Vella IT Office Fitouts: Project Management Case Study & Analysis

Verified

Added on  2023/06/11

|14
|925
|176
Case Study
AI Summary
This case study delves into the challenges faced during the Vella IT Office Fitouts project, focusing on the abrupt departure of the initial project manager and the subsequent impact on project timelines and budget. The analysis includes calculations of cost and schedule variances, revealing the project's financial standing and its deviation from the planned schedule. The report identifies key issues such as ineffective communication, poor leadership, and inadequate team management as contributing factors to the project's difficulties. It emphasizes the importance of selecting a project manager with strong leadership qualities, effective communication skills, and the ability to foster a collaborative team environment, referencing the Organizational Zoo Model as a framework for evaluating potential candidates. The study concludes with recommendations for improving project outcomes through better leadership selection and team management strategies, highlighting the need for a project manager who can effectively guide the project back on track and ensure its successful completion. Desklib provides similar case studies and solved assignments for students.
Document Page
Principles of Project Management
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Introduction
Purpose is to emphasize on leadership and management style
Analyze the case study
Role of Project Management
Deployment of Fitouts
Consider crucial aspects for project status report
Document Page
Cost Variance
Actual cost = $ 675,000
Actual completion of the project can be calculated as average of the completion of
four floors till the date:
= (75 % + 25 % + 25 % + 0 %) / 4
= 31.25 %
BAC (Budget at Completion) of the entire fitout project = $ 1,200,000
Cost Variance = Earned Value of the Project - Actual cost
= $ 375,000 – $ 675,000
= - $ 300,000
Document Page
Schedule Variance
BAC (Budget at Completion) of the entire fitout project = $ 1,200,000
Planned completion of the project = average of the completion of four floors:
= (100 % + 50 % + 50 % + 0 %) / 4
= 50 %
Planned Value of the project
= Planned Completion (%) * BAC
= 50 % X 1,200,000 = $ 600,000
Schedule Variance = Earned Value – Planned Value
= $ 375,000 – $ 600,000
= - $ 225,000
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Interpretation
Since the cost variance values is negative, this states that the project is
still undergoing within the budget
Negative value of the schedule variance depicts project is not in the track
of the completion within the expected time
Schedule of the project need proper consideration
New milestones with new timeline should be proposed
Document Page
List of Additional Information
Executive overview
Project identifiers
Identify the possible strategies
Project summary
Project status report
Include the deliverables and the milestones
Current percentage of the work completed
Actual start date
Actual finish date
Document Page
Leadership Behavior
Previous manager was not suitable
He does not have the effective communication strategy
Improper managerial skills
Improper leadership skills
He should have the quality of listening to others
He should take better decision-making
He should pass the organizational zoo model of leadership
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Organizational Zoo Model
Document Page
Organizational Zoo Model Cont.
This model suggests reflect, plan, do, and observe
A leader should analyze the different course of the action
Every discussion and develops member's reasoning before the association
"Appearance in real life" and "Reflection on Action."
Combining intelligent practice with discussion structure, conduct
investigation, and analogy is special.
Document Page
Recruitment of a New Project
Manager
Emphasis should be on the personal and professional behavior
Manager should be capable of considering a broad aspect of the actions
He or she should consider the value of the contribution of every team member
A metaphor test can be executed for analyzing the behavior of the individual
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Overview of existing team
environment
Project manager was not suitable for executing the project
Negligence of the team members
Improper communication
Wrong decision-making
Irresponsible decisions
Document Page
Conclusion
Based on the above facts, it can be concluded that the previous project that manager
was lagging in many aspects and that led to certain point that can be a difficulty for
new project manager to bring back the project on the track. The above report presents
the cost and schedule variance that stated how the project was effected in the sense of
the timeline because of the improper communication and leadership of the project
manager.