This document provides a project plan for BSBPMG522 Undertake Project Work, including a work breakdown structure, Gantt chart, roles and responsibilities, and approval process.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
BSBPMG522 Undertake project work Project Plan v2.0 (2017/09/04) Name Email address Project Plan Task No.Phases/Task/MilestonesDuration (in days) Start Date(based on elapsed) Finish Date(based on elapsed)Sequence/PredecessorsResources 1Start of the project0Fri 17-05-19Fri 17-05-19<Task no. of the task preceding this one> <Human resource required and any major non-human resources> 2Initial planning and requirement gathering 25Fri 17-05-19Thu 20-06-19 2.1Defining the requirements2Fri 17-05-19Mon 20-05-191Business Partners 2.2Analysis over the present network layout 8Tue 21-05-19Thu 30-05-193Project Manager 2.3Preparing a project and financial plan 15Fri 31-05-19Thu 20-06-193,4Finance Manager 2.4Completion of the phase0Thu 20-06-19Thu 20-06-195 3Procurement phase5Fri 21-06-19Thu 27-06-19 3.1Contacting the network service provider 2Fri 21-06-19Mon 24-06-196Administrative staff 3.2Purchasing of the network equipment 3Tue 25-06-19Thu 27-06-198LAN Cables, Servers, Routers 3.3Completion of the phase0Thu 27-06-19Thu 27-06-199 1
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
BSBPMG522 Undertake project work Project Plan v2.0 (2017/09/04) Task No.Phases/Task/MilestonesDuration (in days) Start Date(based on elapsed) Finish Date(based on elapsed)Sequence/PredecessorsResources 4Implementation of the network27Fri 28-06-19Mon 05-08-19 4.1Designing the network plan4Fri 28-06-19Wed 03-07-1910Network Service Provider, Project Manager 4.2Work over the network plan23Thu 04-07-19Mon 05-08-1912Network Service Provider, Project Manager 4.3Completion of the phase0Mon 05-08-19Mon 05-08-1913 5Project closure phase4Tue 06-08-19Fri 09-08-19 5.1Project sign-off1Tue 06-08-19Tue 06-08-1914 5.2Payment to the stakeholders1Wed 07-08-19Wed 07-08-1916 5.3Collecting the invoices2Thu 08-08-19Fri 09-08-1917 5.4Completion of the phase0Fri 09-08-19Fri 09-08-1918 6End of project0Fri 09-08-19Fri 09-08-1919 2
BSBPMG522 Undertake project work Project Plan v2.0 (2017/09/04) Risk Register Risk No.Risk DescriptionRisk PriorityRisk Mitigation Strategy 1.The project might exceed the estimated plan for the budget 4Avoid – The financial plan for the project should be prepared during the design of the project plan. 2.The project plan might be affecting the present work over the departments 5Mitigate – The entire plan of the project should be prepared 3.The project might get delayed due to delay in the work of procurement of networking items 4Avoid – The project manager should prepare for the procurement of items immediately after the financial plan has been approved. 3
BSBPMG522 Undertake project work Project Plan v2.0 (2017/09/04) Project Budget CategoryItemQuantity/ Number of hoursCost per item or per hourTotal cost WorkBusiness Partners16 hrs WorkAdministration staff16 hrs$ 140$ 2240 WorkFinance Manager120 hrs$ 150$ 39,600 WorkProject Manager64 hrs$ 180$ 11,520 WorkNetwork Service Provider216 hrs$ 120$ 31,680 MaterialLAN Cables40$ 4000$ 4000 MaterialRouters10$ 5000$ 5000 MaterialServers5$ 4500$ 4500 Total:$ 98,540 Project Carefully review the material presented in this unit and the activities you have previously completed. You should reflect on your learning, your own research, and your previous case studies within this unit. Complete the following project tasks, and submit all of the required documentation. Case Study You work for a small business with eight staff members. Here is the employee breakdown of the business: Two business partners, who own the business Three administration staff 4
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
BSBPMG522 Undertake project work Project Plan v2.0 (2017/09/04) One finance manager Two sales staff, who mostly work remotely The business has started to grow. The projection is that, over the next 12 months, there will be an additional three staff members employed, one of whom will be another member for the sales team. It has been found that the computer network is not adequate. You have been appointed as Project Manager to manage the purchase and implementation of a new computer network. It has been decided that all computer equipment will be replaced. You have been given a total project budget of $100,000. You will need to coordinate the implementation to ensure that there is no interruption to the normal day to day operations of the business. Task 1 You have completed the project scope plan as part of your case study assessment in this unit. Develop a project plan. Attached is a project plan template that you may wish to use. Alternatively, you can use one from your workplace. You should ensure that your project plan adheres to the following steps. Step 1- You need to consult with the project team when planning the project. List four aspects on which you would consult the project team about, including whom you would consult. Step 2- What legislation will you need to be aware of when undertaking the project? Give two examples. Step 3- Create a project plan, with a schedule, budget, and risks. You will need to provide: Work breakdown structure A Gantt chart (there are many free Gantt chart tools on the Internet, or you may hand draw it) The roles and responsibilities of the project team, including your own Step 4- Explain how you would obtain approval of your project plan and from whom. 5
BSBPMG522 Undertake project work Project Plan v2.0 (2017/09/04) Task 2 Work through the following steps involved in administering and monitoring the project. Step 1- To maintain and improve the progress of the project, all stakeholders must be aware of their responsibilities and the tasks assigned to them. Discuss how you will ensure that this occurs. Step 2- List two concerns of the project team in this phase of the project and your plans to address these concerns. One concern should be with respect to achieving timelines and the other with respect to achieving quality. Step 3- To reduce the risk of the project going overtime or over budget due to unforeseen problems, you design the project control processes. In these processes, you need to include the relevant stakeholders and what they need to do at each step as well as include the required record keeping for managing/executing the project for the following: Scope, which includes how you stay in scope as well as what happens if the client requests a change to scope Time Finances Resources, both human and non-human Quality (you can use the quality report template provided) Risks Step 4- Provide a status report to keep your stakeholders informed of the project’s progress. You can use the status report template provided or one from your workplace. Task 3 The project is in the final stages. Complete the finalisation and review process for the project by adhering to the following steps. Step 1- Consider what financial documentation you need to complete and what financial records will be important to archive. Complete the financial records for this project. Step 2- Now that the project is complete, the human resources division has requested that you explain the process that you will take in order to reassign your human resources. Step 3- Explain how you will obtain client/stakeholder acceptance that the project is complete. 6
BSBPMG522 Undertake project work Project Plan v2.0 (2017/09/04) Step 4- Create a project checklist that allows you to verify the actual project outcomes achieved against the outcomes as stated in the project scope and project plan. When the form is created, complete it. Would your project be considered successful? Step 5- You have decided to involve the project team members in the project review process. Who should be involved? What input might they be able to provide? How will you involve them? Step 6 - What lessons have you learnt over the course of this project? Identify four key lessons, and suggest how you would change your approach to your next project. You can use the Lessons Learnt template or one from your workplace. 7