This project management report outlines a comprehensive plan for developing and managing a recycling facility at UWE Frenchay Campus. The report begins with a business case emphasizing the environmental and economic benefits of the project, including waste reduction and resource conservation. It then details the project's aim, objectives, and scope, along with a list of deliverables such as a work breakdown structure, activity list, team structure, responsibility matrix, Gantt chart, and risk management plan. The project adopts an agile methodology, highlighting its iterative approach and flexibility. The report covers technical requirements, stakeholder analysis, and a detailed breakdown of project activities, timelines, and resource allocation. It also includes a risk management plan and a lesson report, providing a complete overview of the project's lifecycle, from initiation to completion, and the methodology applied. The project is estimated to cost $142,800 and take 74 days to complete.
tabler-icon-diamond-filled.svg

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
Running head: PROJECT MANAGEMENT
Project management
Name of Student-
Name of University-
Author’s Note-
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
1PROJECT MANAGEMENT
Table of Contents
Project title:......................................................................................................................................1
Project Initiation Plan......................................................................................................................1
Business case...............................................................................................................................1
Project Aim..................................................................................................................................3
Project Objectives........................................................................................................................4
Project Scope...............................................................................................................................4
Project Deliverables.....................................................................................................................4
Stakeholders and Technical requirements...................................................................................5
Technical requirements................................................................................................................5
Work Breakdown Structure.............................................................................................................6
Activity list......................................................................................................................................6
Project Team Structure and Responsibility Matrix.........................................................................8
Project Team Structure................................................................................................................8
Responsibility Matrix..................................................................................................................9
Gantt chart and AON network.......................................................................................................14
Gantt Chart.................................................................................................................................14
AON Diagram............................................................................................................................15
Project Milestones.....................................................................................................................15
Resource Sheet...............................................................................................................................16
Risk Management plan..................................................................................................................17
Lesson Report................................................................................................................................18
Bibliography..................................................................................................................................20
Document Page
2PROJECT MANAGEMENT
Project title:
Managing the development and running of a recycling facility to facilitate the processing
of the plastic waste that is produced at UWE Frenchay Campus.
Project Initiation Plan
Business case
The main reason for developing this project plan is to manage the development as well as
run a recycling facility that helps to process the plastic waste that in produced in the undertaken
campus. The campus that is chosen for this research plan is UWE Frenchay Campus having its
main campus in UWE Bristol.
The benefits of this project is reducing the amount of waste that are sent to the land and
the incinerators. By implementing this project plan, the natural resources including minerals,
timber, as well as water can be conserved from being getting polluted. This project plan will also
increase the economic security that can tap the materials that comes from the domestic areas.
With the recycling of the waste materials, pollution can be reduced as because this project plan
includes collecting of raw materials. As this project deals with plastic recycling, the project
needs to save the energy by the process of recycling. All the valuable resources can be conserved
by recycling process that is proposed in this project plan. This project will also benefit the
workers of the manufacturing industries as because more job vacancies are created in those
industries.
The best approach that can be used for carrying out this project plan is agile methodology
of project management (Binder 2016). The agile methodology is the best suited methodology
that can be used in project as because this project is an iterative method as well as follows
Document Page
3PROJECT MANAGEMENT
incremental way of managing the project. The agile methodology is a particular type of process
that satisfies the demands as well as provides solutions that evolve via collaborative effort that
helps in self organizing as well as includes teams that are cross-functional along with their
customers. This agile methodology improves the inadequacies in the waterfall model. The agile
methodology that is used for this project meets demand of high competitive as well as includes
constant movement in the industry.
The agile methodology used in this project management will stems all the values as well
as principles that are included in the Agile Manifesto. This methodology promotes iteration for
developing the project and includes testing process and quality assurance process in the project
(Kerzner 2017). The agile methodology provides flexibility to the developer of the project. The
activities in the agile methodology are divided in to sprints that helps the developers to carry the
project more smoothly. The agile methodology used in conducting this project plan includes four
values as well as includes 12 main key principles. The values that are included in the agile
approach are:
1. There should be individual as well as interaction in the project processes as well as in
project tools.
2. The software that is being working should have comprehensive documentation.
3. There should be customer collaboration in the project over the contact negotiation.
4. Respond should be given for changing the plan of the project.
The principles associated with this project are:
1. The customer satisfaction is enhanced through early delivery of the project plan.
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
4PROJECT MANAGEMENT
2. The agile methodology helps to accommodate the changing requirement in the
development process of the project plan.
3. Frequent delivery with the software that is being used for.
4. This helps to enable the interactions that can be done face-to-face.
5. The working of the software is considered as some primary measure for the project
progress.
6. The process of agile helps to support many consistent pace of development.
7. Proper attention is given to the technical detail as well as helps in designing increases the
agility.
8. This methodology is very simple.
9. The working software is the main primary measure for the progress.
10. Provides supports, motivation as well as trust in the people involved.
11. Self-organizing enhances team with great architectures, designs as well as requirements.
12. The regular reflections helps to make the project more effective.
The total cost of the project that is being undertaken is $142,800 and it is generally
expected that all project gets complete within the schedule time and scheduled budget. The total
time that is taken to complete this project is 74 days.
Project Aim
The main aim of the project is developing project plan that will help to manage a
recycling facility as well as running the facility that helps to facilitate processing of the plastic
waste produced in the UWE Frenchay Campus. The project aims to complete the recycling
process of the plastic waste in the facility recycling center. The project also aim to select a
project methodology that can deliver the project successfully.
Document Page
5PROJECT MANAGEMENT
Project Objectives
The objectives that are included in this project are:
To carry out the requirement analysis for recycling waste materials.
To investigate the requirement analysis for developing the project.
To study the details of process of recycling the waste materials.
To develop a project plan to manage and maintain the waste facility to recycle waste.
To find out the risk assessment that are included in the project.
Project Scope
The main scope of this project is to provide a detailed plan schedule that will help to
collected the waste materials in UWE Frenchay Campus and manufacture them in the facility
centers. The project scope also analyze the risks assessment that are carried out for carrying out
this project. The project also aims in completing the project within a certain project time
schedule and budget schedule.
Project Deliverables
The project deliverables that are to be delivered in this project are the work breakdown
structure of the project that defines the tasks that are needed for conducting as well as managing
the project. This project also shows the activity list that are to be included in the project plan.
There is also a there is a project team structure that is included in developing different tasks in
the project. This project also includes responsibility matrix that specifies the roles as well as the
responsibilities included for all the team members in the project.
The project also includes a Gantt chart as well as AON network that states the critical
path as well as project milestones included in the project. The report also states a resource sheet
Document Page
6PROJECT MANAGEMENT
that are included with the assignment along with the project cost. The project management plan
is also included in the project that states the internal risks as well as the external risks that are
associated with the project.
Stakeholders and Technical requirements
The stakeholders who are related with this project are:
1. The owner of UWE Frenchay Campus
2. The CEO of UWE Frenchay
3. Project manager
4. Finance manager
5. Risk Analyst
6. Manufacturer
7. 4 workers
8. One quality analyst
Technical requirements
The technical requirements that are included in the project are mainly the technical issues
that are to be considered in the project. There are different aspects that are included in technical
requirement that includes performance, reliability, as well as availability that are to be include in
the project. In this project development plan, the technical requirements mainly includes the
technical requirements such as MS project software for developing the project plan, the standards
that are to be included in developing the project plan.
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7PROJECT MANAGEMENT
Work Breakdown Structure
Recycling Plastic waste
Project Inititaion
Project model
design
Project Survey
Collecting project
materials
Initiating project
Architecture
Project Development
Developing
earthwork and
foundation
Inspection of
Foundation
Developing the
systems
Carrying out
requirement analysis
Collecting of waste
materials
Gathering of
equipment
Carrying out
procurement
analysis
Gathering of waste
materials
Taking the waste
materials to waste
treatment plant
Recycling process
Installation of waste
plant
Processing the
waste
Manufacturing of the
waste
Developing new
products
Project Closure
Checking the
checklist
Checking budget
Maintenance
Campaign waste
management plan
Project Sign off
Figure 1: Work Breakdown Structure
(Source: Created by author)
Activity list
Task Name Duration Start Finish
A
Project model design 3 days
Mon
22/07/19
Wed
24/07/19
B Project Survey 2 days Thu 25/07/19 Fri 26/07/19
C
Collecting project materials 5 days Thu 25/07/19
Wed
31/07/19
D Initiating project Architecture 2 days Thu 1/08/19 Fri 2/08/19
Document Page
8PROJECT MANAGEMENT
E
Developing earthwork and foundation 6 days
Mon
29/07/19
Mon 5/08/19
F Inspection of Foundation 3 days Tue 6/08/19 Thu 8/08/19
G Developing the systems 5 days Fri 9/08/19 Thu 15/08/19
H
Carrying out requirement analysis 4 days Fri 16/08/19
Wed
21/08/19
I Gathering of equipment 2 days Thu 22/08/19 Fri 23/08/19
J Carrying out procurement analysis 2 days Thu 22/08/19 Fri 23/08/19
K Gathering of waste materials 10 days Thu 22/08/19 Wed 4/09/19
L Taking the waste materials to waste treatment
plant
8 days Thu 5/09/19
Mon
16/09/19
M
Installation of waste plant 10 days Tue 17/09/19
Mon
30/09/19
N Processing the waste 6 days Tue 1/10/19 Tue 8/10/19
O
Manufacturing of the waste 6 days Wed 9/10/19
Wed
16/10/19
P
Developing new products 12 days Tue 1/10/19
Wed
16/10/19
Q Checking the checklist 2 days Thu 17/10/19 Fri 18/10/19
Document Page
9PROJECT MANAGEMENT
R
Checking budget 1 day
Mon
21/10/19
Mon
21/10/19
S
Maintenance 5 days Tue 22/10/19
Mon
28/10/19
T Campaign waste management plan 3 days Tue 29/10/19 Thu 31/10/19
U Project Sign off 0 days Thu 31/10/19 Thu 31/10/19
Project Team Structure and Responsibility Matrix
Project Team Structure
Team Structure Responsibility
Project manager The project manager has the responsibility
manage the project and complete the project
on time.
Finance manager The finance manage has the responsibility to
manage the project’s budget and keep the
project budget as per the project schedule.
Risk Analyst The risks analyst helps to find out the risks
that are included in the project. the risks
analyst helps to mitigate all the risks that are
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
10PROJECT MANAGEMENT
included in the project.
Manufacturer The manufacturer included in this project has
the responsibility to make new products from
the recycled ones.
Quality Analyst The quality analyst analyzes the quality of the
product that are being recycled from the waste
materials.
Workers The workers included in the project helps to
collect the waste material inside the campus
and are also involved in manufacturing center
for recycling the waste materials to new
products.
Responsibility Matrix
Resources
Activities
Proje
ct
Man
ager
Procure
ment
Manage
r
Fina
nce
Man
ager
Risk
Anal
yst
Manufac
turer
Wor
ker
1
Wor
ker
2
Wor
ker
3
Wor
ker
4
Qua
lity
Anal
yst
Project
model
design
R A C I I
Project C A R I
Document Page
11PROJECT MANAGEMENT
Survey
Collectin
g project
materials
R C I I
Initiating
project
Architect
ure
C A R I
Developi
ng
earthwor
k and
foundati
on
I C R R R A
Inspectio
n of
Foundati
on
R C I I R
Developi
ng the
systems
C R I A
Document Page
12PROJECT MANAGEMENT
Carrying
out
requirem
ent
analysis
A I I R
Gatherin
g of
equipme
nt
R C I A
Carrying
out
procure
ment
analysis
R A I
Gatherin
g of
waste
materials
I C R R
Taking
the waste
materials
to waste
R A C
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
13PROJECT MANAGEMENT
treatment
plant
Installati
on of
waste
plant
I A R
Processi
ng the
waste
R A C R R I
Manufac
turing of
the waste
C A R R R I
Developi
ng new
products
C A R R R I
Checkin
g the
checklist
R A C I
Checkin
g budget
R I C
Maintena R R C A I
Document Page
14PROJECT MANAGEMENT
nce
Campaig
n waste
manage
ment
plan
R R A C
Project
Sign off
R I I I I
Document Page
15PROJECT MANAGEMENT
Gantt chart and AON network
Gantt Chart
Figure 2: Gantt chart
(Source: Created from M S Project)
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
16PROJECT MANAGEMENT
AON Diagram
Figure 2: AOM Diagram Showing Critical path
(Source: Created by Author using Visio)
The diagram above shows the critical path that is required for the project. This critical
path states completing the project with the shortest possible time that is required for completing
the project. The above critical path states that shortest possible path that can be followed for
completing the project in less duration completing all the activities that are minimum required
for project completion. In the above diagram, the path that is shown in red states the critical path
of the project. The activities that comes in the red path are the activities that comes under critical
path.
The critical path that is determined in the project is : A- B – E- F – G – H – K – L – M –
N – O – Q – R – S – T – U.
Project Milestones
Task Name Duration Start Finish
Initiating project Architecture 2 days Thu 1/08/19 Fri 2/08/19
Carrying out requirement analysis 4 days Fri 16/08/19 Wed 21/08/19
Document Page
17PROJECT MANAGEMENT
Developing new products 12 days Tue 1/10/19 Wed 16/10/19
Project Sign off 0 days Thu 31/10/19 Thu 31/10/19
Resource Sheet
Resource
Name
Type
Materia
l Label
Initial
s
Grou
p
Max.
Units
Std. Rate
Ovt.
Rate
Cost/
Use
Accrue
At
Base
Calenda
r
Project
manager
Work P
100
%
$150.00/
hr
$0.00/
hr
$0.00
Prorate
d
Standar
d
Procurement
Manager
Work P
100
%
$120.00/
hr
$0.00/
hr
$0.00
Prorate
d
Standar
d
Finance
Manager
Work F
100
%
$120.00/
hr
$0.00/
hr
$0.00
Prorate
d
Standar
d
Risk Analyst Work R
100
%
$100.00/
hr
$0.00/
hr
$0.00
Prorate
d
Standar
d
Manufacture
r
Work M
100
%
$100.00/
hr
$0.00/
hr
$0.00
Prorate
d
Standar
d
Worker 1 Work W 100 $50.00/hr $0.00/ $0.00 Prorate Standar
Document Page
18PROJECT MANAGEMENT
% hr d d
Worker 2 Work W
100
%
$50.00/hr
$0.00/
hr
$0.00
Prorate
d
Standar
d
Worker 3 Work W
100
%
$50.00/hr
$0.00/
hr
$0.00
Prorate
d
Standar
d
Worker 4 Work W
100
%
$50.00/hr
$0.00/
hr
$0.00
Prorate
d
Standar
d
Quality
Analyst
Work Q
100
%
$100.00/
hr
$0.00/
hr
$0.00
Prorate
d
Standar
d
Equipment
Materia
l
E $1,200.00 $0.00
Prorate
d
Risk Management plan
The risks that are included in carrying out this project plan are stated below:
Estimate project risks as well as time: The project estimate that is being carried out in
the project is not always maintained. There is always a risk of not estimating the time
properly related to the project.
Changing the requirements: The requirements can be changed while developing the
project. This might be a risk in the project of the changed requirement that is being newly
implemented in the project. The market today is very much competitive and there always
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
19PROJECT MANAGEMENT
remains a chance that the clients changes their vision related to the project that is being
undergoing.
Circumstances that are unforeseen: The project that are undertaken by the project
managers and other stakeholders might fall sick or some circumstances may arise that can
delay the project completion time.
Specifications not clear: The project that is being undertaken might not have proper
project specification that might include incorrect project initiation along with project
specifications that are not always clear for the developers for staring the project.
Technical risks: The technical risks that are included in the project might not be able to
satisfy the project requirement that are included in the project.
Unavoidable risks: The risk that cannot be controlled in the project and also cannot be
avoided. The changing of government policy also comes under unavoidable risks.
Lesson Report
The lesson that can be learnt after completing this project is completing a project with the
scheduled time and within scheduled budget. This particular project report teach to develop a
business case for the project that is being undertaken. This project also helps to lean about how
the waster materials are being recycled to form new products. The project also helps to develop a
project scope and project objective for the undertaken topic.
From this project, the process of developing project plan is expected to be utilized in the
future projects. The developer of the project also can gain project knowledge of creating a WBS
of the project. Gantt chart is developed in this project plan that will help the developers to
develop any project schedule related to any other project. This report also states the project
Document Page
20PROJECT MANAGEMENT
structure team and create critical path of the project. Milestones can also be learnt from the
project.
Document Page
21PROJECT MANAGEMENT
Bibliography
Binder, J., 2016. Global project management: communication, collaboration and management
across borders. Routledge.
Bushuyev, S.D., Bushuyev, D.A., Rogozina, V.B. and Mikhieieva, O.V., 2015, September.
Convergence of knowledge in project management. In 2015 IEEE 8th International Conference
on Intelligent Data Acquisition and Advanced Computing Systems: Technology and Applications
(IDAACS) (Vol. 2, pp. 496-500). IEEE.
Hornstein, H.A., 2015. The integration of project management and organizational change
management is now a necessity. International Journal of Project Management, 33(2), pp.291-
298.
Joslin, R., 2019. Project Management Methodologies, Governance and Success: Insight from
Traditional and Transformative Research. CRC Press.
Kerzner, H., 2017. Project management: a systems approach to planning, scheduling, and
controlling. John Wiley & Sons.
Kerzner, H., 2018. Project management best practices: Achieving global excellence. John Wiley
& Sons.
Muller, R., 2017. Project governance. Routledge.
Radujković, M. and Sjekavica, M., 2017. Project management success factors. Procedia
engineering, 196, pp.607-615.
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
22PROJECT MANAGEMENT
Saltz, J. and Crowston, K., 2017, January. Comparing data science project management
methodologies via a controlled experiment. In Proceedings of the 50th Hawaii International
Conference on System Sciences.
chevron_up_icon
1 out of 23
circle_padding
hide_on_mobile
zoom_out_icon
logo.png

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]