Network Installation Project: Western Mining, University Project
VerifiedAdded on 2022/11/25
|24
|3466
|200
Project
AI Summary
This project report outlines a comprehensive plan for a network installation project at Western Mining, a company with a new branch office in Brisbane. The report begins with a detailed determination of project requirements, including client specifications, questions for the steering committee, and a work breakdown structure. It identifies key stakeholders, their roles, and data gathering techniques. The project then moves into scheduling and management, featuring a Gantt chart, communication plan, and a risk management plan addressing potential issues like software vulnerabilities and technical risks. The report also covers project closure, including outcomes and lessons learned, followed by answers to questions about Australian legislation and copyright. Finally, the report recommends SNMP monitors and outlines characteristics of successful technical teams, providing a well-rounded approach to the project's execution and management.

Running head: NETWORK INSTALLATION IN WESTERN MINING
Project Management: Network Installation in Western Mining
Name of Student
Name of University
Author Note
Project Management: Network Installation in Western Mining
Name of Student
Name of University
Author Note
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1
NETWORK INSTALLATION IN WESTERN MINING
Table of Contents
Part 1: Determination of Project Requirements...................................................................3
Task 1...............................................................................................................................3
1.1.1. Detailed description of Clients’ Requirements..................................................3
1.1.2. Questions that are needed to be asked to the steering committee......................4
Task 2...............................................................................................................................5
Task 3...............................................................................................................................5
1.3.1. Stakeholder Analysis.........................................................................................5
1.3.2. Stakeholders’ Matrix.........................................................................................6
1.3.3. Data gathering Techniques................................................................................7
Task 4...............................................................................................................................9
1.4.1. Charter...............................................................................................................9
1.4.2. Email..................................................................................................................9
Task 5...............................................................................................................................9
Task 6.............................................................................................................................10
Part 2: Scheduling and Managing......................................................................................12
Task 1: Gantt Chart........................................................................................................12
Task 2: Communication Plan.........................................................................................12
Task 3: Risk Management Plan.....................................................................................14
Task 4: Project Closure......................................................................................................16
NETWORK INSTALLATION IN WESTERN MINING
Table of Contents
Part 1: Determination of Project Requirements...................................................................3
Task 1...............................................................................................................................3
1.1.1. Detailed description of Clients’ Requirements..................................................3
1.1.2. Questions that are needed to be asked to the steering committee......................4
Task 2...............................................................................................................................5
Task 3...............................................................................................................................5
1.3.1. Stakeholder Analysis.........................................................................................5
1.3.2. Stakeholders’ Matrix.........................................................................................6
1.3.3. Data gathering Techniques................................................................................7
Task 4...............................................................................................................................9
1.4.1. Charter...............................................................................................................9
1.4.2. Email..................................................................................................................9
Task 5...............................................................................................................................9
Task 6.............................................................................................................................10
Part 2: Scheduling and Managing......................................................................................12
Task 1: Gantt Chart........................................................................................................12
Task 2: Communication Plan.........................................................................................12
Task 3: Risk Management Plan.....................................................................................14
Task 4: Project Closure......................................................................................................16

2
NETWORK INSTALLATION IN WESTERN MINING
2.4.1. Project Outcomes.............................................................................................16
2.4.2. Lesson Learned................................................................................................17
Part 3: Question and Answer.............................................................................................18
Answer 1........................................................................................................................18
Answer 2........................................................................................................................18
Answer 3........................................................................................................................20
3.3.1. Australian Legislations....................................................................................20
3.3.2. Advice..............................................................................................................20
3.3.3. Breach of Copyright legislation.......................................................................21
3.3.4. Copyright Policy..............................................................................................21
Answer 4........................................................................................................................21
Bibliography......................................................................................................................22
NETWORK INSTALLATION IN WESTERN MINING
2.4.1. Project Outcomes.............................................................................................16
2.4.2. Lesson Learned................................................................................................17
Part 3: Question and Answer.............................................................................................18
Answer 1........................................................................................................................18
Answer 2........................................................................................................................18
Answer 3........................................................................................................................20
3.3.1. Australian Legislations....................................................................................20
3.3.2. Advice..............................................................................................................20
3.3.3. Breach of Copyright legislation.......................................................................21
3.3.4. Copyright Policy..............................................................................................21
Answer 4........................................................................................................................21
Bibliography......................................................................................................................22
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3
NETWORK INSTALLATION IN WESTERN MINING
Part 1: Determination of Project Requirements
Task 1
This particular report is related to development of a plan for implementation of IT
solutions in Western mining. In this section of the entire report, the major project requirements
are identified. The identification of the requirements of the project is related to understanding the
detailed specification of the client’s need. The detailed description of the client’s requirements
along with the questions that can be asked to the steering committee are indicated in the
following sections.
1.1.1. Detailed description of Clients’ Requirements
The Pacific IT solutions mainly works for installation and implementation of IT solutions
for the clients. Here, the client for the project is Western Mining. Western Mining has their head
office in Sydney. The client company is planning to open one branch office in Brisbane. The
project that is given to Pacific IT include setting up of a new network in the branch office in
Brisbane. However, to implement the project in a successful manner, it is quite essential for the
company to note the clients’ requirements in an accurate manner. The detailed description of the
clients are indicated in the following paragraph.
As per the requirement specified by the manger of Western Mining, although the branch
office will start off with a lesser number of staffs, the number of staffs are expected to increase
and therefore, network to be implemented should consider, providing services to a larger number
of staffs. As per the requirement specifications of the client, the network services should be
provisioned for 510 staffs.
NETWORK INSTALLATION IN WESTERN MINING
Part 1: Determination of Project Requirements
Task 1
This particular report is related to development of a plan for implementation of IT
solutions in Western mining. In this section of the entire report, the major project requirements
are identified. The identification of the requirements of the project is related to understanding the
detailed specification of the client’s need. The detailed description of the client’s requirements
along with the questions that can be asked to the steering committee are indicated in the
following sections.
1.1.1. Detailed description of Clients’ Requirements
The Pacific IT solutions mainly works for installation and implementation of IT solutions
for the clients. Here, the client for the project is Western Mining. Western Mining has their head
office in Sydney. The client company is planning to open one branch office in Brisbane. The
project that is given to Pacific IT include setting up of a new network in the branch office in
Brisbane. However, to implement the project in a successful manner, it is quite essential for the
company to note the clients’ requirements in an accurate manner. The detailed description of the
clients are indicated in the following paragraph.
As per the requirement specified by the manger of Western Mining, although the branch
office will start off with a lesser number of staffs, the number of staffs are expected to increase
and therefore, network to be implemented should consider, providing services to a larger number
of staffs. As per the requirement specifications of the client, the network services should be
provisioned for 510 staffs.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4
NETWORK INSTALLATION IN WESTERN MINING
As per the requirement of the client, the network for the branch office should be set up
for all four departments, which include the sales, operations, management and exploration. The
requirement of the client further indicates that a non cisco router will be installed in the head
office. As per the requirement of the client, the project is to be implemented in as much less i as
possible.
Specific Requirements: 1. The initial design specifications indicates that the client want to make
use of Cisco 2811 router and 2960 switches.
2. Remote Login is required for the switches and the routers in the head office.
3. Network monitoring systems are compulsory to set up after installation of the network
1.1.2. Questions that are needed to be asked to the steering committee
The questions that are needed to be asked to the steering committee regarding the
execution of the project are indicated as follows-
1. What is the anticipated completion time that can be allocated for the completion of the
project?
2. Is the building in which the project will be conducted is accessible for 24 hours a day?
3. What is the expected budget of the project?
The above three questions are needed to be asked to the steering committee that will
ascertain that the project is completed as per the requirements. Answer to these questions will
help in effective development of the project plan.
NETWORK INSTALLATION IN WESTERN MINING
As per the requirement of the client, the network for the branch office should be set up
for all four departments, which include the sales, operations, management and exploration. The
requirement of the client further indicates that a non cisco router will be installed in the head
office. As per the requirement of the client, the project is to be implemented in as much less i as
possible.
Specific Requirements: 1. The initial design specifications indicates that the client want to make
use of Cisco 2811 router and 2960 switches.
2. Remote Login is required for the switches and the routers in the head office.
3. Network monitoring systems are compulsory to set up after installation of the network
1.1.2. Questions that are needed to be asked to the steering committee
The questions that are needed to be asked to the steering committee regarding the
execution of the project are indicated as follows-
1. What is the anticipated completion time that can be allocated for the completion of the
project?
2. Is the building in which the project will be conducted is accessible for 24 hours a day?
3. What is the expected budget of the project?
The above three questions are needed to be asked to the steering committee that will
ascertain that the project is completed as per the requirements. Answer to these questions will
help in effective development of the project plan.

5
NETWORK INSTALLATION IN WESTERN MINING
Task 2
The work breakdown structure of the undertaken project are indicated in the following
figure-
Figure 1: Illustrating the Work Breakdown Structure
The above figure illustrates the work breakdown structure that is being followed for
execution of the project. The project is subdivided into a number of subsections that ascertains
successful execution of the project. The work breakdown designed gives an idea of the tasks that
are needed to be executed for successful completion of the project. Each phase that is illustrated
in the figure above contains a number of subtasks as well. The figure further illustrates the link
between each tasks that are to be executed as per plan.
Task 3
1.3.1. Stakeholder Analysis
NETWORK INSTALLATION IN WESTERN MINING
Task 2
The work breakdown structure of the undertaken project are indicated in the following
figure-
Figure 1: Illustrating the Work Breakdown Structure
The above figure illustrates the work breakdown structure that is being followed for
execution of the project. The project is subdivided into a number of subsections that ascertains
successful execution of the project. The work breakdown designed gives an idea of the tasks that
are needed to be executed for successful completion of the project. Each phase that is illustrated
in the figure above contains a number of subtasks as well. The figure further illustrates the link
between each tasks that are to be executed as per plan.
Task 3
1.3.1. Stakeholder Analysis
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6
NETWORK INSTALLATION IN WESTERN MINING
The stakeholders who are linked with the undertaken project of setting up of a network,
along with their involvement in the project are indicated in the table below-
Stakeholders Category Power/Influence Interest
Project Manager
(Pacific IT Solutions)
Internal Medium High
Manager (Western
Mining)
External High High
Senior System
Architect
External Medium Medium
Branch Office
Manager
External Medium Low
Staffs (Western
Mining)
External Low Low
Senior Network
Engineer (Pacific IT
Solutions)
Internal Medium Medium
Junior Network
Engineer (Pacific IT
Solutions)
Internal Medium Medium
Table 1: The Stakeholders linked with the network setting up project in Western Mining
1.3.2. Stakeholders’ Matrix
NETWORK INSTALLATION IN WESTERN MINING
The stakeholders who are linked with the undertaken project of setting up of a network,
along with their involvement in the project are indicated in the table below-
Stakeholders Category Power/Influence Interest
Project Manager
(Pacific IT Solutions)
Internal Medium High
Manager (Western
Mining)
External High High
Senior System
Architect
External Medium Medium
Branch Office
Manager
External Medium Low
Staffs (Western
Mining)
External Low Low
Senior Network
Engineer (Pacific IT
Solutions)
Internal Medium Medium
Junior Network
Engineer (Pacific IT
Solutions)
Internal Medium Medium
Table 1: The Stakeholders linked with the network setting up project in Western Mining
1.3.2. Stakeholders’ Matrix
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7
NETWORK INSTALLATION IN WESTERN MINING
The involvement of the stakeholders in this project is represented in the following
stakeholders’ Power/Interest grid-
Figure 2: Illustrating the Stakeholders’ Power/Interest grid
The figure 2, distinguishes the stakeholders that are needed to be kept satisfied, managed
closely, monitored or kept informed. The matric indicates all the important stakeholders of the
project.
1.3.3. Data gathering Techniques
NETWORK INSTALLATION IN WESTERN MINING
The involvement of the stakeholders in this project is represented in the following
stakeholders’ Power/Interest grid-
Figure 2: Illustrating the Stakeholders’ Power/Interest grid
The figure 2, distinguishes the stakeholders that are needed to be kept satisfied, managed
closely, monitored or kept informed. The matric indicates all the important stakeholders of the
project.
1.3.3. Data gathering Techniques

8
NETWORK INSTALLATION IN WESTERN MINING
A project manager is required to develop a plan that ascertain that all the concerned
stakeholders remain engaged with the project. There can be a number of data gathering
techniques that can be used by the project manager to understand the involved persons and the
relationship of the stakeholder with the project. The methods of data collection are indicated as
follows-
1. One on One Interviews: Since the project manager had the detailed idea of all the
individuals linked with the project, it was not a difficulty to identify the stakeholders of the
project. The interest and the engagement of a particular stakeholders with the undertaken project,
can be analyzed with the data gathering method of one on one interview.
2. Focus Group Discussion: Another effective method of collection of data for this
project is focus group discussion. The focus group discussion generally involves gathering of
people from a similar background for discussing a specific topic. All the identified stakeholders
of the project can gather for a focus group discussion with the project manager. Therefore, opting
for this method of data collection is justified.
3. Collaborative Workshop: This is another effective method of data collection that can
be used for collection of the data related to the engagement of the stakeholders in a project.
Collaborative workshop is considered to be effective and it enables the manager to collect
information about the stakeholders of the project.
The above three techniques are considered to be effective for collection of data about the
stakeholders linked with the project. The manager could use any of the three or a combination of
the three methods to collect data about the stakeholders linked with the project.
NETWORK INSTALLATION IN WESTERN MINING
A project manager is required to develop a plan that ascertain that all the concerned
stakeholders remain engaged with the project. There can be a number of data gathering
techniques that can be used by the project manager to understand the involved persons and the
relationship of the stakeholder with the project. The methods of data collection are indicated as
follows-
1. One on One Interviews: Since the project manager had the detailed idea of all the
individuals linked with the project, it was not a difficulty to identify the stakeholders of the
project. The interest and the engagement of a particular stakeholders with the undertaken project,
can be analyzed with the data gathering method of one on one interview.
2. Focus Group Discussion: Another effective method of collection of data for this
project is focus group discussion. The focus group discussion generally involves gathering of
people from a similar background for discussing a specific topic. All the identified stakeholders
of the project can gather for a focus group discussion with the project manager. Therefore, opting
for this method of data collection is justified.
3. Collaborative Workshop: This is another effective method of data collection that can
be used for collection of the data related to the engagement of the stakeholders in a project.
Collaborative workshop is considered to be effective and it enables the manager to collect
information about the stakeholders of the project.
The above three techniques are considered to be effective for collection of data about the
stakeholders linked with the project. The manager could use any of the three or a combination of
the three methods to collect data about the stakeholders linked with the project.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

9
NETWORK INSTALLATION IN WESTERN MINING
Task 4
1.4.1. Charter
A charter is filled up for the network implementation project in Western Mining
1.4.2. Email
Dear Mr. James T. Krik,
I am writing this mail to inform you that I have developed a charter for the Network
Installation project in Western Mining. I am attaching the project charter document for you to go
through the same. If you find the charter appropriate for the project, kindly approve the charter
so that we can start the project. If your find any scope of changes in the charter, kindly highlight
the same so that we can rectify it.
Thanks and Regards,
Please Insert Your Name
Project Manager,
Pacific IT Solutions
Task 5
Three Simple Network Management Protocol (SNMP) monitors that can be used by
Western Mining, for collection and displaying of the SNMP data are listed as follows-
Project Charter.doc
NETWORK INSTALLATION IN WESTERN MINING
Task 4
1.4.1. Charter
A charter is filled up for the network implementation project in Western Mining
1.4.2. Email
Dear Mr. James T. Krik,
I am writing this mail to inform you that I have developed a charter for the Network
Installation project in Western Mining. I am attaching the project charter document for you to go
through the same. If you find the charter appropriate for the project, kindly approve the charter
so that we can start the project. If your find any scope of changes in the charter, kindly highlight
the same so that we can rectify it.
Thanks and Regards,
Please Insert Your Name
Project Manager,
Pacific IT Solutions
Task 5
Three Simple Network Management Protocol (SNMP) monitors that can be used by
Western Mining, for collection and displaying of the SNMP data are listed as follows-
Project Charter.doc
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

10
NETWORK INSTALLATION IN WESTERN MINING
1. PRTG network Monitor: PRTG can be used of monitoring the entire IT
infrastructure of an organization and supports all version of SNMP. Therefore, this particular
SNMP monitor can be used by Western Mining.
2. Cacti: Cacti is recommended as another SNMP monitor which could be used by
Western Mining to graph the network of Pacific IT solutions.
3. Horizon 24: Horizon 24 is recommended for western mining to be used as a SNMP
monitor for displaying the SNMP data. The Horizon 24 include 100 key updates along with the
streaming telemetry and network traffic.
Task 6
The characteristics of successful technical teams in a project are indicated as follows-
1. A Small Team: One of the most effective strategies of developing a successful team is
developing a small team based on the skills of the members and the scope of the project. Less
people in the team reduces the project risks
2. Complementary Skills: The competencies and the skills of the members ascertain
successful delivery of project requirements. A project team should have people with right
combination of the skill sets.
3. A common Purpose: All the members of a team should work for a specific purpose.
This is ideal for successful project completion.
4. Performance Goals: The project management team that is formed should have a
meaningful purpose for establishing an accurate project goals.
NETWORK INSTALLATION IN WESTERN MINING
1. PRTG network Monitor: PRTG can be used of monitoring the entire IT
infrastructure of an organization and supports all version of SNMP. Therefore, this particular
SNMP monitor can be used by Western Mining.
2. Cacti: Cacti is recommended as another SNMP monitor which could be used by
Western Mining to graph the network of Pacific IT solutions.
3. Horizon 24: Horizon 24 is recommended for western mining to be used as a SNMP
monitor for displaying the SNMP data. The Horizon 24 include 100 key updates along with the
streaming telemetry and network traffic.
Task 6
The characteristics of successful technical teams in a project are indicated as follows-
1. A Small Team: One of the most effective strategies of developing a successful team is
developing a small team based on the skills of the members and the scope of the project. Less
people in the team reduces the project risks
2. Complementary Skills: The competencies and the skills of the members ascertain
successful delivery of project requirements. A project team should have people with right
combination of the skill sets.
3. A common Purpose: All the members of a team should work for a specific purpose.
This is ideal for successful project completion.
4. Performance Goals: The project management team that is formed should have a
meaningful purpose for establishing an accurate project goals.

11
NETWORK INSTALLATION IN WESTERN MINING
5. Approach: A team should be able to identify a correct approach for execution and
completion of an undertaken project work.
6. Mutual Accountability: The mutual accountability within the team helps in
achievement of the project milestone in an accurate manner.
NETWORK INSTALLATION IN WESTERN MINING
5. Approach: A team should be able to identify a correct approach for execution and
completion of an undertaken project work.
6. Mutual Accountability: The mutual accountability within the team helps in
achievement of the project milestone in an accurate manner.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 24
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.