Undertake Project Work Assessment Task 2

   

Added on  2023-06-11

14 Pages2640 Words75 Views
ASSESSMENT 2
Student
name S <<name of the student>>, (Please Fill) Student ID
<<student
number>>,
(Please Fill)
Unit code
and name BSBPMG522 – Undertake Project work
Assessment Outcome
Satisfactory Not Satisfactory Resubmission Date: 06/27/16
Trainer’s Feedback:
Trainer’s Name: Dadul Bhutia
Trainer’s Signature: Date:
06/27/16
Students please note:
Your results will be made available in your Student Portal. Your Trainer will also email you
with feedback on your performance, including where gaps are identified. Please ensure you
regularly login to your student portal and Stanley College email to check this information. All
decisions, including Assessments Outcomes can be appealed. For more information please
refer to our Complaints and Appeals Policy (available from Student Services team or via our
website).
Document Name: BSBPMG522_Assessment_Task 2 RTO : 51973 CRICOS Code : 03047E
Location: NovaCore CMS\DMS\Academic Drive\Faculty\Business / Management \BSB15\BSB60215 - Advanced Diploma of Business\BSBPMG522
Undertake Project Work\Assessments\
Version: 1.3 Approved on: 10-11-2017 Review Date: 06/27/16 10-11-
2018 Page 1 of 14
Undertake Project Work Assessment Task 2_1
Student Feedback:
Please take the time to provide us with any feedback on your experience during the delivery
and assessment experience by emailing us directly at feedback@stanleycollege.edu.au
Alternatively you can complete the anonymous monthly student feedback survey.
Role and Responsibilities
Role Name Responsibilities Signatures
Project client /
owner
CEO
Max Lionel Outlining project initial
requirements and the approval of
the project
Max Lionel
Project sponsor /
project director /
project board
Operations
General Manager
Kim
Sweeney
Managing the investments in the
project operations
Kim Sweeney
Project manager
Contractor of all
consulting
<<name of
the
student>>,
(Please
Fill)
Managing all the activities of the
project and forming the
successive alignment of the
operation
<<name of the
student>>,
(Please Fill)
Manager of the
project manager
Ace
Consultancy
Assisting the project manager for
their activities and operations
Ace Consultancy
Marketing
Manager
IT Manager
Pat Misfud
Sam Lee
Bringing the increment in the
resource generation of Max
Lionel Realty
Developing the IT infrastructure
needs of the new operations of
the organization
Pat Misfud
Sam Lee
HR Manager
Agents
Les
Goodale
Management of recruitments of
the employees and agents of
Les Goodale
Document Name: BSBPMG522_Assessment_Task 2 RTO : 51973 CRICOS Code : 03047E
Location: NovaCore CMS\DMS\Academic Drive\Faculty\Business / Management \BSB15\BSB60215 - Advanced Diploma of Business\BSBPMG522
Undertake Project Work\Assessments\
Version: 1.3 Approved on: 10-11-2017 Review Date: 06/27/16 10-11-
2018 Page 2 of 14
Undertake Project Work Assessment Task 2_2
Max Lionel Realty
Abiding by the new strategies
and policies of the organization
Project Sponsor:
Kim Sweeney
Version: 1 Project Client: Max Lionel Realty
Project Manager:
<<name of the
student>>
Date:
06/27/16
File Name:
MLR.doc
Page
2 of 20
Status report
25%
Item Work
completed to-
date
Milestone
date
Revised/
actual date
Budgeted
cost
Revised/
actual cost
Responsible
Strategy
Document
85% 07/07/16 07/12/16 $50,000 $55,000 Documenter,
Strategist
Flyers 65% 07/24/16 07/29/16 $20,000 $25,000 Contractor
Posters 25% 08/04/16 08/09/16 $25,068 $30,068 Contractor
PD training
agents
10% 08/16/16 08/21/16 $30,000 $35,000 Trainer
Document Name: BSBPMG522_Assessment_Task 2 RTO : 51973 CRICOS Code : 03047E
Location: NovaCore CMS\DMS\Academic Drive\Faculty\Business / Management \BSB15\BSB60215 - Advanced Diploma of Business\BSBPMG522
Undertake Project Work\Assessments\
Version: 1.3 Approved on: 10-11-2017 Review Date: 06/27/16 10-11-
2018 Page 3 of 14
Undertake Project Work Assessment Task 2_3
Project Sponsor:
Kim Sweeney
Version: 1 Project Client:
Max Lionel Realty
Project Manager: <<name of the
student>>
Date: 06/27/16 File Name:
MLR.doc
Page
3 of 20
50%
Item Work
completed
to-date
Milestone
date
Revised/actual
date
Budgeted
cost
Revised/
actual
cost
Responsible
Strategy
Document
100% 07/07/16 07/12/16 $50,000 $55,000 Documenter,
Strategist
Posters 100% 08/04/16 08/09/16 $25,068 $30,068 Contractor
PD training
agents
95% 08/16/16 08/21/16 $30,000 $35,000 Trainer
Website 75% 08/18/16 08/20/16 $37,500 $39,500 Website
Developer
Research on
ethical / legal
requirements of
REINSW
35% 09/15/16 09/17/16 $15,500 $17,500 Researcher
Conduct a
training program
to inform agents
of legal and
ethical
obligations
25% 09/26/16 09/28/16 $32,500 $34,500 Trainer
Prepare
communication
documents
15% 10/04/16 10/06/16 $4,500 $6,500 Documenter
Distribution of
communication
materials
12% 10/13/16 10/20/16 $6,500 $8,500 Project
Manager
Finance of overall
project
02% 10/31/16 11/02/16 $300,500 $302,000 Project
Client
Project Sponsor:
Kim Sweeney
Version: 1 Project Client:
Max Lionel Realty
Project Manager: <<name of the
student>>
Date: 08/16/16 File
Name:
Page: 5 of 20
Document Name: BSBPMG522_Assessment_Task 2 RTO : 51973 CRICOS Code : 03047E
Location: NovaCore CMS\DMS\Academic Drive\Faculty\Business / Management \BSB15\BSB60215 - Advanced Diploma of Business\BSBPMG522
Undertake Project Work\Assessments\
Version: 1.3 Approved on: 10-11-2017 Review Date: 06/27/16 10-11-
2018 Page 4 of 14
Undertake Project Work Assessment Task 2_4

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Max Lionel Realty Project: Purpose, Scope, Stakeholders, and Plan
|29
|5849
|313

BSBPMG522 Undertake Project Work - Doc
|22
|3423
|33

Max Lionel reality case study
|10
|1399
|34

Assignment (doc) on Project Business Management
|9
|1199
|13

BSBMKG515 Conduct A Marketing Audit Assessment 2022
|31
|8083
|26

Manage Physical Assets Assessment Task 1 - Australian Ideal College
|16
|4931
|228