This project report focuses on the Wonboyn River Bridge widening project undertaken by Welbilt Pty Ltd. The report details the planning, execution, and management aspects of the project, including the work breakdown structure (WBS), network diagram created using MS Project, and identification of critical activities. It covers initial site establishment, demolition, pile construction, and the various phases involved in building the bridge. The report also includes reflective comments on team performance, highlighting the roles and responsibilities of the project manager and team members. The analysis of the network diagram identifies critical paths and provides insights into project progress and potential challenges. The ultimate goal of the project is to widen the existing highway bridge over the Wonboyn River, improving traffic flow and overall transportation infrastructure. Desklib provides students access to similar solved assignments and past papers for academic support.

Running head: PROJECT REPORT
Project Report
Wonboyn River Bridge Project
Name of the Student:
Student ID:
Name of the University:
Project Report
Wonboyn River Bridge Project
Name of the Student:
Student ID:
Name of the University:
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1PROJECT REPORT
Executive Summary
The following assignment had been made on the concept of developing the planning the
execution of the activities and aligning the significant management of the operations. The project
of Wonboyn River Bridge had been developed for widening of the existing highway bridge over
the river. The Welbilt Pty Ltd had been planning for forming the construction of the bridge and
improving the travelling at the locations. The people had been able to improve their conveyance
with the help of the increased area for travelling. The report would include the work breakdown
structure construction of the project and identifying the probable construction of the highway
bridge. The network diagram had been developed using Ms-Project software and the report had
been developed on the proper management of the operations for the project.
Executive Summary
The following assignment had been made on the concept of developing the planning the
execution of the activities and aligning the significant management of the operations. The project
of Wonboyn River Bridge had been developed for widening of the existing highway bridge over
the river. The Welbilt Pty Ltd had been planning for forming the construction of the bridge and
improving the travelling at the locations. The people had been able to improve their conveyance
with the help of the increased area for travelling. The report would include the work breakdown
structure construction of the project and identifying the probable construction of the highway
bridge. The network diagram had been developed using Ms-Project software and the report had
been developed on the proper management of the operations for the project.

2PROJECT REPORT
Table of Contents
Introduction......................................................................................................................................3
Reflective Comments on Team Performance..................................................................................3
Identification and description of project activities..........................................................................4
Network Diagram..........................................................................................................................11
Analysis of Network......................................................................................................................12
Comments on Relevance of work..................................................................................................12
Suitability of network....................................................................................................................14
Conclusion.....................................................................................................................................14
Bibliography..................................................................................................................................16
Table of Contents
Introduction......................................................................................................................................3
Reflective Comments on Team Performance..................................................................................3
Identification and description of project activities..........................................................................4
Network Diagram..........................................................................................................................11
Analysis of Network......................................................................................................................12
Comments on Relevance of work..................................................................................................12
Suitability of network....................................................................................................................14
Conclusion.....................................................................................................................................14
Bibliography..................................................................................................................................16
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3PROJECT REPORT
Introduction
The specific project alignment would be effectively managed with the formation and
deployment for the alignment and influence management (Kerzner and Kerzner 2017). The
construction management includes the successful integration and implication and listing probable
information management. The project plan development had been successfully implied with the
continuation of the successful project execution. The management of the construction projects
had been implied with the management of the probable information management for developing
the construction project execution (Raj and Wadsamudrakar 2018). The improvement of the
highway construction would be effectively managed with the consideration and utilization of the
successive project plan development.
The following assignment is effectively developed for considering the utilization of the
effective implication management. The improved functional development can be implied with
the consideration and utilization management. The improvement of the information analysis is
implied with the consideration of the factors and alignment of the activities. The report is implied
for taking care of the construction management and information development of activities of
Wonboyn River Bridge Project. The discussion of the network diagram would include the
probable identification of the work packages and forming proper project plan development. The
narrative analysis of the team performance would be done for taking care of the information
management for the construction project.
Reflective Comments on Team Performance
The reflective review of the project operations had been helpful for implying the
management of the activities. I was the project manager with the responsibilities of managing
Introduction
The specific project alignment would be effectively managed with the formation and
deployment for the alignment and influence management (Kerzner and Kerzner 2017). The
construction management includes the successful integration and implication and listing probable
information management. The project plan development had been successfully implied with the
continuation of the successful project execution. The management of the construction projects
had been implied with the management of the probable information management for developing
the construction project execution (Raj and Wadsamudrakar 2018). The improvement of the
highway construction would be effectively managed with the consideration and utilization of the
successive project plan development.
The following assignment is effectively developed for considering the utilization of the
effective implication management. The improved functional development can be implied with
the consideration and utilization management. The improvement of the information analysis is
implied with the consideration of the factors and alignment of the activities. The report is implied
for taking care of the construction management and information development of activities of
Wonboyn River Bridge Project. The discussion of the network diagram would include the
probable identification of the work packages and forming proper project plan development. The
narrative analysis of the team performance would be done for taking care of the information
management for the construction project.
Reflective Comments on Team Performance
The reflective review of the project operations had been helpful for implying the
management of the activities. I was the project manager with the responsibilities of managing
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4PROJECT REPORT
and executing the project operations. I had to make sure that the project work was divided to
specific persons for executing the project activities. We were also responsible for analysing and
planning the completion of the activities and listing the compact analysis of the project
completion. My team comprised of external contractor for resource accumulation and
development of effective alignment model. The project team had the responsibility of developing
successive completion of the project. Being a manager I was responsible for the completion of
the project activities. The planner was involved for developing the project plan for the
completion of the effective project completion. The management of the successful project
activities completion had been developed confiding the management of the operations. The
implication of the factors of development was highly implied with the formation of the
successive project completion and development management. The alignment model is implied
with the continuation and deployment model for the utilization management.
Identification and description of project activities
The Wonboyn River Bridge Project had been developed for widening of the existing
highway bridge over the river. The Welbilt Pty Ltd had been planning for forming the
construction of the bridge and improving the travelling at the locations. The following is the list
of project activities,
WBS Task Name
0 WONBOYN RIVER BRIDGE PROJECT
1 Start, Administration
2 Initial Site Establishment
2.1 Initial Surveying
and executing the project operations. I had to make sure that the project work was divided to
specific persons for executing the project activities. We were also responsible for analysing and
planning the completion of the activities and listing the compact analysis of the project
completion. My team comprised of external contractor for resource accumulation and
development of effective alignment model. The project team had the responsibility of developing
successive completion of the project. Being a manager I was responsible for the completion of
the project activities. The planner was involved for developing the project plan for the
completion of the effective project completion. The management of the successful project
activities completion had been developed confiding the management of the operations. The
implication of the factors of development was highly implied with the formation of the
successive project completion and development management. The alignment model is implied
with the continuation and deployment model for the utilization management.
Identification and description of project activities
The Wonboyn River Bridge Project had been developed for widening of the existing
highway bridge over the river. The Welbilt Pty Ltd had been planning for forming the
construction of the bridge and improving the travelling at the locations. The following is the list
of project activities,
WBS Task Name
0 WONBOYN RIVER BRIDGE PROJECT
1 Start, Administration
2 Initial Site Establishment
2.1 Initial Surveying

5PROJECT REPORT
2.2 Site Clearance
2.3 Signage and Protection
2.4 Drainage system
2.5 Security and guard outposts
2.6 Site Office
2.7 Staff Area/ Parking
2.8 Site Induction
2.9 Traffic Signage
2.10 Accessing Roads
2.11 Temporary Services
2.12 Notify and receive Casting Steel (PSC)
2.13 Construct Casting Bay
3 Surveying
3.1 Set out for Pre-existing bridge
3.2 Set out for Pier Piles
3.3 Set out for pier Piles
4 Demolition
4.1 Railing/End post Demolish
4.2 Partially demolish deck/wing wall
5 De watering/Drainage of creek
5.1 Establish Site boundaries
5.2 Embankment
5.3 Place Sheet Pile to create Coffer Dam
5.4 Drain water
6 Manufacture PSC Planks
2.2 Site Clearance
2.3 Signage and Protection
2.4 Drainage system
2.5 Security and guard outposts
2.6 Site Office
2.7 Staff Area/ Parking
2.8 Site Induction
2.9 Traffic Signage
2.10 Accessing Roads
2.11 Temporary Services
2.12 Notify and receive Casting Steel (PSC)
2.13 Construct Casting Bay
3 Surveying
3.1 Set out for Pre-existing bridge
3.2 Set out for Pier Piles
3.3 Set out for pier Piles
4 Demolition
4.1 Railing/End post Demolish
4.2 Partially demolish deck/wing wall
5 De watering/Drainage of creek
5.1 Establish Site boundaries
5.2 Embankment
5.3 Place Sheet Pile to create Coffer Dam
5.4 Drain water
6 Manufacture PSC Planks
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6PROJECT REPORT
6.1 Order/Receive Steel Fibres
6.2 Determine plank size/dimensions
6.3 Place pre stressed fibres
6.4 Pour Concrete
6.5 Steam cure concrete, demold
7 Excavation
7.1 Excavate for Abutment Pile A
7.2 Excavate for Abutment Pile B
7.3 Excavate for Pier Pile A
7.4 Excavate for Pier Pile B
8 Construct Abutment Piles
8.1 Establish Site
8.2 Place Steel cases into soil and boring
8.3 Place Steel Reinforcement
8.4 Pour Concrete
8.5 Remove Casing
8.6 Cure Concrete
9 Construct Pier Piles
9.1 Place Steel cases into soil and boring
9.2 Place Steel Reinforcement
9.3 Pour Concrete
9.4 Remove Casing
9.5 Cure Concrete
10 Construct Columns
10.1 Place Steel Reinforcement
6.1 Order/Receive Steel Fibres
6.2 Determine plank size/dimensions
6.3 Place pre stressed fibres
6.4 Pour Concrete
6.5 Steam cure concrete, demold
7 Excavation
7.1 Excavate for Abutment Pile A
7.2 Excavate for Abutment Pile B
7.3 Excavate for Pier Pile A
7.4 Excavate for Pier Pile B
8 Construct Abutment Piles
8.1 Establish Site
8.2 Place Steel cases into soil and boring
8.3 Place Steel Reinforcement
8.4 Pour Concrete
8.5 Remove Casing
8.6 Cure Concrete
9 Construct Pier Piles
9.1 Place Steel cases into soil and boring
9.2 Place Steel Reinforcement
9.3 Pour Concrete
9.4 Remove Casing
9.5 Cure Concrete
10 Construct Columns
10.1 Place Steel Reinforcement
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7PROJECT REPORT
10.2 Put formwork in place
10.3 Pour concrete
10.4 Cure Concrete
10.5 Remove Formwork
11 Construct Headstock
11.1 Place Steel Reinforcement
11.2 Put formwork in place
11.3 Pour concrete
11.4 Cure Concrete
11.5 Remove Formwork
12 Construct Abutments
12.1 Place order for Elastomeric strips
12.2 Erect Scaffolding
12.3 Formwork & Reinforcement
12.4 Pour and Compact/Vibrate Concrete
12.5 Cure Concrete
12.6 Remove Formwork
12.7 Install elastomeric bearings/ motor pads/ dowel Pedestals
13 Place PSC
13.1 Order Crane
13.2 Move PSC planks to site
13.3 Order Protection Angle
13.4 Set out position
13.5 Put PSC Planks in place
13.6 Fix Protection Angle
10.2 Put formwork in place
10.3 Pour concrete
10.4 Cure Concrete
10.5 Remove Formwork
11 Construct Headstock
11.1 Place Steel Reinforcement
11.2 Put formwork in place
11.3 Pour concrete
11.4 Cure Concrete
11.5 Remove Formwork
12 Construct Abutments
12.1 Place order for Elastomeric strips
12.2 Erect Scaffolding
12.3 Formwork & Reinforcement
12.4 Pour and Compact/Vibrate Concrete
12.5 Cure Concrete
12.6 Remove Formwork
12.7 Install elastomeric bearings/ motor pads/ dowel Pedestals
13 Place PSC
13.1 Order Crane
13.2 Move PSC planks to site
13.3 Order Protection Angle
13.4 Set out position
13.5 Put PSC Planks in place
13.6 Fix Protection Angle

8PROJECT REPORT
14 Approaching Slab
14.1 Set out Position
14.2 Put Reinforcement in place
14.3 Place formwork
14.4 Pour concrete
14.5 Cure and harden concrete
14.6 Remove Formwork
15 Parapet
15.1 Core
15.2 Put Dowel Reinforcement in place
15.3 Epoxy Mortar (Fill Reo)
15.4 Set out positions
15.5 Put Reinforcement in place
15.6 Place formwork
15.7 Pour Concrete
15.8 Cure/ Harden concrete
15.9 Remove formwork
16 Construct Main Deck
16.1 Set Out Positions
16.2 Put formwork in place for Scutter
16.3 Pour Asphalt concrete
16.4 Cure/ Harden Concrete
16.5 Remove Formwork
17 Wing walls
17.1 Place reinforcement in place
14 Approaching Slab
14.1 Set out Position
14.2 Put Reinforcement in place
14.3 Place formwork
14.4 Pour concrete
14.5 Cure and harden concrete
14.6 Remove Formwork
15 Parapet
15.1 Core
15.2 Put Dowel Reinforcement in place
15.3 Epoxy Mortar (Fill Reo)
15.4 Set out positions
15.5 Put Reinforcement in place
15.6 Place formwork
15.7 Pour Concrete
15.8 Cure/ Harden concrete
15.9 Remove formwork
16 Construct Main Deck
16.1 Set Out Positions
16.2 Put formwork in place for Scutter
16.3 Pour Asphalt concrete
16.4 Cure/ Harden Concrete
16.5 Remove Formwork
17 Wing walls
17.1 Place reinforcement in place
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

9PROJECT REPORT
17.2 Put formwork in place
17.3 Pour concrete
17.4 Cure/Harden Concrete
17.5 Remove formwork
18 Railings
18.1 Place order for Barrier Railings
18.2 Railing Set out
18.3 Cast Posts
18.4 Use Protective Coating
18.5 Weld
18.6 Construct Panels
19 Site Closure
19.1 Cleanup
19.2 Remove site services, amenities, power…
20 Project Completion
Explanation of the project activities: The Wonboyn River Bridge Project is developed
for constructing the bridge with a wider width and it would be implied with the management of
the successful implementation model. The project is initialized with the operations of Start,
Administration process where all the information collection is done.
The first phase of the project includes initial site establishment comprising of the
activities of initial surveying, site clearance, signage and protection, drainage system, security
and guard outposts, site office, staff area/ parking, site induction, traffic signage, accessing roads,
temporary services, notify and receive casting steel (PSC), and construct casting bay.
17.2 Put formwork in place
17.3 Pour concrete
17.4 Cure/Harden Concrete
17.5 Remove formwork
18 Railings
18.1 Place order for Barrier Railings
18.2 Railing Set out
18.3 Cast Posts
18.4 Use Protective Coating
18.5 Weld
18.6 Construct Panels
19 Site Closure
19.1 Cleanup
19.2 Remove site services, amenities, power…
20 Project Completion
Explanation of the project activities: The Wonboyn River Bridge Project is developed
for constructing the bridge with a wider width and it would be implied with the management of
the successful implementation model. The project is initialized with the operations of Start,
Administration process where all the information collection is done.
The first phase of the project includes initial site establishment comprising of the
activities of initial surveying, site clearance, signage and protection, drainage system, security
and guard outposts, site office, staff area/ parking, site induction, traffic signage, accessing roads,
temporary services, notify and receive casting steel (PSC), and construct casting bay.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

10PROJECT REPORT
The second phase of the project surveying involves set out for pre-existing bridge, set out
for pier piles, and set out for pier piles. The next phase Demolition includes the activities of
railing/end post demolishes and partially demolishes deck/wing wall de watering/drainage of
creek. The next phase, establish site boundaries includes the activities of embankment, place
sheet pile to create coffer dam, and drain water.
The next phase, manufacture PSC planks includes the activities of order/receive steel
fibres, determine plank size/dimensions, place pre stressed fibres, pour concrete, and steam cure
concrete, demold. The next phase excavation includes the activities of excavate for abutment pile
A, excavate for abutment pile B, excavate for pier pile A, and excavate for pier pile B. The next
phase, construct abutment piles includes the activities of establish site, place steel cases into soil
and boring, place steel reinforcement, pour concrete, remove casing, and cure concrete.
The next phase construct pier piles includes the activities of place steel cases into soil and
boring, place steel reinforcement, pour concrete, remove casing, and cure concrete. The next
phase construct columns includes the activities of place steel reinforcement, put formwork in
place, pour concrete, cure concrete, and remove formwork. The next phase construct headstock
includes the activities of place steel reinforcement, put formwork in place, pour concrete, cure
concrete, and remove formwork.
The next phase construct abutments includes the activities of place order for elastomeric
strips, erect scaffolding, formwork & reinforcement, pour and compact/vibrate concrete, cure
concrete, remove formwork, and install elastomeric bearings/ motor pads/ dowel pedestals. The
next phase place PSC includes the activities of order crane, move PSC planks to site, order
protection angle, set out position, put PSC planks in place, and fix protection angle. The next
The second phase of the project surveying involves set out for pre-existing bridge, set out
for pier piles, and set out for pier piles. The next phase Demolition includes the activities of
railing/end post demolishes and partially demolishes deck/wing wall de watering/drainage of
creek. The next phase, establish site boundaries includes the activities of embankment, place
sheet pile to create coffer dam, and drain water.
The next phase, manufacture PSC planks includes the activities of order/receive steel
fibres, determine plank size/dimensions, place pre stressed fibres, pour concrete, and steam cure
concrete, demold. The next phase excavation includes the activities of excavate for abutment pile
A, excavate for abutment pile B, excavate for pier pile A, and excavate for pier pile B. The next
phase, construct abutment piles includes the activities of establish site, place steel cases into soil
and boring, place steel reinforcement, pour concrete, remove casing, and cure concrete.
The next phase construct pier piles includes the activities of place steel cases into soil and
boring, place steel reinforcement, pour concrete, remove casing, and cure concrete. The next
phase construct columns includes the activities of place steel reinforcement, put formwork in
place, pour concrete, cure concrete, and remove formwork. The next phase construct headstock
includes the activities of place steel reinforcement, put formwork in place, pour concrete, cure
concrete, and remove formwork.
The next phase construct abutments includes the activities of place order for elastomeric
strips, erect scaffolding, formwork & reinforcement, pour and compact/vibrate concrete, cure
concrete, remove formwork, and install elastomeric bearings/ motor pads/ dowel pedestals. The
next phase place PSC includes the activities of order crane, move PSC planks to site, order
protection angle, set out position, put PSC planks in place, and fix protection angle. The next

11PROJECT REPORT
phase Approaching Slab includes the activities of set out position, put reinforcement in place,
place formwork, pour concrete, cure and harden concrete, and remove formwork.
The next phase Parapet includes the activities of core, put dowel reinforcement in place,
epoxy mortar (fill reo), set out positions, put reinforcement in place, place formwork, pour
concrete, cure/ harden concrete, and remove formwork. The next phase construct main deck
includes the activities of set out positions, put formwork in place for scutter, pour asphalt
concrete, cure/ harden concrete, and remove formwork.
The next phase wing walls include the activities of place reinforcement in place, put
formwork in place, pour concrete, cure/harden concrete, and remove formwork. The next phase
railings includes the activities of place order for barrier railings, railing set out, cast posts, use
protective coating, weld, and construct panels. The next phase site closure includes the activities
of cleanup and removes site services, amenities, power. The final milestone for the project is
project completion.
Network Diagram
phase Approaching Slab includes the activities of set out position, put reinforcement in place,
place formwork, pour concrete, cure and harden concrete, and remove formwork.
The next phase Parapet includes the activities of core, put dowel reinforcement in place,
epoxy mortar (fill reo), set out positions, put reinforcement in place, place formwork, pour
concrete, cure/ harden concrete, and remove formwork. The next phase construct main deck
includes the activities of set out positions, put formwork in place for scutter, pour asphalt
concrete, cure/ harden concrete, and remove formwork.
The next phase wing walls include the activities of place reinforcement in place, put
formwork in place, pour concrete, cure/harden concrete, and remove formwork. The next phase
railings includes the activities of place order for barrier railings, railing set out, cast posts, use
protective coating, weld, and construct panels. The next phase site closure includes the activities
of cleanup and removes site services, amenities, power. The final milestone for the project is
project completion.
Network Diagram
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 18
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.