Project Management for Musical Concert

   

Added on  2022-12-22

14 Pages2919 Words1 Views
Leadership ManagementStatistics and Probability
 | 
 | 
 | 
BM522 Project
Management
1
Project Management for Musical Concert_1

Table of Contents
Introduction......................................................................................................................................3
Main Body.......................................................................................................................................3
Task 1 Network diagram.............................................................................................................3
Task 2 Stakeholder analysis........................................................................................................5
Task 3 Work Breakdown Structure (WBS)................................................................................7
Task 4 Risk Analysis...................................................................................................................9
Task 5 Quality Control..............................................................................................................11
Task 6 Methodologies...............................................................................................................12
References......................................................................................................................................13
2
Project Management for Musical Concert_2

Introduction
This report pertains to undertake management of project to plan a musical concert for the
Camden Sickle Cell and Thalassaemia Service Group. This project aims at raising funds and
spreading awareness about the services, group runs. This project report includes network
diagram and WBS for the other management work required to be undertaken.
Main Body
Task 1 Network diagram
Network diagram is a project management tool which aims to present all activities along
with their sequence and order in the project plan (Marnewick and Marnewick, 2019). It is used to
assess and highlight the relationship between multiple activities embedded in the project plan.
This is a visual presentation tool and makes it easier for the user of the project plan to understand
the project through diagram. Network diagram for the musical concert is as following:
3
Project Management for Musical Concert_3

Illustration 1: Network diagram for Musical concert project
Above network diagram is based on the provided activities chart that have been planned
for the project. It can be seen above that red coloured box represent activity number while the
box on its left represents early start time and on right side, it represents early finish time. Box
below the red box represents activity name and the box on its left represents slack time. First box
in the last line from the left represents late start then box representing duration and finally late
finish time. Based on the above network diagram, critical path for the project has been calculated
below:
4
Project Management for Musical Concert_4

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Project Management for Musical Concert Event
|12
|2297
|62

Project Management for Camden Sickle Cell and Thalassaemia Service Group
|15
|2098
|473

Project Management for Musical Event: Desklib Study Material
|13
|2036
|463

Project Management: Network Diagram, Stakeholder Analysis, WBS, Risk Analysis, Quality Expectation
|12
|2155
|90

Project Management: Stakeholder Analysis, Network Diagram, Work Breakdown Structure, Risk Analysis, Quality Expectation, Agile Methodology
|12
|2222
|32

Project Management for Camden Sickle Cell and Thalassaemia Service Group Music Event
|12
|2397
|350