Project Management: Analysis of Sorento Quay Water Pollution Project

Verified

Added on  2021/02/19

|25
|4821
|79
Project
AI Summary
This project management assignment focuses on addressing the water pollution problem at Sorento Quay. The project encompasses a detailed case study, scope statement, cost estimates using analogous, parametric, and bottom-up methods, and a stakeholder management plan identifying key stakeholders and their roles. It includes a work breakdown structure, communication plan, risk analysis with a risk management plan, and a procurement plan. A Gantt chart, critical path, and critical chain analysis are provided, along with a comprehensive cost baseline. The project aims to establish an environmental testing lab to analyze and clean polluted water, with deliverables including lab setup, testing, and reporting, culminating in a presentation and acceptance by the Joondalup City Council. The assignment highlights project limitations, acceptance criteria, and the importance of effective cost management throughout the project lifecycle. The risk analysis identifies potential environmental disasters, issues with stakeholders, and problems in sample collection, along with mitigation strategies. Finally, the assignment includes a detailed procurement plan outlining the acquisition of necessary materials and resources.
Document Page
Project management
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Table of Contents
Assessment Task 1: Assignment......................................................................................................1
1. Case Study...............................................................................................................................1
2. Scope Statement......................................................................................................................1
2. Estimates.................................................................................................................................2
3. Stakeholder
Management Plan.......................................................................................................................6
4. Work breakdown
structure......................................................................................................................................7
5. Communication Plan...............................................................................................................8
6. Risk Analysis..........................................................................................................................9
7. Procurement Plan..................................................................................................................11
8. Gantt Chart............................................................................................................................12
9. Critical Path...........................................................................................................................12
10. Critical Chain......................................................................................................................13
11. Cost baseline
including...................................................................................................................................13
Assessment Task 2: Report............................................................................................................16
REFERNCES ................................................................................................................................20
Document Page
Document Page
Assessment Task 1: Assignment
1. Case Study
Sorento Quay is one of famous waterways that is getting polluted day by day because it
does not flow back from and to the Indian ocean. There can be other reasons also for water
pollution such as dumping of solid waste, acid rain, global warming etc. Therefore, there is a
major need to save the water from being polluted and make ways that can further reduce the
possibility of water pollution.
The project requires at a minimum the high-level work activities as follows:
ï‚· Lab. setup
ï‚· Lab testing
ï‚· Obtain and test water (iterative process)
ï‚· Conclusion report
ï‚· Presentation
ï‚· Acceptance by Joondalup City Council
2. Scope Statement
In this project, Small testing environmental project is established that help to clean the
polluted water of Sorento Quay. The project's achievement includes comprehensive scheduling
and implementation over an expanded period of moment (Alexander, 2013). The cooperation of
stakeholders is important to achievement, but a few important stakeholders are listed underneath
in the Stakeholder Management Plan.
Problem statement
The problem is identified by Joondalup City Council as the main cause of the problem of
water pollution is the polluted water of the city is coming to Sorento Quay. The dumping of the
solid waste by the population of the city is raising and water is polluted.
Project goal and objectives :
1
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
The main purpose behind it to eradicate the problem of the water pollution of the particular area
to neat and clean the environment factor and so the people nearby Sorento Quay can take neat
and clean breathe as well as improve the air quality in the environment.
Project deliverables:
The essential items that are required to be delivered on exact time so that activity related
to cleaning of Sorento Quay could be completed on desired time. Various items such as stability
chambers, pH meters, refractometer, biofuel analysers, balances evaporators, temperature
chambers and sample prep equipment must be delivered by Laboratory Analysers that is consider
to be the biggest supplier of laboratory equipment in entire Australia.
Project limitation:
This particular project is limited to the implication of the costing system and as per the
method of project management.
Project acceptance criteria:
The Joondalup City Council is required to review the progress of the projects in order to
complete the authenticity of project so that polluted water can be cleaned (Brewer and Dittman,
2018).
2. Estimates
Cost management mainly requires an efficient cost analysis to be undertaken in project's
effective execution (Davis, 2014). Three kinds of projections have been compelled for project in
interest of efficient cost management. The three kinds of methods conducted are analogous
estimates, parametric estimates and estimates from the bottom up. Here the project related to
establish.
Accurate analogous:
Expense Task Description Cost Estimate Whole $’s
Capital Expense Purchase of sample prep
equipment
$ 22000
Capital Expense Development of temperature
chambers.
$ 65900
Capital Expense Purchase of biofuel analysers, $ 59000
2
Document Page
balances and evaporators
Capital Expense Purchase of stability chambers,
pH meters, and refractometers
$ 47100
Capital Expense Contingency $ 16000
Grand Total $ 210000
3
Document Page
Parametric:
Dependent Variables Cost Per Total
$1,70,500.0
0
sample prep equipment 1.00 $22,000.00 $22,000.00
Splice Kits 25.00 $210.00 $5,250.00
Splice Crew 1550.00 $55.00 $85,250.00
Truck Delivery 55.00 $80.00 $4,400.00
Crane 50T 5.00 $105.00 $525.00
Crane 80T 4.00 $120.00 $480.00
Crane 130T 9.00 $125.00 $1,125.00
Franna Crane 25T 12.00 $140.00 $1,680.00
Civil Works crew 44.00 $50.00 $2,200.00
Electrical Contractor 55.00 $60.00 $3,300.00
Contract Rigger 50.00 $35.00 $1,750.00
Contract Fitter 35.00 $125.00 $4,375.00
Contract Supervisor 10.00 $115.00 $1,150.00
Truck Low Loader 70.00 $110.00 $7,700.00
Waste management crew 25.00 $65.00 $1,625.00
Contract scaffolder 24.00 $70.00 $1,680.00
Fixed Plant (Chamber)
Supervisor 15.00 $100.00 $1,500.00
Fixed Plant (Chamber)
Engineer 17.00 $120.00 $2,040.00
Loader 1.00 $1,100.00 $1,100.00
Generator 2.00 $2,200.00 $4,400.00
4
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Off-road forklift 3.00 $1,500.00 $4,500.00
Toilet Block 1.00 $970.00 $970.00
Lab Change Out Equipment 2.00 $2,600.00 $5,200.00
Waste Bins 3.00 $2,100.00 $6,300.00
Independent Variables Total $39,500.00
Splice Crew Known Team No Rs.0 $14,200.00
Contract Labour Known Team Yes 0%,5% $0.00
Electrical Crew Known Team No 0%,5% $1,200.00
Crane Hire Known
Team/Contract Yes 0%,5% $0.00
Hire Equipment Known Team No 0%,5% $120.00
Waste Management Known
Team No 0%,5% $50.00
Loader Hire Contract
Reasona
ble
0%,5%,8%,1
5% $2,100.00
Exchange Rate Belt Purchase Good
0%,5%,8%,1
5% $14,000.00
Exchange Rate Splice Kits
Purchase Good
0%,5%,8%,1
5% $210.00
Length of project Average 0,33%,66% $3,640.00
Project Difficulty Average 0,33%,66% $3,980.00
Project Total $2,10,000.00
Bottom-up
estimates
5
Document Page
6
Document Page
3. Stakeholder
Management Plan.
In order to improve the likelihood of providing the project to schedule, the project
stakeholder scheme was placed together. Stakeholders are essential to achieving the objective by
negotiating and engaging.
Project Title: Environmental
testing lab
Date Prepared: 01st June
2019
Impact
Assess
ment
Expectations/
Strategy
Name
Positio
n Role Contact Influence
Mark
Henry
Project Team
Leader
High
Interest,
High
Power
Key
Player
Weekly reports
on cost base line,
budget variance,
project plan and
project schedule
Leading
Phone:4788764
32 Email:
Henmark@bigp
ond.com
George
Johnso
n
Asset Owner
Team Leader Leading
Phone:4788764
32
Email:Geojhon
@bigpond.com
High
Interest,
High
Power
Key
Player
Meetings on key
milestones
Ricky Area Business Support Phone:4788764 High Keep Report financial
7
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
wood Adviser(finance). ive
32
Email:R.woodl
@finance.com
Interest,
High
Power
Informe
d
data to finance
group. Assist with
cost management
Jonatha
n Trott
Environmentalist
Analyst
Support
ive Phone:4788764
32
Email:J.Trott@
engineering.co
m
High
Interest,
High
Power
Key
Player
Management of
environmental
resources. Update
on project
schedule
Kane
Mint
Location
Manager (project
sponsor)
Support
ive Phone:4788764
32
Email:k.mint@
bauxiteco.com
High
Interest,
High
Power
Key
Player
Report to
corporate, sign
off on
completion.
Email details
8
Document Page
4. Work breakdown
structure.
Project Task Estimated Start Date Estimated Completion Date Task Owner Actual Start Date Actual Completion Date
Project Feasibility Study 01/06/19 03/06/19 John Doe 01/06/19 02/06/19
Cost Benefit Analysis 02/06/19 04/06/19 Jane and John 02/06/19 03/06/19
Project Definition 06/06/19 08/06/19 Jane Doe 06/06/19 09/06/19
Assign Resources 08/06/19 09/06/19 John Smith 08/06/19 11/06/19
Create Project Plan 09/06/19 16/06/19 Kim Lee 09/06/19 11/06/19
Create Communications Plan 15/06/19 17/06/19 Jane Doe 15/06/19 17/06/19
Project Kick-Off Meeting 19/06/19 19/06/19 Jane Doe 19/06/19 20/06/19
Create Phase 1 Plan and Definition 22/06/19 24/06/19 Jane Doe 22/06/19 25/06/19
Phase 1 Execution Kick-Off 24/06/19 24/06/19 Jane Doe 24/06/19 25/06/19
Communicate Phase 1 Progress 25/06/19 01/07/19 John Doe 01/07/19 03/07/19
Change Control Processes 01/07/19 02/07/19 Jane and John 02/07/19 03/07/19
Close Phase 1 02/07/19 03/07/19 Jane Doe 03/07/19 05/07/19
Create Phase 2 Plan and Definition 01/07/19 03/07/19 Chris Johnson 03/07/19 08/07/19
Phase 2 Execution Kick-Off 06/07/19 06/07/19 Chris Johnson 06/07/19 09/07/19
Communicate Phase 2 Progress 07/07/19 09/07/19 Chris Johnson 07/07/19 09/07/19
Change Control Processes 09/07/19 10/07/19 Chris Johnson 09/07/19 11/07/19
Close Phase 2 13/07/19 14/07/19 Jane Doe 13/07/19 14/07/19
Project Delivery 15/07/19 15/07/19 Production Team 15/07/19 17/07/19
Project Closure Meeting 16/07/19 16/07/19 Jane Doe 16/07/19 19/07/19
Performance Appraisal 16/07/19 18/07/19 Jane Doe 18/07/19 22/07/19
Project Feedback Form 16/07/19 18/07/19 Kim Lee 17/07/19 19/07/19
Project Debrief Report 17/07/19 20/07/19 Jane Doe 20/07/19 23/07/19
5. Communication Plan.
Communication management strategy defines a variety of stakeholders' that requires
meaningful information related to project (Eskerod and Vaagaasar, 2014). This is crucial because
it could be expensive to neglect any stakeholder while implementing a project.
Stakeholder Communications Name
Delivery
method/For
mat Producer
Due
Date/Frequency
Mark Henry
Cost Base Line,
Email
Reports
(Project Team
Leader)
Reports Weekly
every Monday at
00:00.00
Budgets, Variance, report, Meetings Weekly on Friday
9