Project Charter for SAP Business All-in-One Deployment at Yes Chemist
VerifiedAdded on 2022/11/26
|11
|1970
|382
Project
AI Summary
This project charter outlines the deployment of SAP Business All-in-One for Yes Chemist, a pharmacy group. The project aims to address operational weaknesses by replacing legacy processes with a new SAP system. The charter details project requirements, including SAP licensing, server room modifications, data conversion, and user training. Key deliverables include project planning, requirements gathering, server room refurbishment, data conversion, integration and testing, go-live, documentation and training, and acceptance testing. The project schedule, spanning 176 days, is broken down into phases with specific milestones. The charter also includes cost breakdowns, quality attributes (real-time reporting, timely service, fast information transfer, and accurate data), and authorization details. This project charter serves as a comprehensive guide for the successful implementation of the SAP system, designed to improve sales, revenue growth, and overall operational efficiency within Yes Chemist. The document also includes a bibliography of relevant project management resources.

VUIS CONSULTING PTY LTD.
PROJECT CHARTER
Project name: SAP Business All-in-One
Projected start date: Tue 25-07-17
Projected end date: Tue 27-03-18
Project Manager: Insert Name
The following template is for educational purposes only.
PROJECT CHARTER
Project name: SAP Business All-in-One
Projected start date: Tue 25-07-17
Projected end date: Tue 27-03-18
Project Manager: Insert Name
The following template is for educational purposes only.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Purpose of the project charter
The project charter for the deployment of SAP Business All-in-one for the pharmacy Yes
Chemist provides the details of the most significant project requirements, major deliverables
and the summary of the project. The charter provides an idea of the estimated project
schedule, cost and the most significant deliverables of the project. The charter further
identifies the significant quality attributes linked with the deployment of SAP in Yes Chemist.
Project summary
The project linked with deployment of SAP in Yes chemist pharmacy is being implemented
to reduce the operational weakness that the group of pharmacies are facing mainly because
of the legacy old process that is followed within Yes Chemist. The project incorporates
conversion of the existing data to a format which will be supported by the new system. The
SAP business all in one system that is proposed is expected to reduce the operational
weaknesses of the pharmacy. The proposed project is expected to improve the considerably
weaker sales and the revenue growth persisting in the organisation. The successful closure
of the project is subjected to identification and elimination of the most significant risks linked
with the project. A realistic project schedule is prepared which will ascertain completion of
each task as per the specifications.
Project Requirements
The successful closure of the project is subjected to fulfilment of certain critical project
requirements, which are as follows-
SAP licensing for 300 users are needed to be considered
Prior to deployment of the SAP, complete modification of the server rooms is
expected
The data conversion process to be followed should involve the legacy data structure
Training the users is a vital consideration
The project execution involves integration of the SAP system with an e-gate feature
The schedule estimate for the SAP deployment project is prepared considering the above
mentioned project requirements.
Major Deliverables/Milestones
The deliverables considered for successful deployment of SAP into the system is indicated
as follows-
Deliverables Deliverables Description
Project Planning This deliverable is linked with preparation
and approval of project charter and Project
Plan
Requirements Phase Collects documents the functional
requirements
Server Room Refurbishment Demolition works and preparation of the
VUIS Consulting Project Charter Page 2
[Insert Author name here]
The project charter for the deployment of SAP Business All-in-one for the pharmacy Yes
Chemist provides the details of the most significant project requirements, major deliverables
and the summary of the project. The charter provides an idea of the estimated project
schedule, cost and the most significant deliverables of the project. The charter further
identifies the significant quality attributes linked with the deployment of SAP in Yes Chemist.
Project summary
The project linked with deployment of SAP in Yes chemist pharmacy is being implemented
to reduce the operational weakness that the group of pharmacies are facing mainly because
of the legacy old process that is followed within Yes Chemist. The project incorporates
conversion of the existing data to a format which will be supported by the new system. The
SAP business all in one system that is proposed is expected to reduce the operational
weaknesses of the pharmacy. The proposed project is expected to improve the considerably
weaker sales and the revenue growth persisting in the organisation. The successful closure
of the project is subjected to identification and elimination of the most significant risks linked
with the project. A realistic project schedule is prepared which will ascertain completion of
each task as per the specifications.
Project Requirements
The successful closure of the project is subjected to fulfilment of certain critical project
requirements, which are as follows-
SAP licensing for 300 users are needed to be considered
Prior to deployment of the SAP, complete modification of the server rooms is
expected
The data conversion process to be followed should involve the legacy data structure
Training the users is a vital consideration
The project execution involves integration of the SAP system with an e-gate feature
The schedule estimate for the SAP deployment project is prepared considering the above
mentioned project requirements.
Major Deliverables/Milestones
The deliverables considered for successful deployment of SAP into the system is indicated
as follows-
Deliverables Deliverables Description
Project Planning This deliverable is linked with preparation
and approval of project charter and Project
Plan
Requirements Phase Collects documents the functional
requirements
Server Room Refurbishment Demolition works and preparation of the
VUIS Consulting Project Charter Page 2
[Insert Author name here]

server room
Data Conversion
Integration and Testing
Conversion of existing data to be stored in
the new system
Go Live The launch of the system
Documentation and training Documentation of the entire report for
lesson learnt and providing the required
training to the staffs
Acceptance testing and sign-off This is the last deliverable of the project
that is linked with successful project
completion and releasing the resources of
the project.
Brief schedule
The schedule prepared for deployment of the SAP in Yes Chemist is indicated in the table
below. The schedule indicates the milestone of the project as well.
Milestone WBS Task Name Duration Start Finish
No 0 SAP Business All-in-One 176 days Tue 25-07-17 Tue 27-03-18
No 1 Project Planning 11 days Tue 25-07-17 Tue 08-08-17
No 1.1 Understanding the
Requirement of the Project 2 days Tue 25-07-17 Wed 26-07-17
No 1.2 Documentation of the
Requirements 1 day Thu 27-07-17 Thu 27-07-17
No 1.3 Development of Project
Charter 4 days Fri 28-07-17 Wed 02-08-17
Yes 1.4 M1: Approval of Project
Charter 0 days Wed 02-08-17 Wed 02-08-17
No 1.5 Development of Project
Plan 4 days Thu 03-08-17 Tue 08-08-17
Yes 1.6 M2: Approval of Project
Plan 0 days Tue 08-08-17 Tue 08-08-17
No 2 Requirements Phase 11 days Wed 09-08-17 Wed 23-08-17
VUIS Consulting Project Charter Page 3
[Insert Author name here]
Data Conversion
Integration and Testing
Conversion of existing data to be stored in
the new system
Go Live The launch of the system
Documentation and training Documentation of the entire report for
lesson learnt and providing the required
training to the staffs
Acceptance testing and sign-off This is the last deliverable of the project
that is linked with successful project
completion and releasing the resources of
the project.
Brief schedule
The schedule prepared for deployment of the SAP in Yes Chemist is indicated in the table
below. The schedule indicates the milestone of the project as well.
Milestone WBS Task Name Duration Start Finish
No 0 SAP Business All-in-One 176 days Tue 25-07-17 Tue 27-03-18
No 1 Project Planning 11 days Tue 25-07-17 Tue 08-08-17
No 1.1 Understanding the
Requirement of the Project 2 days Tue 25-07-17 Wed 26-07-17
No 1.2 Documentation of the
Requirements 1 day Thu 27-07-17 Thu 27-07-17
No 1.3 Development of Project
Charter 4 days Fri 28-07-17 Wed 02-08-17
Yes 1.4 M1: Approval of Project
Charter 0 days Wed 02-08-17 Wed 02-08-17
No 1.5 Development of Project
Plan 4 days Thu 03-08-17 Tue 08-08-17
Yes 1.6 M2: Approval of Project
Plan 0 days Tue 08-08-17 Tue 08-08-17
No 2 Requirements Phase 11 days Wed 09-08-17 Wed 23-08-17
VUIS Consulting Project Charter Page 3
[Insert Author name here]
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

No 2.1 Obtaining the
Functional Requirements 3 days Wed 09-08-17 Fri 11-08-17
No 2.2 Understanding the
Users' Expectations 7 days Wed 09-08-17 Thu 17-08-17
No 2.3
Understanding the
Critical Compliance
Requirements
3 days Fri 18-08-17 Tue 22-08-17
No 2.4 Documentation 1 day Wed 23-08-17 Wed 23-08-17
Yes 2.5 M3: Completion of
Requirements Gathering 0 days Wed 23-08-17 Wed 23-08-17
No 3 Server Room
Refurbishment 82 days Thu 03-08-17 Fri 24-11-17
No 3.1 Demolition 8 hrs Thu 03-08-17 Thu 03-08-17
No 3.2 Sever rom modification 14 days Thu 24-08-17 Tue 12-09-17
No 3.3
Checking If all the
works have been
performed as expected
2 days Wed 13-09-17 Thu 14-09-17
No 3.4 Software Coding 30 days Fri 15-09-17 Thu 26-10-17
No 3.5 Database Coding 20 days Fri 27-10-17 Thu 23-11-17
No 3.6 Connecting new server
with existing server 1 day Fri 24-11-17 Fri 24-11-17
Yes 3.7
M4: Completion of
Server Room
Refurbishment
0 days Fri 24-11-17 Fri 24-11-17
No 4 Data Conversion 71 days Wed 13-09-17 Wed 20-12-17
No 4.1 understand legacy data
structures 3 days Wed 13-09-17 Fri 15-09-17
No 4.2
setup an automated
data extractor script
development
2 days Mon 27-11-17 Tue 28-11-17
No 4.3 data validation and
cleansing effort 3 days Wed 29-11-17 Fri 01-12-17
No 4.4 Completion of B1 1 day Mon 04-12-17 Mon 04-12-17
VUIS Consulting Project Charter Page 4
[Insert Author name here]
Functional Requirements 3 days Wed 09-08-17 Fri 11-08-17
No 2.2 Understanding the
Users' Expectations 7 days Wed 09-08-17 Thu 17-08-17
No 2.3
Understanding the
Critical Compliance
Requirements
3 days Fri 18-08-17 Tue 22-08-17
No 2.4 Documentation 1 day Wed 23-08-17 Wed 23-08-17
Yes 2.5 M3: Completion of
Requirements Gathering 0 days Wed 23-08-17 Wed 23-08-17
No 3 Server Room
Refurbishment 82 days Thu 03-08-17 Fri 24-11-17
No 3.1 Demolition 8 hrs Thu 03-08-17 Thu 03-08-17
No 3.2 Sever rom modification 14 days Thu 24-08-17 Tue 12-09-17
No 3.3
Checking If all the
works have been
performed as expected
2 days Wed 13-09-17 Thu 14-09-17
No 3.4 Software Coding 30 days Fri 15-09-17 Thu 26-10-17
No 3.5 Database Coding 20 days Fri 27-10-17 Thu 23-11-17
No 3.6 Connecting new server
with existing server 1 day Fri 24-11-17 Fri 24-11-17
Yes 3.7
M4: Completion of
Server Room
Refurbishment
0 days Fri 24-11-17 Fri 24-11-17
No 4 Data Conversion 71 days Wed 13-09-17 Wed 20-12-17
No 4.1 understand legacy data
structures 3 days Wed 13-09-17 Fri 15-09-17
No 4.2
setup an automated
data extractor script
development
2 days Mon 27-11-17 Tue 28-11-17
No 4.3 data validation and
cleansing effort 3 days Wed 29-11-17 Fri 01-12-17
No 4.4 Completion of B1 1 day Mon 04-12-17 Mon 04-12-17
VUIS Consulting Project Charter Page 4
[Insert Author name here]
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Configuration
No 4.5
develop automated
script to load data into B1
instance
2 days Tue 05-12-17 Wed 06-12-17
No 4.6 test in real time
instance 3 days Thu 07-12-17 Mon 11-12-17
No 4.7 defect rectification 2 days Tue 12-12-17 Wed 13-12-17
No 4.8
post data migration
analysis and manual data
rectification
1 wk Thu 14-12-17 Wed 20-12-17
Yes 4.9 M5: Completion of Data
Conversion 0 days Wed 20-12-17 Wed 20-12-17
No 5 Integration and Testing 32 days Thu 21-12-17 Fri 02-02-18
No 5.1 Integration of the SAP
system with e-gate feature 5 days Thu 21-12-17 Wed 27-12-17
No 5.2
comprehensive end to
end testing within All-in-
One finance module
10 days Thu 28-12-17 Wed 10-01-18
No 5.3 testing with a live e-
gate instance 7 days Thu 11-01-18 Fri 19-01-18
No 5.4 System Integration
Testing) 7 days Mon 22-01-18 Tue 30-01-18
No 5.5
Incorporation of Testing
Information on Business
Activity Statement
3 days Wed 31-01-18 Fri 02-02-18
Yes 5.6 M6: Completion of
Integration and Testing 0 days Fri 02-02-18 Fri 02-02-18
No 6 Go Live 6 days Mon 05-02-18 Mon 12-02-18
No 6.1
Testing of server
equipment by VUISC
technical staff before SAP
installation
2 days Mon 05-02-18 Tue 06-02-18
No 6.2 Installation by Frontline
Engineer 3 days Wed 07-02-18 Fri 09-02-18
VUIS Consulting Project Charter Page 5
[Insert Author name here]
No 4.5
develop automated
script to load data into B1
instance
2 days Tue 05-12-17 Wed 06-12-17
No 4.6 test in real time
instance 3 days Thu 07-12-17 Mon 11-12-17
No 4.7 defect rectification 2 days Tue 12-12-17 Wed 13-12-17
No 4.8
post data migration
analysis and manual data
rectification
1 wk Thu 14-12-17 Wed 20-12-17
Yes 4.9 M5: Completion of Data
Conversion 0 days Wed 20-12-17 Wed 20-12-17
No 5 Integration and Testing 32 days Thu 21-12-17 Fri 02-02-18
No 5.1 Integration of the SAP
system with e-gate feature 5 days Thu 21-12-17 Wed 27-12-17
No 5.2
comprehensive end to
end testing within All-in-
One finance module
10 days Thu 28-12-17 Wed 10-01-18
No 5.3 testing with a live e-
gate instance 7 days Thu 11-01-18 Fri 19-01-18
No 5.4 System Integration
Testing) 7 days Mon 22-01-18 Tue 30-01-18
No 5.5
Incorporation of Testing
Information on Business
Activity Statement
3 days Wed 31-01-18 Fri 02-02-18
Yes 5.6 M6: Completion of
Integration and Testing 0 days Fri 02-02-18 Fri 02-02-18
No 6 Go Live 6 days Mon 05-02-18 Mon 12-02-18
No 6.1
Testing of server
equipment by VUISC
technical staff before SAP
installation
2 days Mon 05-02-18 Tue 06-02-18
No 6.2 Installation by Frontline
Engineer 3 days Wed 07-02-18 Fri 09-02-18
VUIS Consulting Project Charter Page 5
[Insert Author name here]

No 6.3 Launch 1 day Mon 12-02-18 Mon 12-02-18
Yes 6.4 M7: Application Launch 0 days Mon 12-02-18 Mon 12-02-18
No 7 Documentation and
training 36 days Mon 05-02-18 Mon 26-03-18
No 7.1 Reviewing end user
manuals 2 days Mon 05-02-18 Tue 06-02-18
No 7.2 Customization of the
end user Manuals 10 days Tue 13-02-18 Mon 26-02-18
No 7.3 Customization of
training program 3 days Tue 27-02-18 Thu 01-03-18
No 7.4 Planning the training
sessions 1 day Tue 27-02-18 Tue 27-02-18
No 7.5 Training 15 days Fri 02-03-18 Thu 22-03-18
No 7.6 Documentation 2 days Fri 23-03-18 Mon 26-03-18
Yes 7.7
M8: Completion of
Documentation and
Training
0 days Mon 26-03-18 Mon 26-03-18
No 8 Acceptance testing and
sign-off 85 days Wed 29-11-17 Tue 27-03-18
No 8.1
Checking Completion
of Hardware and Software
Installation
2 days Tue 13-02-18 Wed 14-02-18
No 8.2 Checking Successful
Data Conversion 1 day Tue 27-03-18 Tue 27-03-18
No 8.3 Checking Completion
of Training 1 day Wed 29-11-17 Wed 29-11-17
Yes 8.4 M9: Completion of User
Acceptance Testing 0 days Tue 27-03-18 Tue 27-03-18
Table 1 Brief project schedule
The table 1 provides an idea of the major deliverables and the milestone linked with the
project. The successful closure of the project is subjected to completion of each phase and
delivery of the identified milestone of the project.
VUIS Consulting Project Charter Page 6
[Insert Author name here]
Yes 6.4 M7: Application Launch 0 days Mon 12-02-18 Mon 12-02-18
No 7 Documentation and
training 36 days Mon 05-02-18 Mon 26-03-18
No 7.1 Reviewing end user
manuals 2 days Mon 05-02-18 Tue 06-02-18
No 7.2 Customization of the
end user Manuals 10 days Tue 13-02-18 Mon 26-02-18
No 7.3 Customization of
training program 3 days Tue 27-02-18 Thu 01-03-18
No 7.4 Planning the training
sessions 1 day Tue 27-02-18 Tue 27-02-18
No 7.5 Training 15 days Fri 02-03-18 Thu 22-03-18
No 7.6 Documentation 2 days Fri 23-03-18 Mon 26-03-18
Yes 7.7
M8: Completion of
Documentation and
Training
0 days Mon 26-03-18 Mon 26-03-18
No 8 Acceptance testing and
sign-off 85 days Wed 29-11-17 Tue 27-03-18
No 8.1
Checking Completion
of Hardware and Software
Installation
2 days Tue 13-02-18 Wed 14-02-18
No 8.2 Checking Successful
Data Conversion 1 day Tue 27-03-18 Tue 27-03-18
No 8.3 Checking Completion
of Training 1 day Wed 29-11-17 Wed 29-11-17
Yes 8.4 M9: Completion of User
Acceptance Testing 0 days Tue 27-03-18 Tue 27-03-18
Table 1 Brief project schedule
The table 1 provides an idea of the major deliverables and the milestone linked with the
project. The successful closure of the project is subjected to completion of each phase and
delivery of the identified milestone of the project.
VUIS Consulting Project Charter Page 6
[Insert Author name here]
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Key costs
The key cost linked with the project are indicated in the following cost table-
Task Name Total Cost
SAP Business All-in-One $303,820.00
Project Planning $15,040.00
Understanding the Requirement of the Project $2,080.00
Documentation of the Requirements $480.00
Development of Project Charter $6,240.00
M1: Approval of Project Charter $0.00
Development of Project Plan $6,240.00
M2: Approval of Project Plan $0.00
Requirements Phase $18,320.00
Obtaining the Functional Requirements $4,680.00
Understanding the Users' Expectations $7,280.00
Understanding the Critical Compliance Requirements $5,880.00
Documentation $480.00
M3: Completion of Requirements Gathering $0.00
Server Room Refurbishment $196,480.00
Demolition $0.00
Sever rom modification $15,000.00
Checking If all the works have been performed as
expected $158,120.00
Software Coding $22,800.00
Database Coding $0.00
Connecting new server with existing server $560.00
M4: Completion of Server Room Refurbishment $0.00
Data Conversion $7,720.00
understand legacy data structures $240.00
setup an automated data extractor script development $160.00
data validation and cleansing effort $240.00
Completion of B1 Configuration $80.00
develop automated script to load data into B1 instance $160.00
test in real time instance $2,880.00
defect rectification $160.00
post data migration analysis and manual data
rectification $3,800.00
M5: Completion of Data Conversion $0.00
Integration and Testing $19,720.00
Integration of the SAP system with e-gate feature $400.00
comprehensive end to end testing within All-in-one
finance module $11,200.00
testing with a live e-gate instance $7,280.00
System Integration Testing) $0.00
Incorporation of Testing Information on Business
Activity Statement $840.00
M6: Completion of Integration and Testing $0.00
VUIS Consulting Project Charter Page 7
[Insert Author name here]
The key cost linked with the project are indicated in the following cost table-
Task Name Total Cost
SAP Business All-in-One $303,820.00
Project Planning $15,040.00
Understanding the Requirement of the Project $2,080.00
Documentation of the Requirements $480.00
Development of Project Charter $6,240.00
M1: Approval of Project Charter $0.00
Development of Project Plan $6,240.00
M2: Approval of Project Plan $0.00
Requirements Phase $18,320.00
Obtaining the Functional Requirements $4,680.00
Understanding the Users' Expectations $7,280.00
Understanding the Critical Compliance Requirements $5,880.00
Documentation $480.00
M3: Completion of Requirements Gathering $0.00
Server Room Refurbishment $196,480.00
Demolition $0.00
Sever rom modification $15,000.00
Checking If all the works have been performed as
expected $158,120.00
Software Coding $22,800.00
Database Coding $0.00
Connecting new server with existing server $560.00
M4: Completion of Server Room Refurbishment $0.00
Data Conversion $7,720.00
understand legacy data structures $240.00
setup an automated data extractor script development $160.00
data validation and cleansing effort $240.00
Completion of B1 Configuration $80.00
develop automated script to load data into B1 instance $160.00
test in real time instance $2,880.00
defect rectification $160.00
post data migration analysis and manual data
rectification $3,800.00
M5: Completion of Data Conversion $0.00
Integration and Testing $19,720.00
Integration of the SAP system with e-gate feature $400.00
comprehensive end to end testing within All-in-one
finance module $11,200.00
testing with a live e-gate instance $7,280.00
System Integration Testing) $0.00
Incorporation of Testing Information on Business
Activity Statement $840.00
M6: Completion of Integration and Testing $0.00
VUIS Consulting Project Charter Page 7
[Insert Author name here]
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Go Live $7,440.00
Testing of server equipment by VUISC technical staff
before SAP installation $1,920.00
Installation by Frontline Engineer $3,960.00
Launch $1,560.00
M7: Application Launch $0.00
Documentation and training $33,420.00
Reviewing end user manuals $3,120.00
Customization of the end user Manuals $7,600.00
Customization of training program $5,880.00
Planning the training sessions $1,560.00
Training $14,300.00
Documentation $960.00
M8: Completion of Documentation and Training $0.00
Acceptance testing and sign-off $5,680.00
Checking Completion of Hardware and Software
Installation $3,120.00
Checking Successful Data Conversion $1,640.00
Checking Completion of Training $920.00
M9: Completion of User Acceptance Testing $0.00
Table 2: Representing the cost of the project
Associated Quality Attributes
The necessary quality attributes that are linked with the execution of a project successfully
are as follows-
The system should be able to generate reports in real time
The system should be able to deliver on time services
The information transfer in the system should be fast and reliable
The system should be able to provide accurate data.
Duration
The duration of the project is indicated in the Gantt chart below-
VUIS Consulting Project Charter Page 8
[Insert Author name here]
Testing of server equipment by VUISC technical staff
before SAP installation $1,920.00
Installation by Frontline Engineer $3,960.00
Launch $1,560.00
M7: Application Launch $0.00
Documentation and training $33,420.00
Reviewing end user manuals $3,120.00
Customization of the end user Manuals $7,600.00
Customization of training program $5,880.00
Planning the training sessions $1,560.00
Training $14,300.00
Documentation $960.00
M8: Completion of Documentation and Training $0.00
Acceptance testing and sign-off $5,680.00
Checking Completion of Hardware and Software
Installation $3,120.00
Checking Successful Data Conversion $1,640.00
Checking Completion of Training $920.00
M9: Completion of User Acceptance Testing $0.00
Table 2: Representing the cost of the project
Associated Quality Attributes
The necessary quality attributes that are linked with the execution of a project successfully
are as follows-
The system should be able to generate reports in real time
The system should be able to deliver on time services
The information transfer in the system should be fast and reliable
The system should be able to provide accurate data.
Duration
The duration of the project is indicated in the Gantt chart below-
VUIS Consulting Project Charter Page 8
[Insert Author name here]

VUIS Consulting Project Charter Page 9
[Insert Author name here]
[Insert Author name here]
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Figure 1: The Schedule of the SAP deployment Project
The above figure indicates that the time required to complete the project is 176 days. The
time needed for completion of each phase is indicated in the figure above.
Authorization to proceed
Business Sponsor: Please Insert
Operational Manager (VUISC) Shah Miah
VUIS Consulting Project Charter Page 10
[Insert Author name here]
The above figure indicates that the time required to complete the project is 176 days. The
time needed for completion of each phase is indicated in the figure above.
Authorization to proceed
Business Sponsor: Please Insert
Operational Manager (VUISC) Shah Miah
VUIS Consulting Project Charter Page 10
[Insert Author name here]
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Bibliography
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
Kerzner, H., 2019. Using the project management maturity model: strategic planning for
project management. Wiley.
Larson, E.W. and Gray, C.F., 2017. Project management: The managerial process.
McGraw-Hill Education.
Leach, L.P., 2014. Critical chain project management. Artech House.
Marchewka, J.T., 2014. Information technology project management. John Wiley & Sons.
Milosevic, D.Z. and Martinelli, R.J., 2016. Project management toolbox: tools and techniques
for the practicing project manager. John Wiley & Sons.
VUIS Consulting Project Charter Page 11
[Insert Author name here]
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
Kerzner, H., 2019. Using the project management maturity model: strategic planning for
project management. Wiley.
Larson, E.W. and Gray, C.F., 2017. Project management: The managerial process.
McGraw-Hill Education.
Leach, L.P., 2014. Critical chain project management. Artech House.
Marchewka, J.T., 2014. Information technology project management. John Wiley & Sons.
Milosevic, D.Z. and Martinelli, R.J., 2016. Project management toolbox: tools and techniques
for the practicing project manager. John Wiley & Sons.
VUIS Consulting Project Charter Page 11
[Insert Author name here]
1 out of 11
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.