This report presents the unconstrained schedule for Apex Area Medical Centre Project (AAMC) including precedence table, project schedule description, network diagram, project critical path diagram, project Gantt chart, earned value analysis, cash flow in terms of resources, cash flow for first 25%, and cash flow for last 25%.

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
Running head: PROJECT DRAFT REPORT
Project Draft Report
Apex Area Medical Centre Project (AAMC)
Name of the Student:
Student ID:
Name of the University:
Author’s note:

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
1PROJECT DRAFT REPORT
Table of Contents
Introduction......................................................................................................................................2
1. Unconstrained Schedule..............................................................................................................2
1.1 Precedence Table...................................................................................................................2
1.2 Project Schedule Description.................................................................................................7
1.3 Network Diagram..................................................................................................................9
1.4 Project Critical Path Diagram..............................................................................................10
1.5 Project Gantt Chart..............................................................................................................11
1.6 Earned value analysis..........................................................................................................12
1.8 Cash Flow in terms of resources..........................................................................................13
1.9 Cash Flow for First 25%......................................................................................................15
1.10 Cash flow for Last 25%.....................................................................................................16
Conclusion.....................................................................................................................................21
Bibliography..................................................................................................................................22
Document Page
2PROJECT DRAFT REPORT
Introduction
The following assignment has been made for the development of the improved analysis
and project management for the utilization of the effective management of the work and aligning
the functional management of activities. The following report would involve the completeness of
the work and cohesive management of activities.
1. Unconstrained Schedule
1.1 Precedence Table
Task Name Predecessors Duratio
n Start Successors Finish
Identify mission and
Objectives, Create Project
Charter
7 days Mon
10/8/18 4, 5 Tue
10/16/18
Create Business Plan and
Issue 3 5 days Wed
10/17/18 7 Tue
10/23/18
Create Project Initiation
Document and Issue 3 12 days Wed
10/24/18
Fri
11/9/18
Soil Investigation 4 3 days Wed
10/24/18 8, 9 Fri
10/26/18
Architectural 7 60 days Mon
10/29/18 Fri 2/1/19
Structural 7 15 days Mon
10/29/18 10 Fri
11/16/18
Mechanical 9 10 days Mon
11/19/18 11 Fri
11/30/18
Electrical 10 15 days Mon
12/3/18 14, 17 Fri
12/21/18
Survey 11 5 days Mon
12/24/18 15 Fri
12/28/18
Excavation 14 10 days Mon Fri
Document Page
3PROJECT DRAFT REPORT
12/31/18 1/11/19
Grading 11 5 days Mon
12/24/18 18, 19 Fri
12/28/18
Water Control 17 29 days Mon
12/31/18 20 Thu
2/7/19
Erosion control 17 29 days Mon
12/31/18 20 Thu
2/7/19
Underground utilities 18, 19 10 days Fri 2/8/19 23 Thu
2/21/19
Piles (Precast) 20 14 days Fri
2/22/19 25, 26, 49 Wed
3/13/19
Columns (Basement -
Floor 2) 23 28 days Thu
3/14/19 32 Tue
4/30/19
Columns (Floor 3 - 4) 23 10 days Thu
3/14/19 28 Wed
3/27/19
Columns (Floor 5 - 6) 28 20 days Thu
4/11/19 30 Tue
5/14/19
Columns (Floor 7 - 9) 26 10 days Thu
3/28/19 27 Wed
4/10/19
Slab -Beams
(Basement - Floor 2) 27 12 days Wed
5/15/19 31 Thu
5/30/19
Slab-Beams (Floor 3-
4) 30 8 days Fri
5/31/19 32 Tue
6/11/19
Slab-Beams (Floor 5 -
6) 25, 31 8 days Wed
6/12/19 33 Fri
6/21/19
Slab-Beams (Floor 7 -
9) 32 8 days Mon
6/24/19 35 Wed
7/3/19
Roofing Trusses 33 5 days Thu
7/4/19 36 Wed
7/10/19
Roofing Cover 35 3 days Wed
8/28/19 72, 73, 74 Fri
8/30/19
Columns (Basement -
Floor 2) 21 5 days Mon
9/2/19 40 Fri 9/6/19
Columns Floor( 3 - 4) 39 5 days Mon 41, 44, 45 Fri

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
4PROJECT DRAFT REPORT
9/9/19 9/13/19
Columns Floor( 5 - 6) 40 5 days Mon
9/16/19 42 Fri
9/20/19
Columns Floor( 7 - 9) 41 5 days Mon
9/23/19 46 Fri
9/27/19
Slab-Beams (Basement -
Floor 2) 40 4 days Mon
9/16/19
Thu
9/19/19
Slab-Beams Floor( 3 - 4) 40 4 days Mon
9/16/19
Thu
9/19/19
Slab-Beams Floor( 5 - 6) 42 4 days Mon
9/30/19 47 Thu
10/3/19
Slab-Beams Floor( 7 - 8) 46 4 days Fri
10/4/19
Wed
10/9/19
Stairway (Basement -
Floor 2) 23 2 days Thu
3/14/19 50, 52, 56 Fri
3/15/19
Stairway Floor(3 - 4) 49 2 days Mon
3/18/19 51 Tue
3/19/19
Stairway Floor( 5 -6) 50 4 days Wed
3/20/19
Mon
3/25/19
Stairway Floor( 7 - 8) 49 4 days Mon
3/18/19 53 Thu
3/21/19
Patios 52 1 day Fri
3/22/19
Fri
3/22/19
Internal wall 49 30 days Mon
3/18/19 57, 58 Fri
4/26/19
External wall 56 45 days Mon
4/29/19 69 Fri
6/28/19
Screeding 56 90 days Mon
4/29/19 60 Fri
8/30/19
Partitions 57 55 days Mon
7/1/19 60 Fri
9/13/19
Dry wall 58, 69 45 days Mon
9/16/19 62, 63, 65, 66 Fri
11/15/19
Interior doors 60 20 days Mon 64 Fri
Document Page
5PROJECT DRAFT REPORT
11/18/19 12/13/19
Windows 60 30 days Mon
11/18/19
Fri
12/27/19
Security doors 62 20 days Mon
12/16/19 67 Fri
1/10/20
Tiles 60 90 days Mon
11/18/19 84 Fri
3/20/20
Glazing works 60 40 days Mon
11/18/19 67 Fri
1/10/20
Decoration 66, 64 30 days Mon
1/13/20 68 Fri
2/21/20
Carpeting 67 50 days Mon
2/24/20 85 Fri 5/1/20
Plumbing systems (Main
Line) 36 15 days Mon
9/2/19 75 Fri
9/20/19
Plumbing systems
(Floor. 1-2) 36 10 days Mon
10/21/19 74 Fri
11/1/19
Plumbing systems
(Floor. 3-4) 36, 73 10 days Mon
11/4/19 81 Fri
11/15/19
Plumbing systems
(Floor. 4-6) 72 10 days Mon
9/23/19 76 Fri
10/4/19
Plumbing systems
(Floor. 7-9) 75 10 days Mon
10/7/19 78 Fri
10/18/19
Electrical Fixtures
(Distribution) 76 5 days Mon
10/21/19 79 Fri
10/25/19
Electrical Fixtures (Floor.
1-2) 78 10 days Mon
10/28/19 80 Fri
11/8/19
Electrical Fixtures (Floor.
3-4) 79 10 days Mon
11/11/19 81 Fri
11/22/19
Electrical Fixtures (Floor.
5-6) 74, 80 10 days Mon
11/25/19 82 Fri
12/6/19
Electrical Fixtures (Floor.
7-9) 81 10 days Mon
12/9/19 84 Fri
12/20/19
Systems Controls 65, 82 10 days Mon 85 Fri 4/3/20
Document Page
6PROJECT DRAFT REPORT
3/23/20
Fire alarms 84, 68 10 days Mon
5/4/20 87, 91 Fri
5/15/20
Mechanical Fixtures
(Elevators etc) 85 15 days Mon
5/18/20 88 Fri 6/5/20
Mechanical Fixtures (Floor
1- 4) 87 30 days Mon
6/8/20 89 Fri
7/17/20
Mechanical Fixtures (Floor
5- 9) 88 30 days Mon
7/20/20
Fri
8/28/20
Access roads 85 14 days Mon
5/18/20 92, 93 Thu
6/4/20
Signages 91 5 days Fri 6/5/20 96 Thu
6/11/20
Parking lot 91 14 days Fri 6/5/20 96 Wed
6/24/20
Testing 1 92, 93 2 days Thu
6/25/20
97, 98, 99, 100,
101, 102, 103, 104,
105
Fri
6/26/20
Testing 2 96 2 days Mon
6/29/20 107 Tue
6/30/20
Testing 3 96 2 days Wed
7/1/20 108 Thu
7/2/20
Testing 4 96 2 days Fri 7/3/20 109 Mon
7/6/20
Testing 5 96 2 days Tue
7/7/20
Wed
7/8/20
Testing 6 96 2 days Thu
7/9/20
Fri
7/10/20
Testing 7 96 2 days Mon
7/13/20
Tue
7/14/20
Testing 8 96 2 days Wed
7/15/20
Thu
7/16/20
Testing 9 96 2 days Fri
7/17/20
Mon
7/20/20

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7PROJECT DRAFT REPORT
Testing 10 96 2 days Tue
7/21/20
Wed
7/22/20
Inspections 1 97 1 day Wed
7/1/20 110 Wed
7/1/20
Inspections 2 98 1 day Fri 7/3/20 111 Fri 7/3/20
Inspections 3 99 1 day Tue
7/7/20 112 Tue
7/7/20
Inspections 4 107 1 day Thu
7/2/20 113 Thu
7/2/20
Inspections 5 108 1 day Mon
7/6/20 114 Mon
7/6/20
Inspections 6 109 1 day Wed
7/8/20 115 Wed
7/8/20
Inspections 7 110 1 day Fri 7/3/20 116 Fri 7/3/20
Inspections 8 111 1 day Tue
7/7/20 116 Tue
7/7/20
Inspections 9 112 1 day Thu
7/9/20 116 Thu
7/9/20
Inspections 10 113, 114,
115 1 day Fri
7/10/20
Fri
7/10/20
1.2 Project Schedule Description
The project had been considered for the constructing the flat complex and the utilization
of the construction project management principles for the alignment of the effective and
improved management process. The project has been divided into phases of planning, basement
and floor works, concrete works, electrical works, quality assessment, and inspections. The
construction works would be required for making sure that works can be integrated with the
alignment of the successful and effective management of construction works. The duration of the
projects include the following phases,
Document Page
8PROJECT DRAFT REPORT
Planning: the activities included in this phase are identify mission and objectives, create
project charter, create business plan and issue, and create project initiation document and issue.
Design: the design phase would include the activities of the soil investigation,
architectural, structural, mechanical, and electrical.
Basement and Floors 1 – 9: The work required in basement and flooring include
earthworks, survey, excavation, ground works, grading, water control, erosion control,
underground utilities, structures, reinforcements, piles (precast), columns, columns (basement -
floor 2), columns (floor 3 - 4), columns (floor 5 - 6), columns (floor 7 - 9), slab-beams, slab -
beams (basement - floor 2), slab-beams (floor 3- 4), slab-beams (floor 5 - 6), slab-beams (floor 7
- 9), roofing, roofing trusses, roofing cover, concrete,
Columns: the columns of the flooring would be done by involving the following sub
projects columns (basement - floor 2), columns floor (3 - 4), columns floor (5 - 6), columns floor
(7 - 9).
Slab-Beams: the slam beams would include the slab-beams (basement - floor 2), slab-
beams floor (3 - 4), slab-beams floor (5 - 6), slab-beams floor (7 - 8).
Stairway: Stairway construction would be sub sectioned into stairway (basement - floor
2), stairway floor (3 - 4), stairway floor (5 -6), and stairway floor (7 - 8).
Other works: some other construction works include patios, block wall-masonry, block
wall, internal wall, external wall, screeding, interior –finishes, partitions, dry wall, insulation,
interior doors, windows, security doors, tiles, glazing works, decoration, carpeting, mep systems
Document Page
9PROJECT DRAFT REPORT
Plumbing: the plumbing works include plumbing systems (main line), plumbing systems
(floor. 1-2), plumbing systems (floor. 3-4), plumbing systems (floor. 4-6), plumbing systems
(floor. 7-9).
Electrical: the electrical works include electrical fixtures (distribution), electrical fixtures
(floor. 1-2), electrical fixtures (floor. 3-4), electrical fixtures (floor. 5-6), electrical fixtures
(floor. 7-9), sprinkler, systems controls, fire alarms, mechanical systems, mechanical fixtures
(elevators etc), mechanical fixtures (floor 1- 4), mechanical fixtures (floor 5- 9).
1.3 Network Diagram
7 8
10 14 15
18 20 23 25
26
28 30 31
32 35
39 40 41
44
45
46
49 50 51
52
56 60 62
63
64
65
66
79
85 87
91 92
98
99
100
101
102
103
104
105
107
108
109
110
111
112
113
114
115
3 4
19
5
69
53
57
58
6867
27
74
78
42 47
119
73
17 3633 72 7675
96
84
116
93
97
82 81 80
89
88

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
10PROJECT DRAFT REPORT
1.4 Project Critical Path Diagram
ID Task
Mode
WBS Task Name
3 1.1.1 1.1.1 Identify mission and
Objectives, Create Project
Charter
4 1.1.2 1.1.2 Create Business Plan
and Issue
7 1.1 1.2.1 Soil Investigation
9 1.2.3 1.2.3 Structural
10 1.2.4 1.2.4 Mechanical
11 1.2.5 1.2.5 Electrical
17 2.1.3.1 2.1.3.1 Grading
18 2.1.3.2 2.1.3.2 Water Control
19 2.1.3.3 2.1.3.3 Erosion control
20 2.1.3.4 2.1.3.4 Underground utilities
23 2.2.1.1 2.2.1.1 Piles (Precast)
49 2.3.3.1 2.4.1 Stairway (Basement -
Floor 2)
56 2.4.1.1 2.6.1.1 Internal wall
57 2.4.1.2 2.6.1.2 External wall
69 2.5..5 2.7.4 Partitions
60 2.5.1 2.7.1 Dry wall
62 2.5.2.1 2.7.2.1 Interior doors
64 2.5.2.3 2.7.2.3 Security doors
66 2.5.2.5 2.7.2.5 Glazing works
67 2.5.2.6 2.7.2.6 Decoration
68 2.5.4 2.7.3 Carpeting
85 2.6.3.2 2.10.2 Fire alarms
87 2.6.4.1 2.11.1 Mechanical Fixtures
(Elevators etc)
88 2.6.4.2 2.11.2 Mechanical Fixtures
(Floor 1- 4)
89 2.6.4.3 2.11.3 Mechanical Fixtures
(Floor 5- 9)
Team IbMo
Team IbMo
Geotechnical Engineer[20%],Soil Lab technician[20%],Soil investigation Engineer[20%]
AutoCAD drafts man[50%],Estimator-Compiler,Snr Stuctural Engineer
Mechanical systems designer,AutoCAD drafts man[20%],Estimator-Compiler[20%]
Electrical systems designer,AutoCAD drafts man,Estimator-Compiler
Leveller,Helper[200%],Grader operator
Pump operator (certified),Pump Operator,Helper[200%]
Erosion control specialist,Sediment control specialist,Labourer[200%]
Utility line locator,Utility line assessor,Utility line technician
Auger cast superintendent,Concrete technicians[200%],PM Deep foundations,Concrete mixer technician[200%]
Concrete form setter[600%],Concrete batch maker[200%],Concrete mixer driver[200%],Concrete technicians[500%]
Curtain wall installer[300%],Carpenter[200%],Brick layer[200%],Brick leveller[200%]
Curtain wall installer[300%],Carpenter[200%],Brick layer[200%],Brick leveller[300%]
Partition wall installer[200%],Partition wall technician[200%],metal stud framer
Dry wall finisher[200%],Dry wall installer[200%],Carpenter Foreman
Door assembler[200%],Door installer[200%],Door finisher
Door assembler[200%],Door installer[200%],Door finisher
Glass/ Glazing installer[200%],painter glazing technician[200%],Project Manager Glazing
Painter[200%],Decorator,Paint technician
Carpet Installer[200%],Flooring Installation Helper[200%],Labourer[200%]
Fire alarm technician,Fire alarm supervisor,Fire alarm aassistance/ appprentice[200%]
HVAC Engineer,Commissioning engineer,HVAC technician,HVAC apprentice/assistant[200%],Hel
HVAC Engineer,Commissioning engineer,HVAC technician,HVAC apprentice/ assistant[200%]
HVAC Engineer,Commissioning engineer,HVAC technician,HVAC apprentice/assistant[2
Sep Nov Jan Mar May Jul Sep Nov Jan Mar May Jul Sep Nov Jan Mar May Jul Sep Nov Jan Mar
Qtr 3, 2018 Qtr 1, 2019 Qtr 3, 2019 Qtr 1, 2020 Qtr 3, 2020 Qtr 1, 2021 Qtr 3, 2021 Qtr 1, 2022
Document Page
11PROJECT DRAFT REPORT
1.5 Project Gantt Chart
ID Task
Mode
WBS Task Name
3 1.1.1 1.1.1 Identify mission and
Objectives, Create Project
Charter
4 1.1.2 1.1.2 Create Business Plan
and Issue
5 1.1.3 1.1.3 Create Project Initiation
Document and Issue
7 1.1 1.2.1 Soil Investigation
8 1.2 1.2.2 Architectural
9 1.2.3 1.2.3 Structural
10 1.2.4 1.2.4 Mechanical
11 1.2.5 1.2.5 Electrical
14 2.1.1 2.1.1 Survey
15 2.1.2 2.1.2 Excavation
17 2.1.3.1 2.1.3.1 Grading
18 2.1.3.2 2.1.3.2 Water Control
19 2.1.3.3 2.1.3.3 Erosion control
20 2.1.3.4 2.1.3.4 Underground utilities
23 2.2.1.1 2.2.1.1 Piles (Precast)
25 2.2.1.2.1 2.2.1.2.1 Columns
(Basement - Floor 2)
26 2.2.1.2.2 2.2.1.2.2 Columns (Floor 3 - 4)
27 2.2.1.2.3 2.2.1.2.3 Columns (Floor 5 - 6)
28 2.2.1.2.4 2.2.1.2.4 Columns (Floor 7 - 9)
30 2.2.1.3.1 2.2.1.3.1 Slab -Beams
(Basement - Floor 2)
31 2.2.1.3.2 2.2.1.3.2 Slab-Beams
(Floor 3- 4)
32 2.2.1.3.3 2.2.1.3.3 Slab-Beams
(Floor 5 - 6)
33 2.2.1.3.4 2.2.1.3.4 Slab-Beams
(Floor 7 - 9)
35 2.2.1.4.1 2.2.1.4.1 Roofing Trusses
36 2.2.1.4.2 2.2.1.4.2 Roofing Cover
39 2.3.1.1 2.3.1.1 Columns
(Basement - Floor 2)
40 2.3.1.2 2.3.1.2 Columns Floor( 3 - 4)
41 2.3.1.3 2.3.1.3 Columns Floor( 5 - 6)
42 2.3.1.4 2.3.1.4 Columns Floor( 7 - 9)
44 2.3.2.1 2.3.2.1 Slab-Beams
(Basement - Floor 2)
45 2.3.2.2 2.3.2.2 Slab-Beams Floor( 3 - 4)
46 2.3.2.3 2.3.2.3 Slab-Beams Floor( 5 - 6)
47 2.3.2.4 2.3.2.4 Slab-Beams Floor( 7 - 8)
49 2.3.3.1 2.4.1 Stairway (Basement -
Floor 2)
50 2.3.3.2 2.4.2 Stairway Floor(3 - 4)
51 2.3.3.3 2.4.3 Stairway Floor( 5 -6)
52 2.3.3.4 2.4.4 Stairway Floor( 7 - 8)
53 2.3.4 2.5 Patios
56 2.4.1.1 2.6.1.1 Internal wall
57 2.4.1.2 2.6.1.2 External wall
58 2.4.1.3 2.6.1.3 Screeding
69 2.5..5 2.7.4 Partitions
60 2.5.1 2.7.1 Dry wall
62 2.5.2.1 2.7.2.1 Interior doors
63 2.5.2.2 2.7.2.2 Windows
64 2.5.2.3 2.7.2.3 Security doors
65 2.5.2.4 2.7.2.4 Tiles
66 2.5.2.5 2.7.2.5 Glazing works
67 2.5.2.6 2.7.2.6 Decoration
68 2.5.4 2.7.3 Carpeting
72 2.6.1.1 2.8.1.1 Plumbing systems
(Main Line)
73 2.6.1.2 2.8.1.2 Plumbing systems
(Floor. 1-2)
74 2.6.1.3 2.8.1.3 Plumbing systems
(Floor. 3-4)
75 2.6.1.4 2.8.1.4 Plumbing systems
(Floor. 4-6)
76 2.6.1.5 2.8.1.5 Plumbing systems
(Floor. 7-9)
78 2.6.2.1 2.9.1 Electrical Fixtures
(Distribution)
79 2.6.2.2 2.9.2 Electrical Fixtures (Floor. 1-2)
80 2.6.2.3 2.9.3 Electrical Fixtures (Floor. 3-4)
81 2.6.2.4 2.9.4 Electrical Fixtures (Floor. 5-6)
82 2.6.2.5 2.9.5 Electrical Fixtures (Floor. 7-9)
84 2.6.3.1 2.10.1 Systems Controls
85 2.6.3.2 2.10.2 Fire alarms
87 2.6.4.1 2.11.1 Mechanical Fixtures
(Elevators etc)
88 2.6.4.2 2.11.2 Mechanical Fixtures
(Floor 1- 4)
89 2.6.4.3 2.11.3 Mechanical Fixtures
(Floor 5- 9)
91 3.1 3.1 Access roads
92 3.2 3.2 Signages
93 3.3 3.3 Parking lot
96 4.1 4.1.1 Testing 1
97 4.1 4.1.2 Testing 2
98 4.1 4.1.3 Testing 3
99 4.1 4.1.4 Testing 4
100 4.1 4.1.5 Testing 5
101 4.1 4.1.6 Testing 6
102 4.1 4.1.7 Testing 7
103 4.1 4.1.8 Testing 8
104 4.1 4.1.9 Testing 9
105 4.1 4.1.10 Testing 10
107 4.2 4.2.1 Inspections 1
108 4.2 4.2.2 Inspections 2
109 4.2 4.2.3 Inspections 3
110 4.2 4.2.4 Inspections 4
111 4.2 4.2.5 Inspections 5
112 4.2 4.2.6 Inspections 6
113 4.2 4.2.7 Inspections 7
114 4.2 4.2.8 Inspections 8
115 4.2 4.2.9 Inspections 9
116 4.2 4.2.10 Inspections 10
Team IbMo
Team IbMo
Team IbMo,Test Technicians[0%]
Geotechnical Engineer[20%],Soil Lab technician[20%],Soil investigation Engineer[20%]
Senior architect,AutoCAD drafts man[20%],Estimator-Compiler[20%]
AutoCAD drafts man[50%],Estimator-Compiler,Snr Stuctural Engineer
Mechanical systems designer,AutoCAD drafts man[20%],Estimator-Compiler[20%]
Electrical systems designer,AutoCAD drafts man,Estimator-Compiler
Geodectic Engineer,Surveyor assistant,Geodectic technician
Excavator operator,Dump operator,Helper
Leveller,Helper[200%],Grader operator
Pump operator (certified),Pump Operator,Helper[200%]
Erosion control specialist,Sediment control specialist,Labourer[200%]
Utility line locator,Utility line assessor,Utility line technician
Auger cast superintendent,Concrete technicians[200%],PM Deep foundations,Concrete mixer technician[200%]
Rebar Installer[400%],Rebar detailing co-ordinator[200%],Rebar Detailer[200%],Rebar Bender[400%]
Rebar Bender[400%],Rebar Detailer[200%],Rebar detailing co-ordinator[200%],Rebar Installer[400%]
Rebar Bender[400%],Rebar Detailer[200%],Rebar Installer[400%],Rebar detailing co-ordinator[200%]
Rebar Bender[400%],Rebar Detailer[200%],Rebar Installer[400%],Rebar detailing co-ordinator[200%]
Rebar Bender[400%],Rebar Installer[400%],Rebar detailing co-ordinator[200%],Rebar Detailer[200%]
Rebar Bender[400%],Rebar Installer[400%],Rebar detailing co-ordinator[200%],Rebar Detailer[200%]
Rebar Bender[400%],Rebar Installer[400%],Rebar detailing co-ordinator[200%],Rebar Detailer[200%]
Rebar Bender[400%],Rebar Detailer[200%],Rebar detailing co-ordinator[200%],Rebar Installer[400%]
Truss assembler[400%],Framer[200%],Helper[600%]
Roof helper[400%],Roofer[400%],Labourer[400%]
Concrete form setter[600%],Concrete batch maker[200%],Concrete mixer driver[200%],Labourer[500%]
Concrete batch maker[200%],Concrete form setter[600%],Concrete mixer driver[200%],Labourer[500%]
Concrete form setter[600%],Concrete batch maker[200%],Concrete mixer driver[200%],Labourer[500%]
Concrete batch maker[200%],Concrete form setter[600%],Concrete technicians[500%],Concrete mixer driv
Concrete batch maker,Concrete mixer driver,Concrete form setter,Concrete technicians
Concrete batch maker,Concrete form setter,Concrete technicians,Concrete mixer driver
Concrete batch maker,Concrete form setter,Concrete mixer driver,Concrete technicians
Concrete batch maker,Concrete mixer driver,Concrete technicians,Concrete form setter
Concrete form setter[600%],Concrete batch maker[200%],Concrete mixer driver[200%],Concrete technicians[500%]
Concrete batch maker[200%],Concrete form setter[600%],Concrete mixer driver[200%],Concrete technicians[500%]
Concrete batch maker[200%],Concrete mixer driver[200%],Concrete technicians[500%],Concrete form setter[600%]
Concrete batch maker[200%],Concrete mixer driver[200%],Concrete technicians[500%],Concrete form setter[600%]
Concrete batch maker[200%],Concrete form setter[500%],Concrete mixer driver[200%]
Curtain wall installer[300%],Carpenter[200%],Brick layer[200%],Brick leveller[200%]
Curtain wall installer[300%],Carpenter[200%],Brick layer[200%],Brick leveller[300%]
Screed operator[200%],Concrete finishers[200%],Labourers[300%]
Partition wall installer[200%],Partition wall technician[200%],metal stud framer
Dry wall finisher[200%],Dry wall installer[200%],Carpenter Foreman
Door assembler[200%],Door installer[200%],Door finisher
Window installer[200%],Assistant installer[200%],Installer helper
Door assembler[200%],Door installer[200%],Door finisher
Grout & Tile technician,Tile setter,Tile cutting machine operator
Glass/Glazing installer[200%],painter glazing technician[200%],Project Manager Glazing
Painter[200%],Decorator,Paint technician
Carpet Installer[200%],Flooring Installation Helper[200%],Labourer[200%]
Plumber,Journeyman plumber,Plumbing supervisor
Plumber,Journeyman plumber,Plumbing supervisor
Plumber,J ourneyman plumber,Plumbing supervisor
Plumber,Journeyman plumber,Plumbing supervisor
Plumber,Journeyman plumber,Plumbing supervisor
Licensed electrician,Commissioning specialist - electrical,Electrician,Assistant/Apprentice[200%]
Licensed electrician,Commissioning specialist - electrical,Electrician,Assistant/Apprentice[200%]
Licensed electrician,Commissioning specialist - electrical,Electrician,Assistant/Apprentice[200%]
Licensed electrician,Commissioning specialist - electrical,Electrician,Assistant/Apprentice[200%]
Licensed electrician,Commissioning specialist - electrical,Electrician,Assistant/Apprentice[200%]
Power systems controller,Sytems Engineer,Controls system specialist,Sprinkler fitter,F
Fire alarm technician,Fire alarm supervisor,Fire alarm aassistance/ appprentice[2
HVAC Engineer,Commissioning engineer,HVAC technician,HVAC apprentice/as
HVAC Engineer,Commissioning engineer,HVAC technician,HVAC apprentic
HVAC Engineer,Commissioning engineer,HVAC technician,HVAC appr
Highway construction crew,Crew members for asphalt paving,Asphalt roller
Signage installer,Signage designer
Highway construction crew,Asphalt roller,Crew members for asphalt paving
Test Technicians,Tester (Intern),Construction materials field testing technici
Test Technicians,Tester (Intern),Construction materials field testing technici
Test Technicians,Tester (Intern),Construction materials field testing technic
Test Technicians,Tester (Intern),Construction materials field testing technic
Test Technicians,Tester (Intern),Construction materials field testing technic
Test Technicians,Tester (Intern),Construction materials field testing techni
Test Technicians,Tester (Intern),Construction materials field testing techni
Test Technicians,Tester (Intern),Construction materials field testing techni
Test Technicians,Tester (Intern),Construction materials field testing techn
Test Technicians,Tester (Intern),Construction materials field testing techn
MeP Inspector[10%],Construction inspector[10%],Inspector (Buildings)[10%]
MeP Inspector[10%],Construction inspector[10%],Inspector (Buildings)[10%
MeP Inspector[10%],Construction inspector[10%],Inspector (Buildings)[10%
MeP Inspector[10%],Construction inspector[10%],Inspector (Buildings)[10%]
MeP Inspector[10%],Construction inspector[10%],Inspector (Buildings)[10%
MeP Inspector[10%],Construction inspector[10%],Inspector (Buildings)[10%
MeP Inspector[10%],Construction inspector[10%],Inspector (Buildings)[10%
MeP Inspector[10%],Construction inspector[10%],Inspector (Buildings)[10%
MeP Inspector[10%],Construction inspector[10%],Inspector (Buildings)[10%
MeP Inspector[10%],Construction inspector[10%],Inspector (Buildings)[10%
Sep Nov Jan Mar May Jul Sep Nov Jan Mar May Jul Sep Nov Jan Mar May Jul Sep Nov Jan Mar
Qtr 3, 2018 Qtr 1, 2019 Qtr 3, 2019 Qtr 1, 2020 Qtr 3, 2020 Qtr 1, 2021 Qtr 3, 2021 Qtr 1, 2022
Document Page
12PROJECT DRAFT REPORT
Comments on Schedule: The project schedule has been developed using the adaptive framework and the implication of the works intrigued for the management of the operations. The project was schedule with 495 working days
(summation of the duration of the critical activities). The work required for the completeness of the specific implication and management has been implied with the addition of the individual work packages. The summary tasks has been
reduced to an optimum cost aligning the work developed for the consideration of the smart project completion. The total of the critical tasks duration were consider for the calculation of the work and implication of the work duration.
1.6 Earned value analysis
Task Name Planned Value - PV
(BCWS) Earned Value - EV (BCWP) AC
(ACWP) SV CV EAC BAC VAC
Identify mission and Objectives, Create Project Charter $0.00 $0.00 $0.00 $0.00 $0.0
0 $0.00 $0.00 $0.00
Create Business Plan and Issue $0.00 $0.00 $0.00 $0.00 $0.0
0 $0.00 $0.00 $0.00
Create Project Initiation Document and Issue $0.00 $0.00 $0.00 $0.00 $0.0
0 $0.00 $0.00 $0.00
Soil Investigation $0.00 $0.00 $0.00 $0.00 $0.0
0 $17,496.00 $0.00 ($17,496.00)
Architectural $0.00 $0.00 $0.00 $0.00 $0.0
0 $25,416.00 $0.00 ($25,416.00)
Structural $0.00 $0.00 $0.00 $0.00 $0.0
0 $23,640.00 $0.00 ($23,640.00)
Mechanical $0.00 $0.00 $0.00 $0.00 $0.0
0 $18,072.00 $0.00 ($18,072.00)
Electrical $0.00 $0.00 $0.00 $0.00 $0.0
0 $23,640.00 $0.00 ($23,640.00)
Survey $0.00 $0.00 $0.00 $0.00 $0.0
0 $15,000.00 $0.00 ($15,000.00)
Excavation $0.00 $0.00 $0.00 $0.00 $0.0
0 $21,200.00 $0.00 ($21,200.00)
Grading $0.00 $0.00 $0.00 $0.00 $0.0
0 $24,360.00 $0.00 ($24,360.00)
Water Control $0.00 $0.00 $0.00 $0.00 $0.0
0 $4,200.00 $0.00 ($4,200.00)
Erosion control $0.00 $0.00 $0.00 $0.00 $0.0
0 $6,000.00 $0.00 ($6,000.00)
Underground utilities $0.00 $0.00 $0.00 $0.00 $0.0
0 $28,000.00 $0.00 ($28,000.00)
Piles (Precast) $0.00 $0.00 $0.00 $0.00 $0.0
0 $3,651,832.00 $0.00 ($3,651,832.00)
Columns (Basement - Floor 2) $0.00 $0.00 $0.00 $0.00 $0.0
0 $212,192.00 $0.00 ($212,192.00)
Columns (Floor 3 - 4) $0.00 $0.00 $0.00 $0.00 $0.0
0 $158,200.00 $0.00 ($158,200.00)
Columns (Floor 5 - 6) $0.00 $0.00 $0.00 $0.00 $0.0
0 $111,760.00 $0.00 ($111,760.00)
Columns (Floor 7 - 9) $0.00 $0.00 $0.00 $0.00 $0.0
0 $88,540.00 $0.00 ($88,540.00)
Slab -Beams (Basement - Floor 2) $0.00 $0.00 $0.00 $0.00 $0.0
0 $143,496.00 $0.00 ($143,496.00)
Slab-Beams (Floor 3- 4) $0.00 $0.00 $0.00 $0.00 $0.0
0 $105,734.00 $0.00 ($105,734.00)
Slab-Beams (Floor 5 - 6) $0.00 $0.00 $0.00 $0.00 $0.0
0 $75,524.00 $0.00 ($75,524.00)
Slab-Beams (Floor 7 - 9) $0.00 $0.00 $0.00 $0.00 $0.0
0 $60,419.00 $0.00 ($60,419.00)
Roofing Trusses $0.00 $0.00 $0.00 $0.00 $0.0
0 $32,000.00 $0.00 ($32,000.00)
Roofing Cover $0.00 $0.00 $0.00 $0.00 $0.0
0 $5,312.00 $0.00 ($5,312.00)
Columns (Basement - Floor 2) $0.00 $0.00 $0.00 $0.00 $0.0
0 $25,565.00 $0.00 ($25,565.00)
Columns Floor( 3 - 4) $0.00 $0.00 $0.00 $0.00 $0.0
0 $13,060.00 $0.00 ($13,060.00)
Columns Floor( 5 - 6) $0.00 $0.00 $0.00 $0.00 $0.0
0 $13,060.00 $0.00 ($13,060.00)
Columns Floor( 7 - 9) $0.00 $0.00 $0.00 $0.00 $0.0
0 $14,860.00 $0.00 ($14,860.00)
Slab-Beams (Basement - Floor 2) $0.00 $0.00 $0.00 $0.00 $0.0
0 $18,704.00 $0.00 ($18,704.00)
Slab-Beams Floor( 3 - 4) $0.00 $0.00 $0.00 $0.00 $0.0
0 $29,466.50 $0.00 ($29,466.50)
Slab-Beams Floor( 5 - 6) $0.00 $0.00 $0.00 $0.00 $0.0
0 $13,681.50 $0.00 ($13,681.50)

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
13PROJECT DRAFT REPORT
Slab-Beams Floor( 7 - 8) $0.00 $0.00 $0.00 $0.00 $0.0
0 $24,341.50 $0.00 ($24,341.50)
Stairway (Basement - Floor 2) $0.00 $0.00 $0.00 $0.00 $0.0
0 $11,991.50 $0.00 ($11,991.50)
Stairway Floor(3 - 4) $0.00 $0.00 $0.00 $0.00 $0.0
0 $5,021.50 $0.00 ($5,021.50)
Stairway Floor( 5 -6) $0.00 $0.00 $0.00 $0.00 $0.0
0 $11,991.50 $0.00 ($11,991.50)
Stairway Floor( 7 - 8) $0.00 $0.00 $0.00 $0.00 $0.0
0 $11,991.50 $0.00 ($11,991.50)
Patios $0.00 $0.00 $0.00 $0.00 $0.0
0 $3,101.00 $0.00 ($3,101.00)
Internal wall $0.00 $0.00 $0.00 $0.00 $0.0
0 $375,000.00 $0.00 ($375,000.00)
External wall $0.00 $0.00 $0.00 $0.00 $0.0
0 $425,000.00 $0.00 ($425,000.00)
Screeding $0.00 $0.00 $0.00 $0.00 $0.0
0 $287,280.00 $0.00 ($287,280.00)
Partitions $0.00 $0.00 $0.00 $0.00 $0.0
0 $77,223.00 $0.00 ($77,223.00)
Dry wall $0.00 $0.00 $0.00 $0.00 $0.0
0 $85,000.00 $0.00 ($85,000.00)
Interior doors $0.00 $0.00 $0.00 $0.00 $0.0
0 $12,460.00 $0.00 ($12,460.00)
Windows $0.00 $0.00 $0.00 $0.00 $0.0
0 $18,080.00 $0.00 ($18,080.00)
Security doors $0.00 $0.00 $0.00 $0.00 $0.0
0 $12,400.00 $0.00 ($12,400.00)
Tiles $0.00 $0.00 $0.00 $0.00 $0.0
0 $107,605.00 $0.00 ($107,605.00)
Glazing works $0.00 $0.00 $0.00 $0.00 $0.0
0 $32,720.00 $0.00 ($32,720.00)
Decoration $0.00 $0.00 $0.00 $0.00 $0.0
0 $280,000.00 $0.00 ($280,000.00)
Carpeting $0.00 $0.00 $0.00 $0.00 $0.0
0 $31,600.00 $0.00 ($31,600.00)
Plumbing systems (Main Line) $0.00 $0.00 $0.00 $0.00 $0.0
0 $9,760.00 $0.00 ($9,760.00)
Plumbing systems (Floor. 1-2) $0.00 $0.00 $0.00 $0.00 $0.0
0 $7,840.00 $0.00 ($7,840.00)
Plumbing systems (Floor. 3-4) $0.00 $0.00 $0.00 $0.00 $0.0
0 $7,840.00 $0.00 ($7,840.00)
Plumbing systems (Floor. 4-6) $0.00 $0.00 $0.00 $0.00 $0.0
0 $7,840.00 $0.00 ($7,840.00)
Plumbing systems (Floor. 7-9) $0.00 $0.00 $0.00 $0.00 $0.0
0 $7,840.00 $0.00 ($7,840.00)
Electrical Fixtures (Distribution) $0.00 $0.00 $0.00 $0.00 $0.0
0 $28,000.00 $0.00 ($28,000.00)
Electrical Fixtures (Floor. 1-2) $0.00 $0.00 $0.00 $0.00 $0.0
0 $18,840.00 $0.00 ($18,840.00)
Electrical Fixtures (Floor. 3-4) $0.00 $0.00 $0.00 $0.00 $0.0
0 $18,840.00 $0.00 ($18,840.00)
Electrical Fixtures (Floor. 5-6) $0.00 $0.00 $0.00 $0.00 $0.0
0 $18,840.00 $0.00 ($18,840.00)
Electrical Fixtures (Floor. 7-9) $0.00 $0.00 $0.00 $0.00 $0.0
0 $18,840.00 $0.00 ($18,840.00)
Systems Controls $0.00 $0.00 $0.00 $0.00 $0.0
0 $25,000.00 $0.00 ($25,000.00)
Fire alarms $0.00 $0.00 $0.00 $0.00 $0.0
0 $10,740.00 $0.00 ($10,740.00)
Mechanical Fixtures (Elevators etc) $0.00 $0.00 $0.00 $0.00 $0.0
0 $95,000.00 $0.00 ($95,000.00)
Mechanical Fixtures (Floor 1- 4) $0.00 $0.00 $0.00 $0.00 $0.0
0 $88,950.00 $0.00 ($88,950.00)
Mechanical Fixtures (Floor 5- 9) $0.00 $0.00 $0.00 $0.00 $0.0
0 $88,000.00 $0.00 ($88,000.00)
Access roads $0.00 $0.00 $0.00 $0.00 $0.0
0 $877,616.00 $0.00 ($877,616.00)
Signages $0.00 $0.00 $0.00 $0.00 $0.0
0 $2,000.00 $0.00 ($2,000.00)
Parking lot $0.00 $0.00 $0.00 $0.00 $0.0
0 $827,616.00 $0.00 ($827,616.00)
Document Page
14PROJECT DRAFT REPORT
Testing 1 $0.00 $0.00 $0.00 $0.00 $0.0
0 $5,592.00 $0.00 ($5,592.00)
Testing 2 $0.00 $0.00 $0.00 $0.00 $0.0
0 $5,592.00 $0.00 ($5,592.00)
Testing 3 $0.00 $0.00 $0.00 $0.00 $0.0
0 $5,592.00 $0.00 ($5,592.00)
Testing 4 $0.00 $0.00 $0.00 $0.00 $0.0
0 $5,592.00 $0.00 ($5,592.00)
Testing 5 $0.00 $0.00 $0.00 $0.00 $0.0
0 $5,592.00 $0.00 ($5,592.00)
Testing 6 $0.00 $0.00 $0.00 $0.00 $0.0
0 $5,592.00 $0.00 ($5,592.00)
Testing 7 $0.00 $0.00 $0.00 $0.00 $0.0
0 $5,592.00 $0.00 ($5,592.00)
Testing 8 $0.00 $0.00 $0.00 $0.00 $0.0
0 $5,592.00 $0.00 ($5,592.00)
Testing 9 $0.00 $0.00 $0.00 $0.00 $0.0
0 $5,592.00 $0.00 ($5,592.00)
Testing 10 $0.00 $0.00 $0.00 $0.00 $0.0
0 $5,592.00 $0.00 ($5,592.00)
Inspections 1 $0.00 $0.00 $0.00 $0.00 $0.0
0 $7,064.00 $0.00 ($7,064.00)
Inspections 2 $0.00 $0.00 $0.00 $0.00 $0.0
0 $7,064.00 $0.00 ($7,064.00)
Inspections 3 $0.00 $0.00 $0.00 $0.00 $0.0
0 $7,064.00 $0.00 ($7,064.00)
Inspections 4 $0.00 $0.00 $0.00 $0.00 $0.0
0 $7,064.00 $0.00 ($7,064.00)
Inspections 5 $0.00 $0.00 $0.00 $0.00 $0.0
0 $7,064.00 $0.00 ($7,064.00)
Inspections 6 $0.00 $0.00 $0.00 $0.00 $0.0
0 $7,064.00 $0.00 ($7,064.00)
Inspections 7 $0.00 $0.00 $0.00 $0.00 $0.0
0 $7,064.00 $0.00 ($7,064.00)
Inspections 8 $0.00 $0.00 $0.00 $0.00 $0.0
0 $7,064.00 $0.00 ($7,064.00)
Inspections 9 $0.00 $0.00 $0.00 $0.00 $0.0
0 $7,064.00 $0.00 ($7,064.00)
Inspections 10 $0.00 $0.00 $0.00 $0.00 $0.0
0 $7,064.00 $0.00 ($7,064.00)
1.7 Cash Flow in terms of time
October
2018 November
2018 December
2018 January
2019 February
2019 March
2019 April 2019 May 2019 June 2019 July 2019 August
2019 September
2019 October
2019 November
2019 December
2019 January
2020 February
2020 March
2020 April 2020 May 2020 June 2020 July 2020 August
2020
$0.00
$500,000.00
$1,000,000.00
$1,500,000.00
$2,000,000.00
$2,500,000.00
$3,000,000.00
Cost
1.8 Cash Flow in terms of resources
Document Page
15PROJECT DRAFT REPORT
Geotechnical Engineer Excavator operator Auger cast superintendent Concrete form setter Construction inspector Door installer Paint technician Assistant/Apprentice HVAC apprentice/assistant Labourere
$0.00
$50,000.00
$100,000.00
$150,000.00
$200,000.00
$250,000.00
$300,000.00
$350,000.00
$400,000.00
$450,000.00
$500,000.00
Cost
Cash flow Report- in the above diagrams it is clear that the implication of the resource estimation using the management of the works and the implication of the smart management processing. The resource management has been implied
with the consideration for the management of the smart and effective implication development. The most of the resource expenditure has been done in the month of February-March of 2019 and May-June of 2020. The implication would
also be resulted for the management of the activities for taking care of the work related to the implication of the work and forming the management process. The development of the factors and implication of works and it would allow the
calculation of the effective management process. The resource usage has shown the cost estimates and the probable management of the factors aligning the work development and formation of the specific implication. The management has
been implied with the consideration of the resource management and processing. The alignment would be effectively managed with the work developed and aligned with the significant development.
The resources of the project has been non-uniformly distributed across the timeline and work scheduled. The bar graphs have been helpful for aligning with the formation of the works and utilization of the smart project alignment. The non-
uniform deposition of the specific resources over the period of time. The requirement of the works has been diverse and it has resulted in forming the management of the specific work requirements for the users. The different level of
requirements of the factors for aligning the management work development.
Resource management can be implied with the help of the resource distribution and the management of the works and implying the utilization of work for the implication. The confinement of the works with the completeness management
of the resources would be effective. It is possible that the process of refining the resources and distributing the works would be implied successfully. The alignment and the work distribution has been managed with the confinement of the
work developing the implication of the smart project resource management.

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
16PROJECT DRAFT REPORT
1.9 Cash Flow for First 25%
Task Mode WBS Task Name % Complete Duration
Auto
Scheduled 0 Project Apex_first 25 24% 495 days
Auto
Scheduled 1 Preliminaries 99% 85 days
Auto
Scheduled 1.1 Planning 99% 25 days
Auto
Scheduled 1.1.1 Identify mission and Objectives,
Create Project Charter 100% 7 days
Auto
Scheduled 1.1.2 Create Business Plan and Issue 100% 5 days
Auto
Scheduled 1.1.3 Create Project Initiation
Document and Issue 99% 12 days
Auto
Scheduled 1.2 Design 100% 73 days
Auto
Scheduled 1.1 Soil Investigation 100% 3 days
Auto
Scheduled 1.2 Architectural 100% 60 days
Auto
Scheduled 1.2.3 Structural 100% 15 days
Auto
Scheduled 1.2.4 Mechanical 100% 10 days
Auto
Scheduled 1.2.5 Electrical 100% 15 days
Auto
Scheduled 2 Basement and Floors 1 - 9 16% 440 days
Auto
Scheduled 2.1 Earthworks 100% 44 days
Auto
Scheduled 2.1.1 Survey 100% 5 days
Auto
Scheduled 2.1.2 Excavation 100% 10 days
Auto
Scheduled 2.1.3 Groundworks 100% 44 days
Auto
Scheduled 2.1.3.1 Grading 100% 5 days
Auto
Scheduled 2.1.3.2 Water Control 100% 29 days
Auto
Scheduled 2.1.3.3 Erosion control 100% 29 days
Auto 2.1.3.4 Underground utilities 100% 10 days
Document Page
17PROJECT DRAFT REPORT
Scheduled
Auto
Scheduled 2.2 Structures 37% 136 days
Auto
Scheduled 2.2.1 Reinforcements 37% 136 days
Auto
Scheduled 2.2.1.1 Piles (Precast) 100% 14 days
Auto
Scheduled 2.2.1.2 Columns 47% 44 days
Auto
Scheduled 2.2.1.2.1 Columns (Basement - Floor 2) 50% 28 days
Auto
Scheduled 2.2.1.2.2 Columns (Floor 3 - 4) 100% 10 days
Auto
Scheduled 2.2.1.2.3 Columns (Floor 5 - 6) 0% 20 days
Auto
Scheduled 2.2.1.2.4 Columns (Floor 7 - 9) 80% 10 days
Auto
Scheduled 2.3.3 Stairway 100% 8 days
Auto
Scheduled 2.3.3.1 Stairway (Basement - Floor 2) 100% 2 days
Auto
Scheduled 2.3.3.2 Stairway Floor(3 - 4) 100% 2 days
Auto
Scheduled 2.3.3.3 Stairway Floor( 5 -6) 100% 4 days
Auto
Scheduled 2.3.3.4 Stairway Floor( 7 - 8) 100% 4 days
Auto
Scheduled 2.3.4 Patios 100% 1 day
1.10 Cash flow for Last 25%
Task Mode WBS Task Name % Complete
Auto
Scheduled 0 Project Apex_last 25 74%
Auto
Scheduled 1 Preliminaries 99%
Auto
Scheduled 1.1 Planning 99%
Auto
Scheduled 1.1.1 Identify mission and Objectives,
Create Project Charter 100%
Auto 1.1.2 Create Business Plan and Issue 100%
Document Page
18PROJECT DRAFT REPORT
Scheduled
Auto
Scheduled 1.1.3 Create Project Initiation
Document and Issue 99%
Auto
Scheduled 1.2 Design 100%
Auto
Scheduled 1.1 Soil Investigation 100%
Auto
Scheduled 1.2 Architectural 100%
Auto
Scheduled 1.2.3 Structural 100%
Auto
Scheduled 1.2.4 Mechanical 100%
Auto
Scheduled 1.2.5 Electrical 100%
Auto
Scheduled 2 Basement and Floors 1 - 9 75%
Auto
Scheduled 2.1 Earthworks 100%
Auto
Scheduled 2.1.1 Survey 100%
Auto
Scheduled 2.1.2 Excavation 100%
Auto
Scheduled 2.1.3 Groundworks 100%
Auto
Scheduled 2.1.3.1 Grading 100%
Auto
Scheduled 2.1.3.2 Water Control 100%
Auto
Scheduled 2.1.3.3 Erosion control 100%
Auto
Scheduled 2.1.3.4 Underground utilities 100%
Auto
Scheduled 2.2 Structures 100%
Auto
Scheduled 2.2.1 Reinforcements 100%
Auto
Scheduled 2.2.1.1 Piles (Precast) 100%
Auto
Scheduled 2.2.1.2 Columns 100%
Auto
Scheduled 2.2.1.2.1 Columns (Basement - Floor 2) 100%
Auto 2.2.1.2.2 Columns (Floor 3 - 4) 100%

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
19PROJECT DRAFT REPORT
Scheduled
Auto
Scheduled 2.2.1.2.3 Columns (Floor 5 - 6) 100%
Auto
Scheduled 2.2.1.2.4 Columns (Floor 7 - 9) 100%
Auto
Scheduled 2.2.1.3 Slab-Beams 100%
Auto
Scheduled 2.2.1.3.1 Slab -Beams (Basement - Floor
2) 100%
Auto
Scheduled 2.2.1.3.2 Slab-Beams (Floor 3- 4) 100%
Auto
Scheduled 2.2.1.3.3 Slab-Beams (Floor 5 - 6) 100%
Auto
Scheduled 2.2.1.3.4 Slab-Beams (Floor 7 - 9) 100%
Auto
Scheduled 2.2.1.4 Roofing 100%
Auto
Scheduled 2.2.1.4.1 Roofing Trusses 100%
Auto
Scheduled 2.2.1.4.2 Roofing Cover 100%
Auto
Scheduled 2.3 Concrete 100%
Auto
Scheduled 2.3.1 Columns 100%
Auto
Scheduled 2.3.1.1 Columns (Basement - Floor 2) 100%
Auto
Scheduled 2.3.1.2 Columns Floor( 3 - 4) 100%
Auto
Scheduled 2.3.1.3 Columns Floor( 5 - 6) 100%
Auto
Scheduled 2.3.1.4 Columns Floor( 7 - 9) 100%
Auto
Scheduled 2.3.2 Slab-Beams 100%
Auto
Scheduled 2.3.2.1 Slab-Beams (Basement - Floor 2) 100%
Auto
Scheduled 2.3.2.2 Slab-Beams Floor( 3 - 4) 100%
Auto
Scheduled 2.3.2.3 Slab-Beams Floor( 5 - 6) 100%
Auto
Scheduled 2.3.2.4 Slab-Beams Floor( 7 - 8) 100%
Auto 2.3.3 Stairway 100%
Document Page
20PROJECT DRAFT REPORT
Scheduled
Auto
Scheduled 2.3.3.1 Stairway (Basement - Floor 2) 100%
Auto
Scheduled 2.3.3.2 Stairway Floor(3 - 4) 100%
Auto
Scheduled 2.3.3.3 Stairway Floor( 5 -6) 100%
Auto
Scheduled 2.3.3.4 Stairway Floor( 7 - 8) 100%
Auto
Scheduled 2.3.4 Patios 100%
Auto
Scheduled 2.3.4 Blockwall-Masonry 100%
Auto
Scheduled 2.4.1 Bockwall 100%
Auto
Scheduled 2.4.1.1 Internal wall 100%
Auto
Scheduled 2.4.1.2 External wall 100%
Auto
Scheduled 2.4.1.3 Screeding 100%
Auto
Scheduled 2.5 Interior -Finishes 59%
Auto
Scheduled 2.5..5 Partitions 100%
Auto
Scheduled 2.5.1 Dry wall 100%
Auto
Scheduled 2.5.2 Insulation 55%
Auto
Scheduled 2.5.2.1 Interior doors 100%
Auto
Scheduled 2.5.2.2 Windows 100%
Auto
Scheduled 2.5.2.3 Security doors 60%
Auto
Scheduled 2.5.2.4 Tiles 36%
Auto
Scheduled 2.5.2.5 Glazing works 80%
Auto
Scheduled 2.5.2.6 Decoration 0%
Auto
Scheduled 2.5.4 Carpeting 0%
Auto 2.6 MEP systems 100%
Document Page
21PROJECT DRAFT REPORT
Scheduled
Auto
Scheduled 2.6.1 Plumbing 100%
Auto
Scheduled 2.6.1.1 Plumbing systems (Main Line) 100%
Auto
Scheduled 2.6.1.2 Plumbing systems (Floor. 1-2) 100%
Auto
Scheduled 2.6.1.3 Plumbing systems (Floor. 3-4) 100%
Auto
Scheduled 2.6.1.4 Plumbing systems (Floor. 4-6) 100%
Auto
Scheduled 2.6.1.5 Plumbing systems (Floor. 7-9) 100%
Auto
Scheduled 2.6.2 Electrical 100%
Auto
Scheduled 2.6.2.1 Electrical Fixtures (Distribution) 100%
Auto
Scheduled 2.6.2.2 Electrical Fixtures (Floor. 1-2) 100%
Auto
Scheduled 2.6.2.3 Electrical Fixtures (Floor. 3-4) 100%
Auto
Scheduled 2.6.2.4 Electrical Fixtures (Floor. 5-6) 100%
Auto
Scheduled 2.6.2.5 Electrical Fixtures (Floor. 7-9) 100%
Conclusion
The assignment had include the construction works of making sure that the work gas
been implied with the utilization of the successive management works. The alignment had been
helpful for maintaining the works and it would be helpful for aligning the works and improving
the management process.

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
22PROJECT DRAFT REPORT
Bibliography
Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management. Project
Management Institute.
Harrison, F., & Lock, D. (2017). Advanced project management: a structured approach. Routledge.
Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning, scheduling,
and controlling. John Wiley & Sons.
Larson, E. W., Gray, C. F., Danlin, U., Honig, B., & Bacarini, D. (2014). Project management: The
managerial process (Vol. 6). Grandview Heights, OH: McGraw-Hill Education.
Marchewka, J. T. (2014). Information technology project management. John Wiley & Sons.
Nicholas, J. M., & Steyn, H. (2017). Project management for engineering, business and technology.
Routledge.
Verzuh, E. (2015). The fast forward MBA in project management. John Wiley & Sons.
Walker, A. (2015). Project management in construction. John Wiley & Sons.