logo

Wall Framing Process

11 Pages2083 Words202 Views
   

Added on  2019-09-24

Wall Framing Process

   Added on 2019-09-24

ShareRelated Documents
Answer: 1Bulk excavation and fill Answer: 2 Jack’s Excavation Answer: 3 A.Resource Answer: 4 Labour, 1 and $10,200Answer: 5 Install sheet flooring.Answer: 6 Timber Specialist. Answer: 7 A.Resource. Answer: 8 1.Material 2.10633.$3.00 Case study: 3 Answer: 1B.Plot the actual cost on a graph.It was require to collect information about which month expense most. 1 | P a g e
Wall Framing Process_1
Answer: 2 Answer: April 3210May-2510June 290July 1600August 100September1030 Answer:3 B: March and May, these month were underestimated. That could be major impact on the builder’s capacity. Answer: 4 A.No you cannot see this directly from the graph. In order to estimate overall project was underestimated or overestimated, it was require to calculate accumulated difference and plotted on a graph. May-1830June-1540July 60August 160September1190Answer: 5 Overestimated. The total project costs were overestimated. The builder was precise or accurate for their work because difference found only $1190. Task-1 Project schedule: 2 | P a g e
Wall Framing Process_2
Project Schedule Project Schedule with critical path3 | P a g e
Wall Framing Process_3
Project scheduleLabour schedule: Labour schedule with shift and Labour Costs Period of start time EmployeesMonTueWed ThuFriSat SunPaid Total Name 08-01-201809-01-201810-01-201811-01-201812-01-201813-01-201814-01-2018Hour Labour cost Employee1Day shift Day shiftNight shift Day shift Night shift 40$620Employee2Leave Shift BShit A Shift C 20$310Employee3Total Paid Hour Daily Labour Cost Note: Shift A,B,C are 8hours Day shift : 8:30 to 5:30 PM4 | P a g e
Wall Framing Process_4

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Construction Project Management: Labor, Material, and Process Ordering
|26
|5389
|170

Construction Project Management Case Studies and Processes
|26
|5431
|244