This document presents a plan for developing a mobile application focused on fitness and weight management. It includes details on roles and responsibilities, budgeting, risk analysis (highlighting low privacy risks associated with wearable technology), and a conclusion emphasizing the app's potential benefits for users seeking to improve their health and well-being.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
PROJECT MANAGEMENT
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Executive Summary
This app is to develop for fitness and weight management. The main functionality of
this application is to track the details and energy intake of the user from the database and
help them to reduce their weight. By monitoring the person activities and then providing the
health tips for the purpose of maintaining the weight.
1
This app is to develop for fitness and weight management. The main functionality of
this application is to track the details and energy intake of the user from the database and
help them to reduce their weight. By monitoring the person activities and then providing the
health tips for the purpose of maintaining the weight.
1
Table of Contents
Executive Summary.............................................................................................................................1
1. Introduction.................................................................................................................................2
2. Assumptions.................................................................................................................................3
3. Project Execution.........................................................................................................................4
4. Planning Methodology.................................................................................................................6
5. Project calendar...........................................................................................................................8
6. Work breakdown structure......................................................................................................12
7. Organisation Break down structure.........................................................................................13
8. Responsibility Assignment Matrix...........................................................................................13
9. Task Details................................................................................................................................13
10. Project schedule Manpower..................................................................................................18
11. Cost estimation.......................................................................................................................18
12. Risk Analysis..........................................................................................................................21
13. Conclusion..............................................................................................................................21
References..........................................................................................................................................21
2
Executive Summary.............................................................................................................................1
1. Introduction.................................................................................................................................2
2. Assumptions.................................................................................................................................3
3. Project Execution.........................................................................................................................4
4. Planning Methodology.................................................................................................................6
5. Project calendar...........................................................................................................................8
6. Work breakdown structure......................................................................................................12
7. Organisation Break down structure.........................................................................................13
8. Responsibility Assignment Matrix...........................................................................................13
9. Task Details................................................................................................................................13
10. Project schedule Manpower..................................................................................................18
11. Cost estimation.......................................................................................................................18
12. Risk Analysis..........................................................................................................................21
13. Conclusion..............................................................................................................................21
References..........................................................................................................................................21
2
1. Introduction
Nowadays, many high quality mobile application are developed for health professionals
and users and focus the entire health care chain, therefore, data collection, diagnosis,
prevention, monitoring and treatment. Our team has developed a fitness and weight
management app which has been enable via android market. The objective of this study is to
share our experience with rolling out a fitness and weight management app. We discuss the
acceptance health application by healthcare industry and end-users. We discuss how mobile
apps will be spread in the closed future, tracking daily energy intake via recording food
consumed then concentrated on meal type and type of snacks from database of kind of meals
and energy content provided in the application. In addition, tracking energy content expanded
through daily activities. The app is to use of daily energy intake by inputting personal
information and also use adaptive algorithm to improve predictive accuracy of weight loss or
gain from the input ("How To Develop The Best Fitness Application?", 2017).
2. Assumptions
The assumptions are listed below (Cooke, Tate & Cooke, 2011).
Task Name
Fitness Development and Management Apps
Project Manager
Review App Requirement
Delivering all project requirements to the development
team.
Technical documentation
Identify the product technical specification based on
client Requirements
Conduct Workshop
To establish High level features
To establish Process flows
Priority Initial Release Plan
3
Nowadays, many high quality mobile application are developed for health professionals
and users and focus the entire health care chain, therefore, data collection, diagnosis,
prevention, monitoring and treatment. Our team has developed a fitness and weight
management app which has been enable via android market. The objective of this study is to
share our experience with rolling out a fitness and weight management app. We discuss the
acceptance health application by healthcare industry and end-users. We discuss how mobile
apps will be spread in the closed future, tracking daily energy intake via recording food
consumed then concentrated on meal type and type of snacks from database of kind of meals
and energy content provided in the application. In addition, tracking energy content expanded
through daily activities. The app is to use of daily energy intake by inputting personal
information and also use adaptive algorithm to improve predictive accuracy of weight loss or
gain from the input ("How To Develop The Best Fitness Application?", 2017).
2. Assumptions
The assumptions are listed below (Cooke, Tate & Cooke, 2011).
Task Name
Fitness Development and Management Apps
Project Manager
Review App Requirement
Delivering all project requirements to the development
team.
Technical documentation
Identify the product technical specification based on
client Requirements
Conduct Workshop
To establish High level features
To establish Process flows
Priority Initial Release Plan
3
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Developer Team
Tracking user activity
Body measurements/weight history
Number of steps/distance travelled
Calories burnt
Favourite types of activity/sports
Duration of exercise
Measuring Heartbeat rate
Movement tracking
Social share
Push notifications
Outstanding design
both UI and UX Parts
Product Backlog of story lines
Pre- release Phase
User acceptance testing
Performance Testing
Training
Release/Production
Warranty
Hotfixes
Support
Sprint release
Project Closure
Completion of contractual and commercial
arrangements
Project evaluation
Lessons Learned to be delivered and prepared to client
and company
4
Tracking user activity
Body measurements/weight history
Number of steps/distance travelled
Calories burnt
Favourite types of activity/sports
Duration of exercise
Measuring Heartbeat rate
Movement tracking
Social share
Push notifications
Outstanding design
both UI and UX Parts
Product Backlog of story lines
Pre- release Phase
User acceptance testing
Performance Testing
Training
Release/Production
Warranty
Hotfixes
Support
Sprint release
Project Closure
Completion of contractual and commercial
arrangements
Project evaluation
Lessons Learned to be delivered and prepared to client
and company
4
3. Project Execution
The Project execution includes the Project plan. The Project plan is given below.
The project plan Task details given below (Heerkens, 2015).
The Project plan resource details are given below.
Resource Name Type Max. Units Std. Rate
Technical Writer Work 100% $ 25.00/hr
Designer Work 100% $ 30.00/hr
Android Developer Work 100% $ 35.00/hr
Project Manager Work 100% $ 50.00/hr
Tester Work 100% $ 25.00/hr
5
The Project execution includes the Project plan. The Project plan is given below.
The project plan Task details given below (Heerkens, 2015).
The Project plan resource details are given below.
Resource Name Type Max. Units Std. Rate
Technical Writer Work 100% $ 25.00/hr
Designer Work 100% $ 30.00/hr
Android Developer Work 100% $ 35.00/hr
Project Manager Work 100% $ 50.00/hr
Tester Work 100% $ 25.00/hr
5
Big Fixer Work 100% $ 25.00/hr
Product Owner Work 100% $ 20.00/hr
Quality Assurer Work 100% $ 35.00/hr
Solution Architect Work 100% $ 30.00/hr
Business Analyst Work 100% $ 40.00/hr
Resource status
Name Start Finish Remaining Work
Technical Writer Wed 06-09-17 Wed 27-09-
17
56 hrs
Designer Fri 15-09-17 Fri 02-02-18 176 hrs
Android Developer Fri 08-09-17 Fri 02-02-18 184 hrs
Project Manager Mon 04-09-17 Fri 02-02-18 280 hrs
Tester Thu 16-11-17 Fri 01-12-17 96 hrs
Big Fixer Thu 16-11-17 Tue 02-01-18 120 hrs
Product Owner Mon 02-10-17 Fri 02-02-18 376 hrs
Quality Assurer Fri 15-09-17 Wed 31-01-
18
184 hrs
Solution Architect Thu 28-09-17 Thu 11-01-18 192 hrs
Business Analyst Fri 15-09-17 Fri 02-02-18 360 hrs
4. Planning Methodology
In fitness Development and management using the project plan to execute the fitness
applications. The Project plan easily understand by using the Gantt chart view in MS project
management. The fitness applications Gantt chart view is shown below (Horine, n.d.).
6
Product Owner Work 100% $ 20.00/hr
Quality Assurer Work 100% $ 35.00/hr
Solution Architect Work 100% $ 30.00/hr
Business Analyst Work 100% $ 40.00/hr
Resource status
Name Start Finish Remaining Work
Technical Writer Wed 06-09-17 Wed 27-09-
17
56 hrs
Designer Fri 15-09-17 Fri 02-02-18 176 hrs
Android Developer Fri 08-09-17 Fri 02-02-18 184 hrs
Project Manager Mon 04-09-17 Fri 02-02-18 280 hrs
Tester Thu 16-11-17 Fri 01-12-17 96 hrs
Big Fixer Thu 16-11-17 Tue 02-01-18 120 hrs
Product Owner Mon 02-10-17 Fri 02-02-18 376 hrs
Quality Assurer Fri 15-09-17 Wed 31-01-
18
184 hrs
Solution Architect Thu 28-09-17 Thu 11-01-18 192 hrs
Business Analyst Fri 15-09-17 Fri 02-02-18 360 hrs
4. Planning Methodology
In fitness Development and management using the project plan to execute the fitness
applications. The Project plan easily understand by using the Gantt chart view in MS project
management. The fitness applications Gantt chart view is shown below (Horine, n.d.).
6
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
The fitness application resource status and cost shown below.
Technical Writer
Designer
Android Developer
Project Manager
Tester
Big Fixer
Product Owner
Quality Assurer
Solution Architect
Business Analyst
0 hrs
50 hrs
100 hrs
150 hrs
200 hrs
250 hrs
300 hrs
350 hrs
400 hrs
Actual Work Remaining Work Baseline Work
Resource Cost
Resource Name Type Max. Units Std. Rate
Technical Writer Work 100% $ 25.00/hr
Designer Work 100% $ 30.00/hr
Android Developer Work 100% $ 35.00/hr
Project Manager Work 100% $ 50.00/hr
Tester Work 100% $ 25.00/hr
Big Fixer Work 100% $ 25.00/hr
7
Technical Writer
Designer
Android Developer
Project Manager
Tester
Big Fixer
Product Owner
Quality Assurer
Solution Architect
Business Analyst
0 hrs
50 hrs
100 hrs
150 hrs
200 hrs
250 hrs
300 hrs
350 hrs
400 hrs
Actual Work Remaining Work Baseline Work
Resource Cost
Resource Name Type Max. Units Std. Rate
Technical Writer Work 100% $ 25.00/hr
Designer Work 100% $ 30.00/hr
Android Developer Work 100% $ 35.00/hr
Project Manager Work 100% $ 50.00/hr
Tester Work 100% $ 25.00/hr
Big Fixer Work 100% $ 25.00/hr
7
Product Owner Work 100% $ 20.00/hr
Quality Assurer Work 100% $ 35.00/hr
Solution Architect Work 100% $ 30.00/hr
Business Analyst Work 100% $ 40.00/hr
The fitness applications Milestones is given below.
04-09-17 24-09-17 14-10-17 03-11-17 23-11-17 13-12-17 02-01-18 22-01-18
0
5
10
15
20
25
30
Remaining Tasks Remaining Actual Tasks
5. Project calendar
8
LATE MILESTONES MILESTONES UP NEXT
Quality Assurer Work 100% $ 35.00/hr
Solution Architect Work 100% $ 30.00/hr
Business Analyst Work 100% $ 40.00/hr
The fitness applications Milestones is given below.
04-09-17 24-09-17 14-10-17 03-11-17 23-11-17 13-12-17 02-01-18 22-01-18
0
5
10
15
20
25
30
Remaining Tasks Remaining Actual Tasks
5. Project calendar
8
LATE MILESTONES MILESTONES UP NEXT
The Overall the fitness development and management application project schedule is shown
below (Kerzner, n.d.).
9
below (Kerzner, n.d.).
9
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
10
11
6. Work breakdown structure
The Fitness development and management work breakdown structure is shown below
(PROJECT MANAGEMENT INSTITUTE., 2017).
12
Fitness Development and Management Apps
Project
manager
Technical
document
ation
Conduct
Workshop
Developer
Team
Pre-
release
Phase
Release/
Production
Project
Closure
Review
App
Requirem
ent
To establish
High level
features
Tracking
user
activity
User
acceptan
ce testing
Warra
nty
Comp
letion
Delivering all
project
requirements
to the
development
team.
Identify the
product
technical
specification
To establish
High level
features
To establish
High level
features
Social
share
Push
notificatio
ns
Outstandi
ng design
Perform
ance
Testing
Traini
ng
Hotf
ixes
Supp
ort
Spri
nt
relea
se
Eval
uatio
n
Learn
ed
Lesso
ns
The Fitness development and management work breakdown structure is shown below
(PROJECT MANAGEMENT INSTITUTE., 2017).
12
Fitness Development and Management Apps
Project
manager
Technical
document
ation
Conduct
Workshop
Developer
Team
Pre-
release
Phase
Release/
Production
Project
Closure
Review
App
Requirem
ent
To establish
High level
features
Tracking
user
activity
User
acceptan
ce testing
Warra
nty
Comp
letion
Delivering all
project
requirements
to the
development
team.
Identify the
product
technical
specification
To establish
High level
features
To establish
High level
features
Social
share
Push
notificatio
ns
Outstandi
ng design
Perform
ance
Testing
Traini
ng
Hotf
ixes
Supp
ort
Spri
nt
relea
se
Eval
uatio
n
Learn
ed
Lesso
ns
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
7. Organisation Break down structure
The Fitness development and management Organizational breakdown structure is shown
below.
13
Fitness Development and Management Apps
Project
manager
Technical
document
ation
Conduct
Workshop
Developer
Team
Pre-
release
Phase
Release/
Production
Project
Closure
Project
Manager
Android
Developer Tester
Proje
ct
Own
er
Proje
ct
owne
r
Technical
Writer
Business
analyst
Android
Developer
Designer
Quality
Assurer
Solution
Architect
Quality
Assurer
Busin
ess
analy
st
Proj
ect
man
ager
Busi
ness
anal
yst
Deve
loper
Proje
ct
Man
ager
Busin
ess
analy
st
The Fitness development and management Organizational breakdown structure is shown
below.
13
Fitness Development and Management Apps
Project
manager
Technical
document
ation
Conduct
Workshop
Developer
Team
Pre-
release
Phase
Release/
Production
Project
Closure
Project
Manager
Android
Developer Tester
Proje
ct
Own
er
Proje
ct
owne
r
Technical
Writer
Business
analyst
Android
Developer
Designer
Quality
Assurer
Solution
Architect
Quality
Assurer
Busin
ess
analy
st
Proj
ect
man
ager
Busi
ness
anal
yst
Deve
loper
Proje
ct
Man
ager
Busin
ess
analy
st
8. Responsibility Assignment Matrix
Responsible assignment Matrix for Resources are given below.
14
Responsible assignment Matrix for Resources are given below.
14
9. Task Details
Task Details are given below.
Task Name Duration Start Finish
Fitness Development and Management Apps 110 days Mon 04-09-
17 Fri 02-02-18
Project Manager 2 days Mon 04-09-
17 Tue 05-09-17
Review App Requirement 1 day Mon 04-09-
17 Mon 04-09-17
Delivering all project requirements to the
development team. 1 day Tue 05-09-
17 Tue 05-09-17
Technical documentation 2 days Wed 06-09-
17 Thu 07-09-17
Identify the product technical specification based on
client Requirements 2 days Wed 06-09-17 Thu 07-09-17
Conduct Workshop 14 days Fri 08-09-17 Wed 27-09-17
To establish High level features 5 days Fri 08-09-17 Thu 14-09-17
15
Task Details are given below.
Task Name Duration Start Finish
Fitness Development and Management Apps 110 days Mon 04-09-
17 Fri 02-02-18
Project Manager 2 days Mon 04-09-
17 Tue 05-09-17
Review App Requirement 1 day Mon 04-09-
17 Mon 04-09-17
Delivering all project requirements to the
development team. 1 day Tue 05-09-
17 Tue 05-09-17
Technical documentation 2 days Wed 06-09-
17 Thu 07-09-17
Identify the product technical specification based on
client Requirements 2 days Wed 06-09-17 Thu 07-09-17
Conduct Workshop 14 days Fri 08-09-17 Wed 27-09-17
To establish High level features 5 days Fri 08-09-17 Thu 14-09-17
15
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
To establish Process flows 4 days Fri 15-09-17 Wed 20-09-17
Priority Initial Release Plan 5 days Thu 21-09-
17 Wed 27-09-17
Developer Team 35 days Thu 28-09-
17 Wed 15-11-17
Tracking user activity 30 days Thu 28-09-
17 Wed 08-11-17
Body measurements/weight history 2 days Thu 28-09-
17 Fri 29-09-17
Number of steps/distance travelled 1 day Mon 02-10-
17 Mon 02-10-17
Calories burnt 1 day Tue 03-10-
17 Tue 03-10-17
Favourite types of activity/sports 1 day Wed 04-10-
17 Wed 04-10-17
Duration of exercise 4 days Thu 05-10-
17 Fri 03-11-17
Measuring Heartbeat rate 1 day Mon 06-11-
17 Mon 06-11-17
Movement tracking 2 days Tue 07-11-
17 Wed 08-11-17
Social share 1 day Thu 09-11-
17 Thu 09-11-17
Push notifications 1 day Thu 09-11-
17 Thu 09-11-17
Outstanding design 4 days Fri 10-11-17 Wed 15-11-17
both UI and UX Parts 1 day Fri 10-11-17 Fri 10-11-17
Product Backlog of story lines 3 days Mon 13-11-
17 Wed 15-11-17
Pre- release Phase 19 days Thu 16-11-
17 Tue 12-12-17
User acceptance testing 7 days Thu 16-11-
17 Fri 24-11-17
Performance Testing 5 days Mon 27-11-
17 Fri 01-12-17
Training 7 days Mon 04-12-
17 Tue 12-12-17
Release/Production 30 days Wed 13-12-
17 Tue 23-01-18
Warranty 7 days Wed 13-12-
17 Thu 21-12-17
Hotfixes 8 days Fri 22-12-17 Tue 02-01-18
Support 7 days Wed 03-01- Thu 11-01-18
16
Priority Initial Release Plan 5 days Thu 21-09-
17 Wed 27-09-17
Developer Team 35 days Thu 28-09-
17 Wed 15-11-17
Tracking user activity 30 days Thu 28-09-
17 Wed 08-11-17
Body measurements/weight history 2 days Thu 28-09-
17 Fri 29-09-17
Number of steps/distance travelled 1 day Mon 02-10-
17 Mon 02-10-17
Calories burnt 1 day Tue 03-10-
17 Tue 03-10-17
Favourite types of activity/sports 1 day Wed 04-10-
17 Wed 04-10-17
Duration of exercise 4 days Thu 05-10-
17 Fri 03-11-17
Measuring Heartbeat rate 1 day Mon 06-11-
17 Mon 06-11-17
Movement tracking 2 days Tue 07-11-
17 Wed 08-11-17
Social share 1 day Thu 09-11-
17 Thu 09-11-17
Push notifications 1 day Thu 09-11-
17 Thu 09-11-17
Outstanding design 4 days Fri 10-11-17 Wed 15-11-17
both UI and UX Parts 1 day Fri 10-11-17 Fri 10-11-17
Product Backlog of story lines 3 days Mon 13-11-
17 Wed 15-11-17
Pre- release Phase 19 days Thu 16-11-
17 Tue 12-12-17
User acceptance testing 7 days Thu 16-11-
17 Fri 24-11-17
Performance Testing 5 days Mon 27-11-
17 Fri 01-12-17
Training 7 days Mon 04-12-
17 Tue 12-12-17
Release/Production 30 days Wed 13-12-
17 Tue 23-01-18
Warranty 7 days Wed 13-12-
17 Thu 21-12-17
Hotfixes 8 days Fri 22-12-17 Tue 02-01-18
Support 7 days Wed 03-01- Thu 11-01-18
16
18
Sprint release 8 days Fri 12-01-18 Tue 23-01-18
Project Closure 8 days Wed 24-01-
18 Fri 02-02-18
Completion of contractual and commercial
arrangements 2 days Wed 24-01-
18 Thu 25-01-18
Project evaluation 4 days Fri 26-01-18 Wed 31-01-18
Lessons Learned to be delivered and prepared to
client and company 2 days Thu 01-02-
18 Fri 02-02-18
Resource allocation for each tasks
Task Name Duration Start Finish Resource Names
Fitness Development and
Management Apps 110 days Mon 04-
09-17
Fri 02-02-
18
Project Manager 2 days Mon 04-
09-17
Tue 05-09-
17
Review App Requirement 1 day Mon 04-
09-17
Mon 04-
09-17 Project Manager
Delivering all project requirements to
the development team. 1 day Tue 05-
09-17
Tue 05-09-
17 Project Manager
Technical documentation 2 days Wed 06-
09-17
Thu 07-09-
17
Identify the product technical specification
based on client Requirements 2 days Wed 06-
09-17
Thu 07-09-
17 Technical Writer
Conduct Workshop 14 days Fri 08-
09-17
Wed 27-
09-17
To establish High level features 5 days Fri 08-
09-17
Thu 14-09-
17
Project Manager,
Android Developer
To establish Process flows 4 days Fri 15-
09-17
Wed 20-
09-17
Business Analyst,
Designer ,Quality
Assurer
Priority Initial Release Plan 5 days Thu 21-
09-17
Wed 27-
09-17
Android Developer,
Business Analyst,
Designer ,Technical
17
Sprint release 8 days Fri 12-01-18 Tue 23-01-18
Project Closure 8 days Wed 24-01-
18 Fri 02-02-18
Completion of contractual and commercial
arrangements 2 days Wed 24-01-
18 Thu 25-01-18
Project evaluation 4 days Fri 26-01-18 Wed 31-01-18
Lessons Learned to be delivered and prepared to
client and company 2 days Thu 01-02-
18 Fri 02-02-18
Resource allocation for each tasks
Task Name Duration Start Finish Resource Names
Fitness Development and
Management Apps 110 days Mon 04-
09-17
Fri 02-02-
18
Project Manager 2 days Mon 04-
09-17
Tue 05-09-
17
Review App Requirement 1 day Mon 04-
09-17
Mon 04-
09-17 Project Manager
Delivering all project requirements to
the development team. 1 day Tue 05-
09-17
Tue 05-09-
17 Project Manager
Technical documentation 2 days Wed 06-
09-17
Thu 07-09-
17
Identify the product technical specification
based on client Requirements 2 days Wed 06-
09-17
Thu 07-09-
17 Technical Writer
Conduct Workshop 14 days Fri 08-
09-17
Wed 27-
09-17
To establish High level features 5 days Fri 08-
09-17
Thu 14-09-
17
Project Manager,
Android Developer
To establish Process flows 4 days Fri 15-
09-17
Wed 20-
09-17
Business Analyst,
Designer ,Quality
Assurer
Priority Initial Release Plan 5 days Thu 21-
09-17
Wed 27-
09-17
Android Developer,
Business Analyst,
Designer ,Technical
17
Writer
Developer Team 35 days Thu 28-
09-17
Wed 15-
11-17
Tracking user activity 30 days Thu 28-
09-17
Wed 08-
11-17
Body measurements/weight history 2 days Thu 28-
09-17
Fri 29-09-
17
Designer ,Quality
Assurer, Solution
Architect
Number of steps/distance travelled 1 day Mon 02-
10-17
Mon 02-
10-17
Designer ,Product
Owner
Calories burnt 1 day Tue 03-
10-17
Tue 03-10-
17
Android Developer,
Quality Assurer
Favourite types of activity/sports 1 day Wed 04-
10-17
Wed 04-
10-17
Android Developer,
Quality Assurer,
Solution Architect
Duration of exercise 4 days Thu 05-
10-17
Fri 03-11-
17
Business Analyst,
Solution Architect
Measuring Heartbeat rate 1 day Mon 06-
11-17
Mon 06-
11-17
Android Developer,
Solution Architect
Movement tracking 2 days Tue 07-
11-17
Wed 08-
11-17 Quality Assurer
Social share 1 day Thu 09-
11-17
Thu 09-11-
17
Push notifications 1 day Thu 09-
11-17
Thu 09-11-
17
Quality Assurer,
Solution Architect
Outstanding design 4 days Fri 10-
11-17
Wed 15-
11-17
both UI and UX Parts 1 day Fri 10-
11-17
Fri 10-11-
17
Android Developer,
Designer
Product Backlog of story lines 3 days Mon 13-
11-17
Wed 15-
11-17
Product Owner, Quality
Assurer, Solution
Architect
18
Developer Team 35 days Thu 28-
09-17
Wed 15-
11-17
Tracking user activity 30 days Thu 28-
09-17
Wed 08-
11-17
Body measurements/weight history 2 days Thu 28-
09-17
Fri 29-09-
17
Designer ,Quality
Assurer, Solution
Architect
Number of steps/distance travelled 1 day Mon 02-
10-17
Mon 02-
10-17
Designer ,Product
Owner
Calories burnt 1 day Tue 03-
10-17
Tue 03-10-
17
Android Developer,
Quality Assurer
Favourite types of activity/sports 1 day Wed 04-
10-17
Wed 04-
10-17
Android Developer,
Quality Assurer,
Solution Architect
Duration of exercise 4 days Thu 05-
10-17
Fri 03-11-
17
Business Analyst,
Solution Architect
Measuring Heartbeat rate 1 day Mon 06-
11-17
Mon 06-
11-17
Android Developer,
Solution Architect
Movement tracking 2 days Tue 07-
11-17
Wed 08-
11-17 Quality Assurer
Social share 1 day Thu 09-
11-17
Thu 09-11-
17
Push notifications 1 day Thu 09-
11-17
Thu 09-11-
17
Quality Assurer,
Solution Architect
Outstanding design 4 days Fri 10-
11-17
Wed 15-
11-17
both UI and UX Parts 1 day Fri 10-
11-17
Fri 10-11-
17
Android Developer,
Designer
Product Backlog of story lines 3 days Mon 13-
11-17
Wed 15-
11-17
Product Owner, Quality
Assurer, Solution
Architect
18
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Pre- release Phase 19 days Thu 16-
11-17
Tue 12-12-
17
User acceptance testing 7 days Thu 16-
11-17
Fri 24-11-
17
Big Fixer,
Designer ,Tester
Performance Testing 5 days Mon 27-
11-17
Fri 01-12-
17
Quality Assurer,
Solution Architect,
Tester
Training 7 days Mon 04-
12-17
Tue 12-12-
17
Business Analyst,
Product Owner, Project
Manager
Release/Production 30 days Wed 13-
12-17
Tue 23-01-
18
Warranty 7 days Wed 13-
12-17
Thu 21-12-
17
Business Analyst,
Product Owner
Hotfixes 8 days Fri 22-
12-17
Tue 02-01-
18
Big Fixer, Business
Analyst, Product Owner
Support 7 days Wed 03-
01-18
Thu 11-01-
18
Android Developer,
Product Owner, Project
Manager, Solution
Architect
Sprint release 8 days Fri 12-
01-18
Tue 23-01-
18
Business Analyst,
Product Owner, Project
Manager
Project Closure 8 days Wed 24-
01-18
Fri 02-02-
18
Completion of contractual and
commercial arrangements 2 days Wed 24-
01-18
Thu 25-01-
18
Project evaluation 4 days Fri 26-
01-18
Wed 31-
01-18
Product Owner, Project
Manager, Quality
Assurer
Lessons Learned to be delivered and
prepared to client and company
2 days Thu 01-
02-18
Fri 02-02-
18
Android Developer,
Business Analyst,
Designer ,Product
19
11-17
Tue 12-12-
17
User acceptance testing 7 days Thu 16-
11-17
Fri 24-11-
17
Big Fixer,
Designer ,Tester
Performance Testing 5 days Mon 27-
11-17
Fri 01-12-
17
Quality Assurer,
Solution Architect,
Tester
Training 7 days Mon 04-
12-17
Tue 12-12-
17
Business Analyst,
Product Owner, Project
Manager
Release/Production 30 days Wed 13-
12-17
Tue 23-01-
18
Warranty 7 days Wed 13-
12-17
Thu 21-12-
17
Business Analyst,
Product Owner
Hotfixes 8 days Fri 22-
12-17
Tue 02-01-
18
Big Fixer, Business
Analyst, Product Owner
Support 7 days Wed 03-
01-18
Thu 11-01-
18
Android Developer,
Product Owner, Project
Manager, Solution
Architect
Sprint release 8 days Fri 12-
01-18
Tue 23-01-
18
Business Analyst,
Product Owner, Project
Manager
Project Closure 8 days Wed 24-
01-18
Fri 02-02-
18
Completion of contractual and
commercial arrangements 2 days Wed 24-
01-18
Thu 25-01-
18
Project evaluation 4 days Fri 26-
01-18
Wed 31-
01-18
Product Owner, Project
Manager, Quality
Assurer
Lessons Learned to be delivered and
prepared to client and company
2 days Thu 01-
02-18
Fri 02-02-
18
Android Developer,
Business Analyst,
Designer ,Product
19
Owner, Project Manager
10. Project schedule Manpower
In fitness development and management application, the total project schedule man power
is 1000% because the fitness application project contains the 10 employees.
Resource Name Max. Units
Technical Writer 100%
Designer 100%
Android Developer 100%
Project Manager 100%
Tester 100%
Big Fixer 100%
Product Owner 100%
Quality Assurer 100%
Solution Architect 100%
Business Analyst 100%
11. Cost estimation
The overall fitness application cost is $66.640. 00. The cost estimation is given below
("How to create an activity tracking app? Apps for fitness integrated with wearables.",
2017).
20
10. Project schedule Manpower
In fitness development and management application, the total project schedule man power
is 1000% because the fitness application project contains the 10 employees.
Resource Name Max. Units
Technical Writer 100%
Designer 100%
Android Developer 100%
Project Manager 100%
Tester 100%
Big Fixer 100%
Product Owner 100%
Quality Assurer 100%
Solution Architect 100%
Business Analyst 100%
11. Cost estimation
The overall fitness application cost is $66.640. 00. The cost estimation is given below
("How to create an activity tracking app? Apps for fitness integrated with wearables.",
2017).
20
28-
08-
17
11-
09-
17
25-
09-
17
09-
10-
17
23-
10-
17
06-
11-
17
20-
11-
17
04-
12-
17
18-
12-
17
01-
01-
18
15-
01-
18
29-
01-
18
0%
1%
1%
$ 0.00
$ 20,000.00
$ 40,000.00
$ 60,000.00
Cost Estimation
Cumulative Percent Complete Cumulative Cost
% Complete
Cumulative Cost
21
08-
17
11-
09-
17
25-
09-
17
09-
10-
17
23-
10-
17
06-
11-
17
20-
11-
17
04-
12-
17
18-
12-
17
01-
01-
18
15-
01-
18
29-
01-
18
0%
1%
1%
$ 0.00
$ 20,000.00
$ 40,000.00
$ 60,000.00
Cost Estimation
Cumulative Percent Complete Cumulative Cost
% Complete
Cumulative Cost
21
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Cost Status
Fitness Development and Management Apps
$ 0.00
$ 10,000.00
$ 20,000.00
$ 30,000.00
$ 40,000.00
$ 50,000.00
$ 60,000.00
$ 70,000.00
C ost Status
Remaining Cost Actual Cost Baseline Cost
Cost variance for resources
Technical Writer
Designer
Android Developer
Project Manager
Tester
Big Fixer
Product Owner
Quality Assurer
Solution Architect
Business Analyst
$ 1,400.00
$ 5,280.00
$ 6,440.00
$ 14,000.00
$ 2,400.00
$ 3,000.00
$ 7,520.00
$ 6,440.00
$ 5,760.00
$ 14,400.00
Cost Variance
Name Cost Baseline Cost Cost Variance
Technical Writer $ 1,400.00 $ 0.00 $ 1,400.00
Designer $ 5,280.00 $ 0.00 $ 5,280.00
Android Developer $ 6,440.00 $ 0.00 $ 6,440.00
Project Manager $ 14,000.00 $ 0.00 $ 14,000.00
Tester $ 2,400.00 $ 0.00 $ 2,400.00
Big Fixer $ 3,000.00 $ 0.00 $ 3,000.00
22
Fitness Development and Management Apps
$ 0.00
$ 10,000.00
$ 20,000.00
$ 30,000.00
$ 40,000.00
$ 50,000.00
$ 60,000.00
$ 70,000.00
C ost Status
Remaining Cost Actual Cost Baseline Cost
Cost variance for resources
Technical Writer
Designer
Android Developer
Project Manager
Tester
Big Fixer
Product Owner
Quality Assurer
Solution Architect
Business Analyst
$ 1,400.00
$ 5,280.00
$ 6,440.00
$ 14,000.00
$ 2,400.00
$ 3,000.00
$ 7,520.00
$ 6,440.00
$ 5,760.00
$ 14,400.00
Cost Variance
Name Cost Baseline Cost Cost Variance
Technical Writer $ 1,400.00 $ 0.00 $ 1,400.00
Designer $ 5,280.00 $ 0.00 $ 5,280.00
Android Developer $ 6,440.00 $ 0.00 $ 6,440.00
Project Manager $ 14,000.00 $ 0.00 $ 14,000.00
Tester $ 2,400.00 $ 0.00 $ 2,400.00
Big Fixer $ 3,000.00 $ 0.00 $ 3,000.00
22
Product Owner $ 7,520.00 $ 0.00 $ 7,520.00
Quality Assurer $ 6,440.00 $ 0.00 $ 6,440.00
Solution Architect $ 5,760.00 $ 0.00 $ 5,760.00
Business Analyst $ 14,400.00 $ 0.00 $ 14,400.00
MS Project file is attached here.
12. Risk Analysis
The Risk register and analysis is used to update the impact and probability of matrix
results. It perform the quality check on the matrix results. It easily categorize the risks to
handle the project. It also perform the urgency assessment to find which risk is requires to
immediate attention. But there is no high level risks. It has the low privacy risks. To
mitigate the privacy risks to use wearable and their corresponding applications.
13. Conclusion
This paper concludes with analysis of the user adoption of mobile application for fitness
and weight management based on literature research and experience with fitness and weight
management app. Health relevant apps on mobile devices are easy to use often and appeal to
lot of user. It permits to take measurement whenever they required. The apps provide a lot of
functionality for wither free or few cost. These apps are particular suitable for the people
those who want to be fit and manage the weight. Through this app we can track daily energy
intake through recording food consumed then concentrated on meal type and type of snacks
from database of kind of meals and energy content provided in the application. Additionally,
tracking energy content expanded through daily activities. By giving personal details such as
height, weight, age, gender, the app is use the daily energy intake and expenditure to weight
gain or loss and to use adaptive algorithm to improve predictive accuracy of weight loss or
gain from the input.
23
Quality Assurer $ 6,440.00 $ 0.00 $ 6,440.00
Solution Architect $ 5,760.00 $ 0.00 $ 5,760.00
Business Analyst $ 14,400.00 $ 0.00 $ 14,400.00
MS Project file is attached here.
12. Risk Analysis
The Risk register and analysis is used to update the impact and probability of matrix
results. It perform the quality check on the matrix results. It easily categorize the risks to
handle the project. It also perform the urgency assessment to find which risk is requires to
immediate attention. But there is no high level risks. It has the low privacy risks. To
mitigate the privacy risks to use wearable and their corresponding applications.
13. Conclusion
This paper concludes with analysis of the user adoption of mobile application for fitness
and weight management based on literature research and experience with fitness and weight
management app. Health relevant apps on mobile devices are easy to use often and appeal to
lot of user. It permits to take measurement whenever they required. The apps provide a lot of
functionality for wither free or few cost. These apps are particular suitable for the people
those who want to be fit and manage the weight. Through this app we can track daily energy
intake through recording food consumed then concentrated on meal type and type of snacks
from database of kind of meals and energy content provided in the application. Additionally,
tracking energy content expanded through daily activities. By giving personal details such as
height, weight, age, gender, the app is use the daily energy intake and expenditure to weight
gain or loss and to use adaptive algorithm to improve predictive accuracy of weight loss or
gain from the input.
23
References
Cooke, H., Tate, K., & Cooke, H. (2011). Project management. New York: McGraw-Hill.
Heerkens, G. (2015). Project management. [Place of publication not identified]: Mcgraw-Hill
Education.
Horine, G. Project management.
How to create an activity tracking app? Apps for fitness integrated with wearables..
(2017). Eastern Peak. Retrieved 4 September 2017, from
https://easternpeak.com/blog/apps-for-fitness-integrated-with-wearables-how-to-create-
an-activity-tracking-app/
How To Develop The Best Fitness Application?. (2017). The App Solutions. Retrieved 4
September 2017, from https://theappsolutions.com/blog/development/fit-app-
development/
Kerzner, H. Project management.
PROJECT MANAGEMENT INSTITUTE. (2017). GUIDE TO THE PROJECT
MANAGEMENT BODY OF KNOWLEDGE. [S.l.]: PROJECT MANAGEMENT INST.
24
Cooke, H., Tate, K., & Cooke, H. (2011). Project management. New York: McGraw-Hill.
Heerkens, G. (2015). Project management. [Place of publication not identified]: Mcgraw-Hill
Education.
Horine, G. Project management.
How to create an activity tracking app? Apps for fitness integrated with wearables..
(2017). Eastern Peak. Retrieved 4 September 2017, from
https://easternpeak.com/blog/apps-for-fitness-integrated-with-wearables-how-to-create-
an-activity-tracking-app/
How To Develop The Best Fitness Application?. (2017). The App Solutions. Retrieved 4
September 2017, from https://theappsolutions.com/blog/development/fit-app-
development/
Kerzner, H. Project management.
PROJECT MANAGEMENT INSTITUTE. (2017). GUIDE TO THE PROJECT
MANAGEMENT BODY OF KNOWLEDGE. [S.l.]: PROJECT MANAGEMENT INST.
24
1 out of 25
Your All-in-One AI-Powered Toolkit for Academic Success.
 +13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024  |  Zucol Services PVT LTD  |  All rights reserved.