Network Upgrade Project: Wireless Network Implementation
VerifiedAdded on 2025/06/19
|26
|2693
|186
AI Summary
Desklib provides solved assignments and past papers to help students succeed.

ETWORK PROJECT MANAGEMENT
Upgrading the existing wired network to new
Wireless network for the organization
Student Name:
Student ID:
Upgrading the existing wired network to new
Wireless network for the organization
Student Name:
Student ID:
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Contents
Introduction.................................................................................................................................................3
Project scope...........................................................................................................................................3
Work Breakdown Structure (WBS)..............................................................................................................4
Estimated time-line...................................................................................................................................10
Resources needed.....................................................................................................................................11
Gantt Charts and Network Diagrams.........................................................................................................12
Estimated cost...........................................................................................................................................14
Quality plan...............................................................................................................................................15
Stakeholder analysis..................................................................................................................................16
Communications plan................................................................................................................................17
Risks management plan.............................................................................................................................18
Ethical issues analysis................................................................................................................................19
Project deployment plan...........................................................................................................................20
Project Signoff...........................................................................................................................................21
Post project review................................................................................................................................22
Conclusion.................................................................................................................................................23
References.................................................................................................................................................24
List of tables and images
Table 1: List of tasks....................................................................................................................................6
Table 2: Table for the estimated cost of the project.................................................................................14
Table 3: Risk management table...............................................................................................................18
Table 4: Project Signoff..............................................................................................................................21
Introduction.................................................................................................................................................3
Project scope...........................................................................................................................................3
Work Breakdown Structure (WBS)..............................................................................................................4
Estimated time-line...................................................................................................................................10
Resources needed.....................................................................................................................................11
Gantt Charts and Network Diagrams.........................................................................................................12
Estimated cost...........................................................................................................................................14
Quality plan...............................................................................................................................................15
Stakeholder analysis..................................................................................................................................16
Communications plan................................................................................................................................17
Risks management plan.............................................................................................................................18
Ethical issues analysis................................................................................................................................19
Project deployment plan...........................................................................................................................20
Project Signoff...........................................................................................................................................21
Post project review................................................................................................................................22
Conclusion.................................................................................................................................................23
References.................................................................................................................................................24
List of tables and images
Table 1: List of tasks....................................................................................................................................6
Table 2: Table for the estimated cost of the project.................................................................................14
Table 3: Risk management table...............................................................................................................18
Table 4: Project Signoff..............................................................................................................................21

Figure 1: WBS structure for the given project.............................................................................................5
Figure 2: Gantt Chart for the given project................................................................................................12
Figure 3: Network diagram of the given project........................................................................................13
Figure 2: Gantt Chart for the given project................................................................................................12
Figure 3: Network diagram of the given project........................................................................................13
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Introduction
Project Management is a term developed to define all the steps and process which are used to manage
and control each and every action taken within any project in order to achieve high success rate for the
complete project instead of the failure of error with the project. It helps in proper planning of the
complete project in advance as well as their evaluation on multiple factors to remove any error or
conflict within the project in advance before actual implementation of the project (Kerzner, 2017). Here,
a project to upgrade the existing wired network with a new “Wireless” network for an organization has
been discussed.
Project scope
This project has been designed and developed in such a way that it will enhance the skills of an
individual to manage and control complete project with proper coordination, planning, and evaluation
for the project along with the estimation of the total cost of new project for the organization which
fulfills the aim of this project.
Project Management is a term developed to define all the steps and process which are used to manage
and control each and every action taken within any project in order to achieve high success rate for the
complete project instead of the failure of error with the project. It helps in proper planning of the
complete project in advance as well as their evaluation on multiple factors to remove any error or
conflict within the project in advance before actual implementation of the project (Kerzner, 2017). Here,
a project to upgrade the existing wired network with a new “Wireless” network for an organization has
been discussed.
Project scope
This project has been designed and developed in such a way that it will enhance the skills of an
individual to manage and control complete project with proper coordination, planning, and evaluation
for the project along with the estimation of the total cost of new project for the organization which
fulfills the aim of this project.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Work Breakdown Structure (WBS)
It consists of all the details of different stages of the complete project which plays a significant role in
planning as well as management of different task which needs to be performed at a specific task and
their order in the project. It helps to increase or decrease the costing and resources required within the
project (Robinson et al. 2018). Different stages of the given project for network upgrade has been shown
below:
It consists of all the details of different stages of the complete project which plays a significant role in
planning as well as management of different task which needs to be performed at a specific task and
their order in the project. It helps to increase or decrease the costing and resources required within the
project (Robinson et al. 2018). Different stages of the given project for network upgrade has been shown
below:

Figure 1: WBS structure for the given project
U p g ra d in g th e e x is ti n g w ire d
n e tw o rk to n e w W ire le ss n e tw o rk
Planning
Survey of existing network
Analysis of new users and
devices
Selection of new
equipment
Research on new wireless
devices
Selection of supplier
Designing of new network
Layout for new network
Testing and evaluation of
designed layout
Implementation of new
network design
Wiring for new network
design
Setup of new wireless
devices
Configuration of new
devices
Testing
Task NameTesting of new
network
Checking errors
Fixing errors and
connectivity issues
Finalizing new network
Task NameCompletion of
new wireless network
Final testing for wireless
network
U p g ra d in g th e e x is ti n g w ire d
n e tw o rk to n e w W ire le ss n e tw o rk
Planning
Survey of existing network
Analysis of new users and
devices
Selection of new
equipment
Research on new wireless
devices
Selection of supplier
Designing of new network
Layout for new network
Testing and evaluation of
designed layout
Implementation of new
network design
Wiring for new network
design
Setup of new wireless
devices
Configuration of new
devices
Testing
Task NameTesting of new
network
Checking errors
Fixing errors and
connectivity issues
Finalizing new network
Task NameCompletion of
new wireless network
Final testing for wireless
network
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Table 1: List of tasks
Task Mode Task Name Duration Start Finish Predecessors Resource
Names Cost
Auto
Scheduled
Upgrading the
existing wired
network to new
Wireless
network
53 wks Mon
7/15/19
Fri
7/17/20 $51,040.00
Auto
Scheduled Planning 7 wks Mon
7/15/19
Fri
8/30/19 $7,840.00
Auto
Scheduled
Survey of
existing network 4 wks Mon
7/15/19 Fri 8/9/19
Network
Designer,
Project
Manager
$4,000.00
Auto
Scheduled
Analysis of
new users and
devices
3 wks Mon
8/12/19
Fri
8/30/19 2
Network
Administrator,
Project
Manager
$3,840.00
Auto
Scheduled Milestone: 0 days Fri
8/30/19
Fri
8/30/19 3 $0.00
Auto
Scheduled
Selection of
new equipment 7 wks Mon
9/2/19
Fri
10/18/19 1 $7,160.00
Auto
Scheduled
Research on
new wireless
devices
4 wks Mon
9/2/19
Fri
9/27/19 4 IT manager $2,720.00
Auto
Scheduled
Selection of
supplier
3 wks Mon
9/30/19
Fri
10/18/19
6 IT manager,
Project
$4,440.00
Task Mode Task Name Duration Start Finish Predecessors Resource
Names Cost
Auto
Scheduled
Upgrading the
existing wired
network to new
Wireless
network
53 wks Mon
7/15/19
Fri
7/17/20 $51,040.00
Auto
Scheduled Planning 7 wks Mon
7/15/19
Fri
8/30/19 $7,840.00
Auto
Scheduled
Survey of
existing network 4 wks Mon
7/15/19 Fri 8/9/19
Network
Designer,
Project
Manager
$4,000.00
Auto
Scheduled
Analysis of
new users and
devices
3 wks Mon
8/12/19
Fri
8/30/19 2
Network
Administrator,
Project
Manager
$3,840.00
Auto
Scheduled Milestone: 0 days Fri
8/30/19
Fri
8/30/19 3 $0.00
Auto
Scheduled
Selection of
new equipment 7 wks Mon
9/2/19
Fri
10/18/19 1 $7,160.00
Auto
Scheduled
Research on
new wireless
devices
4 wks Mon
9/2/19
Fri
9/27/19 4 IT manager $2,720.00
Auto
Scheduled
Selection of
supplier
3 wks Mon
9/30/19
Fri
10/18/19
6 IT manager,
Project
$4,440.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Manager
Auto
Scheduled Milestone: 0 days Fri
10/18/19
Fri
10/18/19 7 $0.00
Auto
Scheduled
Designing of
new network 10 wks Mon
10/21/19
Fri
12/27/19 5 $4,400.00
Auto
Scheduled
Layout for
new network 5 wks Mon
10/21/19
Fri
11/22/19 8 Network
Designer $1,000.00
Auto
Scheduled
Testing and
evaluation of
designed layout
5 wks Mon
11/25/19
Fri
12/27/19 10
Network
Administrator,
Network
Designer
$3,400.00
Auto
Scheduled Milestone: 0 days Fri
12/27/19
Fri
12/27/19 11 $0.00
Auto
Scheduled
Implementation
of new network
design
14 wks Mon
12/30/19 Fri 4/3/20 9 $13,680.00
Auto
Scheduled
Wiring for new
network design 5 wks Mon
12/30/19
Fri
1/31/20 12 Project team,
Technical Staff $4,200.00
Auto
Scheduled
Setup of new
wireless devices 5 wks Mon
2/3/20 Fri 3/6/20 14 Project team,
Technical Staff $4,200.00
Auto
Scheduled
Configuration
of new devices 4 wks Mon
3/9/20 Fri 4/3/20 15
Network
Administrator,
Project team,
Technical Staff
$5,280.00
Auto
Scheduled Milestone: 0 days Fri 4/3/20 Fri 4/3/20 16 $0.00
Auto
Scheduled Milestone: 0 days Fri
10/18/19
Fri
10/18/19 7 $0.00
Auto
Scheduled
Designing of
new network 10 wks Mon
10/21/19
Fri
12/27/19 5 $4,400.00
Auto
Scheduled
Layout for
new network 5 wks Mon
10/21/19
Fri
11/22/19 8 Network
Designer $1,000.00
Auto
Scheduled
Testing and
evaluation of
designed layout
5 wks Mon
11/25/19
Fri
12/27/19 10
Network
Administrator,
Network
Designer
$3,400.00
Auto
Scheduled Milestone: 0 days Fri
12/27/19
Fri
12/27/19 11 $0.00
Auto
Scheduled
Implementation
of new network
design
14 wks Mon
12/30/19 Fri 4/3/20 9 $13,680.00
Auto
Scheduled
Wiring for new
network design 5 wks Mon
12/30/19
Fri
1/31/20 12 Project team,
Technical Staff $4,200.00
Auto
Scheduled
Setup of new
wireless devices 5 wks Mon
2/3/20 Fri 3/6/20 14 Project team,
Technical Staff $4,200.00
Auto
Scheduled
Configuration
of new devices 4 wks Mon
3/9/20 Fri 4/3/20 15
Network
Administrator,
Project team,
Technical Staff
$5,280.00
Auto
Scheduled Milestone: 0 days Fri 4/3/20 Fri 4/3/20 16 $0.00

Auto
Scheduled Testing 10 wks Mon
4/6/20
Fri
6/12/20 13 $7,920.00
Auto
Scheduled
Testing of new
network 4 wks Mon
4/6/20 Fri 5/1/20 17 Network
Administrator $1,920.00
Auto
Scheduled
Checking
errors 3 wks Mon
5/4/20
Fri
5/22/20 19 Network
Administrator $1,440.00
Auto
Scheduled
Fixing errors
and connectivity
issues
3 wks Mon
5/25/20
Fri
6/12/20 20
Network
Administrator,
Network
Designer,
Project team,
Technical Staff
$4,560.00
Auto
Scheduled Milestone: 0 days Fri
6/12/20
Fri
6/12/20 21 $0.00
Auto
Scheduled
Finalizing new
network 5 wks Mon
6/15/20
Fri
7/17/20 18 $10,040.00
Auto
Scheduled
Completion of
the new wireless
network
2 wks Mon
6/15/20
Fri
6/26/20 22
Network
Administrator,
Project team,
IT Staff
$2,960.00
Auto
Scheduled
Final testing
for wireless
network
3 wks Mon
6/29/20
Fri
7/17/20 24
IT manager, IT
Staff, Network
Administrator,
Project
Manager
$7,080.00
Auto
Scheduled
Milestone:
Network ready to
0 days Fri
7/17/20
Fri
7/17/20
25 $0.00
Scheduled Testing 10 wks Mon
4/6/20
Fri
6/12/20 13 $7,920.00
Auto
Scheduled
Testing of new
network 4 wks Mon
4/6/20 Fri 5/1/20 17 Network
Administrator $1,920.00
Auto
Scheduled
Checking
errors 3 wks Mon
5/4/20
Fri
5/22/20 19 Network
Administrator $1,440.00
Auto
Scheduled
Fixing errors
and connectivity
issues
3 wks Mon
5/25/20
Fri
6/12/20 20
Network
Administrator,
Network
Designer,
Project team,
Technical Staff
$4,560.00
Auto
Scheduled Milestone: 0 days Fri
6/12/20
Fri
6/12/20 21 $0.00
Auto
Scheduled
Finalizing new
network 5 wks Mon
6/15/20
Fri
7/17/20 18 $10,040.00
Auto
Scheduled
Completion of
the new wireless
network
2 wks Mon
6/15/20
Fri
6/26/20 22
Network
Administrator,
Project team,
IT Staff
$2,960.00
Auto
Scheduled
Final testing
for wireless
network
3 wks Mon
6/29/20
Fri
7/17/20 24
IT manager, IT
Staff, Network
Administrator,
Project
Manager
$7,080.00
Auto
Scheduled
Milestone:
Network ready to
0 days Fri
7/17/20
Fri
7/17/20
25 $0.00
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

use
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Estimated time-line
It is one of the most significant parts for any project which needs to be calculated first so that project
planning can be developed in a proper way along with the allocation of all the resources and
management of an estimated value for the cost of the project (Barber, 2019). Here the estimated time
of “53 weeks” has been taken to complete the project with given resources.
It is one of the most significant parts for any project which needs to be calculated first so that project
planning can be developed in a proper way along with the allocation of all the resources and
management of an estimated value for the cost of the project (Barber, 2019). Here the estimated time
of “53 weeks” has been taken to complete the project with given resources.

Resources needed
It is another significant part of a given project in order to manage all the tasks and stages of a given
project within the given timeline using equipment & tools available to complete the project within the
estimated range of cost. With the development of new technology, multiple applications and software
have been invented to manage resource allocation and their requirement in the project (Aston, 2019).
Different resources required in the given “Network Project” has been listed below:
Stakeholders and other members of the project
Project team
Network tools
Wireless devices
Configuration applications and software
Security equipment and their arrangement.
Network applications and their management.
Availability of testing agent and their tools
It is another significant part of a given project in order to manage all the tasks and stages of a given
project within the given timeline using equipment & tools available to complete the project within the
estimated range of cost. With the development of new technology, multiple applications and software
have been invented to manage resource allocation and their requirement in the project (Aston, 2019).
Different resources required in the given “Network Project” has been listed below:
Stakeholders and other members of the project
Project team
Network tools
Wireless devices
Configuration applications and software
Security equipment and their arrangement.
Network applications and their management.
Availability of testing agent and their tools
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 26
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.