1. Start
1.2. De sign of goals
1.3. Preliminary design
1.3 Pre paring of investment pape rs
1.5 Selection of De signe r 1.6 Selection of subcontractors
1.4 Hiring of funding source 1.4 Hiring of f unding source 1.7 Procurement of materials 1.8 Completion of Initiation Phase
3.5 Painting the walls
2.2 Plan Pass 2.3 Shifting the Kitchen 2.4 Setting up Temporary Kitche n 2.5 Demolishing of old kitchen 2.6 Rubbing and cleaning 2.7 Applying a temporary paint 2.8 Completion of De sign Phase
3.1 Plan for ne w kitchen design 3.2 Plan Pass 3.3 Preparing of Subcontractors 3.4 Bringing initial procurement
6.3 Removal of Trash
4.1 Che cking of Ele ctric Supply 4.2 Installation of cabinetry 4.3 Installation of Refrigerator 4.4 Shifting the Temporary Kitchen 4.5 Completion of Installation Phase
5.1 Te sting of the installed components
5.2 Te sting of the entire kitchen setup 5.3 Performing of a demo Kitchen work
5.4 Completion of Testing Phase
6.1 Shifting of the leftover paint boxes 6.2 Removal of unused material
7.5 Completing the payment procedures 7.6 Completion of Project Closure Phase
8. Stop
6.4 Performing of clean-up 6.5 Completion of clean- up phase
7.1 Assuring project manager of f ulfillment 7.2 Sign off on procurement 7.3 Sign off on contractors 7.4 Sign off of de signe r
(Fig 2: The Workflow Diagram)
(Source: Created by author)
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7PROJECT ON RENOVATING A KITCHEN SETUP
7. Risk Analysis Table
NAME OBJECTIVE
REF/ID PRE-MITIGATION DEPARTMENT/
LOCATION MITIGATIONS / WARNINGS / REMEDIES POST-
MITIGATION
RISK RISK SEVERITY RISK LIKELIHOOD RISK LEVEL RISK SEVERITY RISK LIKELIHOOD RISK LEVEL ACCEPTABLE
TO PROCEED?
1 The demolition plan might not work
properly UNDESIRABLE IMPROBABLE EXTREME
Projec t Manager,
Kitc hen Interior
Designer
Plan should be set suc c essfully UNDESIRABLE IMPROBABLE EXTREME YES
2 The projec t would not be c ompleted
within the estimated budget UNDESIRABLE IMPROBABLE MEDIUM Projec t Manager The financ ial budget should be planned
properly UNDESIRABLE IMPROBABLE MEDIUM YES
3 The projec t would not be c ompleted
within the deadline AC C EPTABLE POSSIBLE MEDIUM Projec t Manager The schedules should be designed
properly AC CEPTABLE POSSIBLE MEDIUM YES
4
The kitchen renovation project might
incure other consequences on financial
loss
INTOLERABLE IMPROBABLE HIGH Projec t Manager The financ ial budget should be planned
properly INTOLERABLE IMPROBABLE HIGH NO
(Fig 3: Diagram of Risk Analysis Table)
(Source: Created by author)
Document Page
8PROJECT ON RENOVATING A KITCHEN SETUP
Bibliography
Davis, A. and Fisher, R., 2015. Kitchen and Bath Sustainable Design: Conservation, Materials,
Practices. John Wiley & Sons.
Fager-Pintilä, E., 2017. Improving productivity in pipe renovation project by standardized
solutions.
Lad, V.H., Patel, H.R., Rathod, M.H.A., Lad, V.H., Patel, H.R. and Rathod, M.H.A., 2016.
Application of Building Information Modeling (BIm) for Renovation Project. International
Journal, 2, pp.282-287.
Mjörnell, K., 2015, December. A Strong Research Environment for Sustainable Renovation
Established in Sweden. In Smart and Sustainable Built Environment (SASBE) Conference
2015 (p. 127).
Naaranoja, M., Kähkönen, K. and Keinänen, M., 2016. Role of Power and Sense Making in the
Briefing of a Small Renovation Project. Creating built environments of new opportunities, 1,
p.611.
Vrijhoef, R., 2016, July. Effects of Lean Work Organization and Industrialization on Workflow
and Productive Time in Housing Renovation Projects. In Proceedings of the 24th Annual
Conference of the International Group for Lean Construction.