Wembley Stadium Project Report

Verified

Added on  2020/01/07

|17
|5010
|312
Report
AI Summary
This report is a case study of the Wembley Stadium construction project, focusing on its project management aspects. It examines various elements including stakeholder management (contractors, labor, customers, community, sports people, government, and shareholders), time management (using Gantt charts and critical path analysis), risk management (unreasonable allocation, cash flow problems, poor performance, poor site management, and design changes), team dynamics, cost management, and the application of the triple constraint triangle theory. The report analyzes the methodologies and processes employed, specifically the critical path method and total quality management, and discusses the factors contributing to both the project's successes and failures. The conclusion emphasizes the importance of skilled personnel, effective communication, resource allocation, and transparent accountability in successful project management, drawing lessons from the Wembley Stadium experience.
Document Page
Project Management
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
TABLE OF CONTENTS
INTRODUCTION...........................................................................................................................4
Project management.........................................................................................................................4
STAKEHOLDERS..........................................................................................................................4
TIME MANAGEMENT..................................................................................................................6
RISK MANAGEMENT...................................................................................................................9
TEAMS..........................................................................................................................................10
COST MANAGEMENT...............................................................................................................11
TRIPPLE CONTRAINT TRIAGLE..............................................................................................12
METHODOLOGIES AND PROCESSES.....................................................................................13
SUCCESS AND FAILURE...........................................................................................................15
CONCLUSION..............................................................................................................................15
REFERENCES..............................................................................................................................17
Document Page
INTRODUCTION
Project management refers the procedure related to working on a specific project for
improving the performance of particular field. It enables corporation to integrate all related
resources and complete the project related activities in an effectual manner. Present report is
based on construction of Wembley stadium and its effective management related to utilizing the
time and resources effectively. For this purpose, report covers the reasons behind failure of the
public project management and understanding the varied issues or remedies available to improve
the performance of the project in a cost effective manner. In addition to this, triple constraint
triangle theory and importance of stakeholders etc are explained in context of the Wembley
stadium project. Moreover, success and failure of the project has been explained along with
application of suitable methodology to complete the same.
PROJECT MANAGEMENT
The project of Wembley stadium has been taken into account which is construction
project. Here, the specific purpose of stadium consists of several functions such as rugby
matches and football so as to organize the private evenest and other related concerts. Owing to
this, issues related to time is faced along with higher cost. For this purpose, current project is
being implemented in order to save time as well as cost so as to accomplish the purpose of the
stadium effectively. However, the procedure of construction was delayed due to the bidding. For
this purpose, lowest cost request was order for the contractors in order to ensure the optimum
utilization of the limited resources (Alotaibi and Mafimisebi, 2016). On the other hand,
implementation phase was delayed as the arch execution was challenging. For this purpose,
appropriate project management work should be done under which bidding related issues can be
resolved. For example, profession and qualified personnel can be invited for the bidding so they
can focus on the services. Moreover, experienced engineers were needed so as to implement the
more advanced design in the construction of Wembley stadium. Accordingly, project
management related task has been completed through following the below mentioned steps or
aspects.
STAKEHOLDERS
There are several stakeholders associated with the project which are explained as follows-
Document Page
Contractors or engineers-The major issue related to Wembley stadium was associated
with wrong suppliers and bidders. They were focusing on higher cost which tend to
increase the budget to a great extent. For this purpose, qualified personnel were required
to associated in the project who can manage the performance of the project effectively.
However, advanced design of the project can be made possible with the inclusion of
skilled and competent engineers (Heagney, 2016). Labour-Labour associated with the project must also possess the necessary skills who
can effective contribute towards the success of the project. It would be more effective to
cater the requirement of the project and complete the same in relatively less time span. Customers-The customers or audience are the main parties who will consume the
services rendered through Wembley stadium. For this purpose, preferences of customers
are taken into account while preparing the stadium. For example, appropriate ventilation,
air facility and seating arrangement is taken into account. This in turn meet the
expectations of people attention the event effectively (Richard, Sorooshian and Shariman,
2016). Community-The general community surrounding the stadium is also affected through
several factors. At this juncture, project should be completed by focusing on their
requirement and proper facilities related to disposal of waster etc. At the same time, water
and air pollution should not be occurred to general community. These specific aspects are
considered as the time of completion of the construction project. Sports people-It is the most important stakeholders associated with the project of
Wembley stadium. They need several kind of facilities regarding practice, rest rooms and
other facilities. It is considered at the time of preparing structure of stadium and
providing the basic amenities for the players (Martinelli and Milosevic, 2016).
Government and shareholders-It covers people who invest the fund in the completion of
the project. Government must specific the budget effectively as per the requirement of the
project. At the same time, government or shareholders have certain expectations related
to quality and return which must be accomplished through consideration.
However, some of the ways are applied for the completion of project should be effective
under which business ensure to associate the qualified and highly skilled personnel. Similarly,
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
the management team should be strong who can effectively cope up with the changes and
address the issues which are being faced at the time of completion of the project.
TIME MANAGEMENT
Time management refers to the appropriate management of activities within the given
time span. For this purpose, management must list all the activities to be covered under the
project. The below mentioned table is showing detail information related to activities covered
under the project. This proves to be effective for project management to assigning the right task
to right people and ensure the accomplish the standards set for the project (Bresnen, 2016). The
time line of each activity has also been presented through which it becomes easy for the
researcher or corporation to meet the long as well as short term objectives of the project in a right
manner. It would be effective to support all project managers or members associated in the team.
Sr. No. Activities Time Predecessors
1 Planing of the Wembley Stadium 60 days
2 Conducing the research 100 days 1
3 Preparing the final plan 150 days 1,2
4 Acquiring the resources 300 days 2
5 Allocation of resources 30 days 1
6 Contingency provision for
multiplex
25 days 3,4
7 Cost of infrastructure 50 days 3
8 Financing cost 90 days 5,7,6
9 Management and development
team construction
20 days 3
10 Purchasing the site 30 days 1,2
11 Construction contract with fixed
price
40 days 8,9
12 Cost overruns in construction 10Days 10,11
13 Implementing the plan 400 days 12
14 Execution 300 days 13
15 Settlement 90 days 14
Total
Document Page
The below mentioned table has been extracted from the application of software related to
the management of the project. It reflects the starting as well as finish time of the each activity. It
considered as the processed table.
Task Mode Task Name Duration Start Finish Predecessors
Manually
Scheduled
Planing of the Wembley
Stadium 1 day Mon 4/10/17 Mon 4/10/17
Manually
Scheduled Conducing the research 1 day Tue 4/11/17 Tue 4/11/17 1
Manually
Scheduled Preparing the final plan 1 day? Wed 4/12/17 Wed 4/12/17 1,2
Manually
Scheduled Acquiring the resources 1 day Wed 4/12/17 Wed 4/12/17 2
Manually
Scheduled Allocation of resources 1 day Tue 4/11/17 Tue 4/11/17 1
Manually
Scheduled
Contingency provision
for multiplex 1 day Thu 4/13/17 Thu 4/13/17 3,4
Manually
Scheduled Cost of infrastructure 1 day Thu 4/13/17 Thu 4/13/17 3
Manually
Scheduled Financing cost 1 day Fri 4/14/17 Fri 4/14/17 5,7,6
Manually
Scheduled
Management and
development team
construction
1 day Thu 4/13/17 Thu 4/13/17 3
Manually
Scheduled Purchasing the site 1 day? Wed 4/12/17 Wed 4/12/17 1,2
Manually
Scheduled
Construction contract
with fixed price 1 day? Mon 4/17/17 Mon 4/17/17 8,9
Manually
Scheduled
Cost overruns in
construction 1 day Tue 4/18/17 Tue 4/18/17 10,11
Manually
Scheduled Implementing the plan 1 day Wed 4/19/17 Wed 4/19/17 12
Manually
Scheduled Execution 1 day Thu 4/20/17 Thu 4/20/17 13
Manually
Scheduled Settlement 1 day Fri 4/21/17 Fri 4/21/17 14
Document Page
The above mentioned gantt chart is representing the activities related to project and
which will help project management to complete the Wembley stadium project in a specified
time span. This aids to deliver good quality of services to end users effectively.
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
The above mentioned diagram reflects that activities covered under critical path are;
1+2+4+3+6+7+8+11+12+13+14+15. It represented that activity 5,10 and 9 will be completed
simultaneously in the mentioned activities of critical path. Hence, it is considered as the most
appropriate approach for the completion of long as well as short term objectives associated with
the Wembley project.
RISK MANAGEMENT
The management is considered as the most typical task in the project management. It
assists employees to input their knowledge for improving service delivery procedure. These are
explained as follows- Unreasonable allocation-It is very important in a specific project to allocate the financial
resources and other related in accordance with different project. This enables project
manager to control the risk and reach at the fruitful outcome effectively (Patanakul and
et. al., 2016). Furthermore, unreasonable allocation tend to increase the cost and make the
service delivery very poor. Cash-flow problems-The issue related to poor cash flow was also found under the project
of Wembley stadium. This affected the project performance to a great extent because
people associated with the same found issue regarding reducing the cost of operation. In
addition to this, cost of operation was very higher in comparison to requirement of the
project just because of association of poor resources allocation aspects.
Document Page
Poor performance-The performance of workforce associated in the project was not up to
the mark. The personnel involved in the team was not skilled and highly talented through
which they face issues in completing the project on time along with low cost. Though, the
poor performance is the outcome of ineffective personnel who do not possess necessary
skills and attributes (Sökmen and Çebi, 2017). Poor site management-Under this, poor site management is the crucial issue through
which al associated members cannot focus on their task as they were guided in the wrong
direction. It serves as the waste of the money and increase the cost to a great extent.
Owing to this, it significant to include highly competent and experienced engineers who
can handle the performance related to project in a right manner (Blomquist, Farashah and
Thomas, 2016).
Design changes-The risk related to managing the change remain higher under public
project due to association of huge amount for the construction whereby increase in fuel
cost due to economical and political changes has direct impact on the cost of material. It
facilitates to support the business to a great extent and contribute towards the success of
the business in an effectual manner. In addition to this, economic and political risk should
be minimized with the implementation of the emergency plan. It contribute towards the
long run success and completion of the all related activities of the project.
TEAMS
The team consists of workers, project management and financers in the project who
actively take part in the process of project competition. However, the role of project manager,
contractors and engineers is considered as the crucial who work upon the major activities and
accordingly roles and responsibilities of all employees is decided in advance. This proves to be
effective to integrate all related resources and reduce the cost of operation (Paquin, Gauthier and
Morin, 2016). Project owner plays important role and in the current project manager will serve as
the significant role.
The general director handle the work related to allocation of finance and other resources
as per the activities of construction project related to Wembley Stadium. It assists members to
get the right direction as per the activities defined in the project. However, team leader is
responsible for the allocation of work in accordance with capabilities and skills of the personnel.
Document Page
This facilitates to shed light on time saving and cost saving aspect. It is because workforce get
the work as per the requirement (Lakemond and et. al., 2016). However, the suppliers contracted
must be coordinated properly so they will get to know about the requirement related to project.
For this purpose, management of the project complete the task regarding the appropriate
communication procedure under which timely meeting is taken with the workforce and they are
informed regarding he schedule of initiation of each activity. Not only this but they are promoted
to reduce the time taken for the completion of the project. It aids to determine the allocation of
resources effectively. It aids to cater requirement of all related stakeholders ans support project t
get completed on time. It can be critically evaluated that conflict among team members occur
due to less clarity in their work (Kivilä, Martinsuo and Vuorinen, 2017). This tends to affect their
performance to a great extent and in turn they cannot contribute equally towards the success of
the project. However, responsibility assignment matrix is followed by the project manager
through which all related responsibilities of members is defined in advance and accordingly they
get the power or resources to manage all related task in an effectual manner.
In addition to this, project manager follow the most suitable strategy or leadership style
whereby workforce can be motivated and influenced in order to accomplish the given task. This
aids to encourage them to put their efforts in the direction of growth and success of the project.
Not only but they are provided reward for their better performance and achievement in the
project. It can be made possible through continuous evaluation and monitoring of the project.
COST MANAGEMENT
The below mentioned table is showing the total cost associated with the project. It covers
cost related to each activity and its direct impact on the performance of the project. However, the
total cost of the project was estimated to be £1 billion. The actual cost of the Wembley stadium
has been stated as follows. It would be effective for the project management to accomplish all
related activities. The higher cost was related to purchasing the site only which tend to increase
overall cost of the project (£750m bill turns Wembley into a new Dome, 2017). Owing to this,
suitable care should be taken at the time of allocation of fund. This in turn project manager
focuses on reducing the cost associated with the project and meet the aim and objectives of the
same in an effectual manner.
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Cost Activities
£1.6m Expenditure made through DCMS for the
review of the England Sport
£20m Contingency provision for multiplex
£21m Cost of infrastructure
£79m Financing cost
£86m Management and development fee
£106m Purchasing the site
£445m Construction contract with fixed price
£183m Cost overruns in construction
£20.8m Cost overruns
Total £962.4m
The cost reduction can be done with the help of association skilled and competent
personnel. However, the cost might increase due to offering the training and development. This
in turn cost might different in each case.
TRIPPLE CONTRAINT TRIAGLE
It is considered as the most important theory under the project management which deals
in the three aspects such as scope, cost and time. It proves to be effective for formulating and
analysing the challenges faced at the time of formulation, evaluation and implementation of
private or public related projects. For this purpose, project management team focus on allocation
of financial resources effective with a purpose to reduce cost and increase overall rate of return.
For example, Wembley stadium needs proper financial resources through which all facilities can
be added at the time of the completion of the project (Kivilä, Martinsuo and Vuorinen, 2017).
Furthermore, emergency sources must also be allocated whereby company or project can be
funded in case of requirement of scarcity of the financial resources. However, expert of project
in the finance department estimate the proper cost as per the activities covered under the project.
This proves to be effective in determining the success of the project and deliver good quality of
services to large number of buyers. This facilitates to meet the objectives of the project
effectively.
Document Page
Furthermore, certain portion of capital can be set aside whereby it is made possible to
change the project development requirement in case needed. This helps to deliver good quality of
services to large number of buyers and accordingly accomplish all related activities in a right
manner. On a critical note, wrong estimation was done on the Wembley stadium project was not
right. This was the biggest reason behind the delay in the project and affected. whereby it
becomes easy to cater requirement of all related parties and project in an effectual manner. In
addition to this, alternative ways of the financing must be decided in advance so that company
can address the issue related to scarcity of resources and meet the expectations of all associated
parties.
Time as another important factor of the triple triangle where all project have different
time line. Here, timeline of the project is considered in accordance with the several formal and
informal factors. It consists of workers associated with project or site through which they can
successfully accomplishing the project in relatively less time span. Time management of the
project determines its success whereby scheduling is done through project managers so as to
estimate the proper time for each project management step (Blomquist, Farashah and Thomas,
2016). Though, time management covers all activities such as acquisitions of raw material and
making the available to the site. However, the case study of Wembley stadium reflects that delay
was caused due to poor time management and accordingly it was stretched to 5 years. It could
have been completed in less time.
In addition to this, scope of the project was also considered but still it leads to failure of
the same. Here, scope of the project was considered in accordance with economic and
technological changes. For example, construction project consider the economic changes that
inflation and recession tend to affect the performance of the business to a great extent (Sökmen
and Çebi, 2017). Owing to this, price of fuel might be increased which has significant impact on
the material or transportation. This affects the performance of the project and in turn cost and
time must be focused. The project related to Wembley stadium shed light on time and cost so as
to effectively management the project related activities. On a critical note, in-spite of appropriate
procedure related to quality, initial used raw material was of low quality. This affected the
performance of the project. Thus, time, cost and scope of the project related to Wembley stadium
was not decided effectively which in turn failure was occurred to the project.